CITY OF VANCOUVER

ADMINISTRATIVE REPORT

 

Date:

April 7, 2004

 

Author:

Brian Emlyn

 

Phone No.:

7389

 

RTS No.:

4152

 

CC File No.:

1805

 

Meeting Date:

April 20, 2004

TO:

Vancouver City Council

FROM:

General Manager of Engineering Services

SUBJECT:

Tender No. 2004 - 01: Construction of Concrete Curbs and Gutters and Asphaltic Concrete Pavement on Sundry Streets

RECOMMENDATION

COUNCIL POLICY

Construction contracts over $300,000 are to be awarded by Council.

PURPOSE

The purpose of this report is to obtain Council approval to award Tender No. 2004-01 for the construction of curbs and gutters and pavements on sundry streets

BACKGROUND

The street projects forming this report were approved at the Local Improvement Court of Revision on February 11th, 2004.

DISCUSSION

Tenders for the construction of Concrete Curbs and Gutters and Asphaltic Concrete Pavement on Sundry Streets (Tender No. 2004-01) were opened on March 14th, 2004 and referred to the General Manager of Engineering Services for tabulation.

All tenders were checked for completeness and accuracy and any miscalculations or omissions corrected. Tabulations of the amount bid, with the lowest bid underlined, are shown below:

Contractor=s Bids (Summary of Schedule 2): Bids are inclusive of all Taxes;

Columbia Bitulithic Ltd. $1, 470, 896.79
Imperial Paving Ltd $1,500, 140. 00
Jack Cewe Ltd. $1,520, 791. 00
Winvan Paving Ltd. $1,575, 545. 58

FINANCIAL IMPLICATIONS

The Engineer's Estimate for this contract was $1, 200, 000. 00. Noting that the construction industry has become increasingly busy it is believed that the low bid, as well as the other submissions are consistent with reports from outside agencies which indicate increases in construction costs. Based on this latest information the low bid is considered reasonable. The total estimated cost for construction of the streets in this tender is $ 2, 200, 000. 00, this estimated cost not only contains the contracted street work but also provision for sewer, waterworks, electrical and utility adjustments, catch basin adjustments, and unanticipated extra work. Funding for the City=s share of this work has been approved by Council as part of the Local Improvement approval process.

CONCLUSION

The low bid is balanced and consistent with the trend of contract unit price bids. Although higher than the Engineers estimate the low bid reflects the current busy state of the construction industry. The General Manager of Engineering Services recommends that Contact 2004-01 be awarded to Columbia Bitulithic Ltd.

* * * * *


ag20040420.htm