ADMINISTRATIVE REPORT
Date: June 20, 2002
Author/Local: P. Bremner/6720
RTS No. 02820
CC File No. 1805
Council: July 9, 2002
TO:
Vancouver City Council
FROM:
General Manager of Engineering Services
SUBJECT:
New Chess Street Works Yard Award of Contract
Piling and EarthworksRECOMMENDATION
A. THAT Council approve award of Contract No. 0202350A02PTCC for Piling to the low tenderer, Griffith Pile Driving Ltd., in the amount of $855,741.00, with funding provided from Yards Basic Capital Account Number 30003133.
B. THAT Council approve award of Contract No. 0202200A01PTCC for Earthworks to the low tenderer, Con West Contractors Ltd., in the amount of $1,344,376.30, with funding provided from Yards Basic Capital Account Number 30003133.
C. THAT the General Manager of Engineering Services be authorized to execute and deliver Notices of Award on behalf of the City, and the Director of Legal Services be authorized to execute and deliver contracts No.0202350A02PTCC and No.0202200A01PTCC on behalf of the City.
D. THAT no legal rights or obligations will be created or arise by Council's approval of Recommendations A and B unless and until a Notice of Award is executed and delivered by the City to Griffith Pile Driving Ltd. and Con West Contractors Ltd.
GENERAL MANAGER'S COMMENTS
The General Manager of Engineering Services RECOMMENDS approval of the foregoing.
COUNCIL POLICY
Construction contracts more than $300,000 are to be awarded by Council.
PURPOSE
This report seeks authorization to award construction contracts for Piling and Earthworks for the New Chess Street Yard.
BACKGROUND
· Development of the New Chess Works Yard is part of the 2000 - 2002 Capital Plan.
· On July 31, 2001, Council approved awarding the design and construction management contract for the yard to Omicron Consulting Group.
· On November 20, 2001, Council approved implementing LEEDTM sustainable practices into the two main buildings in the yard.
· Construction management is being used for the works yard development which involves sequential tendering for the main building components.DISCUSSION
This report recommends approval of Piling and Earthworks contracts. The first of a number of construction contracts for the new works yard. From a public invitation for expression of interest for prequalifications, five contractors were prequalified for Piling and eight contractors were prequalified for Earthworks. The following complete tenders were received (including GST):
Piling
Contract No. 0202350A02PTCC
Griffiths Pile Driving Inc.
$855,741.00
Agra Foundations Limited
$897,150.00
West Shore Constructors Limited
$969,017.62
Vancouver Pile Driving Ltd.
$999,602.50
Fraser River Pile & Dredge Ltd.
$1,089,750.00
The engineer's estimate for this work is $903,741. The low bid is below the engineer's estimate and fits within the overall budget for the project. On the basis of best value, it is recommended that the Piling contract be awarded to Griffiths Pile Driving Inc., the lowbidder, in the amount of $855,741.00 including GST.
Earthworks
Contract No. 0202200A01PTCC
Con West Contracting Ltd.
$1,344,376.30
Gemco Construction Ltd.
$1,703,232.90
Southwest Contracting Ltd.
$2,158,038.54
The engineer's estimate for this work is $1,705,958. The low bid is below the engineer's estimate and fits within the overall budget for the project. On the basis of best value, it is recommended that the Earthworks contract be awarded to Con West Contracting Ltd., the low bidder, in the amount of $1,344,376.30 including GST.
All tenderers have been notified of these recommendations.
FINANCIAL IMPLICATIONS
The overall budget approved for this project is $21.884 million. When last reported to Council, there was a funding shortfall of approximately $800,000. These tenders are below estimate and are helpful in making up the shortfall. Through the balance of the tendering, adjustments will be made to address this shortfall. Funding for the project is approved in the 2000 - 2002 Capital Plan and Capital Financing Fund Loans. Funding for these tenders which totals $2,200,117.30 is available in Yards Basic Capital account no. 30003133.
SUSTAINABILITY
Contracts covered by these tenders incorporate a number of sustainable features. The steel piles will contain 80% recycled material and the piles will be filled with concrete containing 60% flyash. Typical flyash content is in the 15 to 25% range due to restraints on cure times. In this case, because the cure time in the concrete piles is not critical, the percentage of flyash can be maximized.
The Earthwork contract includes construction of a sediment pond to control stormwater runoff from the site during construction. A truck wheel wash will also be put in place to control material tracked out onto the street. Earth excavated from the site will be used as fill material on the boulevard and industrial sites to keep it from being dumped into a landfill. Asphalt grindings from city streets will be used in place of importing gravels for the site.
* * * * *
(c) 1998 City of Vancouver