   RECOMMENDATION

        THAT the application by Greystone Properties Ltd. to rezone 5104-56
        Joyce Street  (Lots A, R, 5 and 6, Block  158, D.L. 37, Plans 2750,
        20906,  LMP   24057)  from   C-2C  Commercial   District  to   CD-1
        Comprehensive Development District be referred to a Public Hearing,
        together with:

        i)   revised plans received January 25, 1996;
        ii)  draft  by-law provisions generally as contained in Appendix A;
             and
        iii) the recommendation of the Director of Land Use and Development
             to  approve the application, subject to conditions of approval
             contained in Appendix B.

        FURTHER  THAT  the  Director  of Legal  Services  be  instructed to
        prepare  the  necessary  by-laws for  consideration  at  the Public
        Hearing, including  a consequential amendment to the Sign By-law to
        establish  sign  regulations  for  this  CD-1  in  accordance  with
        Schedule B (C-2C).


   GENERAL MANAGER'S COMMENTS

        The  General Manager of  Community Services RECOMMENDS  approval of
        the foregoing.


   COUNCIL POLICY

   Relevant Council policies for the site include: 

   -    Joyce Station Area Plan, approved by City  Council on May 20, 1987;
        and

   -    CD-1 By-law No. 7204 and Joyce/Vanness Guidelines for the adjoining
        Collingwood Village development.PURPOSE AND SUMMARY

   This report assesses a CD-1 rezoning application for  a site situated on
   the westerly boundary  of the Collingwood Village  development, adjacent
   to  the  Joyce  Street  SkyTrain  station.    Proposed  is  a  16-storey
   residential tower above a commercial podium which includes space for the
   Joyce Street  Community  Crime Prevention  Office.   The proposed  floor
   space ratio  and height cannot  be accommodated under the  existing C-2C
   Commercial   zoning.     A  more   detailed  description  of   the  site
   circumstances is outlined in Appendix C.

   Analysis  of  the  application  by  Planning  and  Real Estate  Services
   indicates that  the  proposal  is  marginally  feasible  from  a  market
   perspective,  and that  the  resultant  development  maintains  a  scale
   consistent with the adjoining Collingwood Village.  Staff recommend that

   the application be referred to Public Hearing.

                                      MAP




























   DISCUSSION

   Crime Prevention Office:  The Joyce Community Crime Prevention Office is
   presently  located in  an existing  storefront on  the property,  and is
   operated  and  staffed  by  a  non-profit  society  with  a  substantial
   community base.   The proposal is to  provide ground-level space in  the
   new  development  for  the  continuation  of this  office.    The  Crime
   Prevention  Office is expected  to be sustainable  in the long  term, in
   part because of:

   -    the  proposed  endowment  fund  ($35,000  rezoning  condition)  for
        ongoing operations;
   -    the  interest  of   and  partnership  with  the   Vancouver  Police
        Department,   who  utilize  the  office  for  report  writing,  and
        impromptu  and formal meetings with individuals and groups from the
        community; and
   -    the strong community support for the office  and its service to the
        local area.

   No  contingency strategy  for alternate  community use of  this proposed
   City-owned  space is  therefore recommended  at this  time.   Should the
   question  of alternate  use  of  the space  arise  in  the future,  City
   departments will need to work with the community to identify appropriate
   uses and a report to Council may be needed before any decision is made.

   Density  and Height:   While  both density  and height  are considerably
   higher  than  would  normally  be  considered  appropriate  for  a  C-2C
   neighbourhood  shopping district  such as this,  the massing  concept is
   compatible with this unique context.   The four storey commercial podium
   relates well to what will  likely occur on immediately adjoining parcels
   on Joyce Street  under the existing  C-2C zoning (one  of which is  also
   owned  by the  applicant), while  the  residential tower  fits with  the
   heights  of  towers  in  the  Collingwood Village  to  the  east.    The
   additional  density and  height  proposed  are a  direct  bonus for  the
   provision  of the  crime prevention office  and would  not be seen  as a

   precedent for similar proposals on other C-2C sites in the area.

   Height and Views:   The rezoning will represent a  significant change to
   the  development  pattern  which  could occur  under  the  existing C-2C
   zoning,  which effectively  limits  height to  10.7  m  (35 ft.).    The
   proposed  16-storey and 47.9  m (157 ft.)  height will limit  some views
   toward the Downtown for residents in adjoining residential towers within
   the  Collingwood  Village  development.    Staff have  spoken  with  one
   resident  and  have  received  a  letter  with  36  listed  names,  both
   expressing opposition to  the proposal because of view  blockage.Form of
   Development:   The Urban Design  Panel reviewed this application  on two
   occasions, on October 25, 1995  and on January 31, 1996 (after revisions
   were made).   The residential tower  was moved to the  north end of  the
   site, allowing for creation of a  significant roof amenity area over the
   commercial podium and greater identity for the entrance.  The commercial
   podium  relates  better   both  to  the  street   and  adjoining  future
   development.   In  general, the  Panel felt  the project  had progressed
   sufficiently to warrant support.

   The  Urban  Design  Panel  still   has  concerns  with  respect  to  the
   residential tower (see Appendix D for detailed Panel comments):

   -    towers  in  the  Collingwood  Village  (and  this  project)  appear
        overbearing because of the uniformity of floorplates; and

   -    an  increase  in height  from  16 to  20 storeys,  combined  with a
        smaller  floorplate, could  reduce  this  effect  and  improve  the
        building's relationship to the street.

   Staff  share the  concern  of  the Urban  Design  Panel regarding  tower
   appearance  in the  area.   Additional  height does  not have  community
   support and staff would  be reluctant to pursue such an  idea without an
   overall review of the Collingwood  Village zoning and guidelines.  Staff
   therefore  do  not   support  additional  height,  but   recommend  that
   modifications  to  the tower's  appearance  be made  at  the development
   application  stage.    Changes  could  include  the  minor variation  of
   building elements and  materials to produce a greater  vertical emphasis
   to the tower.

   Financial Evaluation of the Density Bonus:  The Real Estate Division has
   reviewed  the economic  viability of  the proposal  and states  that the
   proposed  development   is  marginally  feasible  under  current  market
   conditions.  Staff recommend conditions of the rezoning approval related
   to securing of the space for the crime prevention office  (see Condition
   [C], Appendix B).

   CONCLUSION

   Planning  staff support the  proposed rezoning  of 5104-56  Joyce Street
   from C-2C to  CD-1 for a  high-density mixed-use development,  including
   provision for  a City-owned  139.4 m›  (1,500 sq.  ft.) Community  Crime
   Prevention Office.   It is recommended that the  application be referred
   to  a Public  Hearing, subject  to the  proposed conditions  of approval
   presented in Appendix B.

                                     * * *
                                                                 Appendix A
                                                                Page 1 of 1

                    OUTLINE OF DRAFT CD-1 BY-LAW PROVISIONS
                    _______________________________________


   Use
                -  Dwelling Units;
                -  Cultural and Recreational  Uses, except  for Arcade  and

                   Billiard Hall;
                -  Institutional  uses,  except for  Detoxification  Centre
                   and Hospital;
                -  Office Uses;
                -  Retail Uses,  except for  Adult  Retail Store,  Gasoline
                   Station  -  Full Service  or  Gasoline  Station -  Split
                   island and Vehicle Dealer;
                -  Service   Uses,   except  for   Cabaret,   Drive-through
                   Service,  Funeral Home,  Motor Vehicle  Repair Shop  and
                   Motor Vehicle Wash; and
                -  Accessory Uses customarily ancillary to the above uses.

   Density

                -  Maximum floor space ratio of 5.6. 


   Maximum Height

                -  47.9 m (157 ft.)


   Parking

                -  As  required   in  the   Parking  By-law,  except   that
                   residential parking is  to be provided  at a minimum  of
                   one space per dwelling unit plus  one space for each 200
                   m› of gross floor area.


   Loading

                -  As  required  in the  Parking  By-law,  except that  one
                   additional  loading  bay   is  required  for  each   200
                   dwelling units.


   Bicycle

                -  Bicycle parking  is to  be provided  as required  in the
                   Parking By-law.                               APPENDIX B
                                                                Page 1 of 2


                        PROPOSED CONDITIONS OF APPROVAL
                       ________________________________


   (a)    That the proposed form  of development be approved by Council  in
          principle,   generally  as  prepared  by  Musson  Cattell  Mackey
          Partnership  and  stamped  "Received  City  Planning  Department,
          January 25,  1996", provided  that the Director  of Planning  may
          allow  minor  alterations  to   this  form  of  development  when
          approving the detailed  scheme of development  as outlined in (b)
          below.

   (b)    That, prior  to approval by Council  of the form of  development,
          the applicant shall obtain  approval of a development application
          by the Director of Planning, who shall have  particular regard to
          the following:

          (i)    further design development  to the tower to  provide for a
                 slimmer appearance, such design review not to include  any
                 consideration of additional height;

          (ii)   design  details  to incorporate  crime prevention  through

                 environmental design (CPTED) principles (refer to Appendix
                 D - Police Department comments);

          (iii)  provision   of   recycling/garbage   facilities   to   the
                 satisfaction of Engineering Services;

          (iv)   submission of a detailed landscape plan;

          (v)    provision  of  street  trees  to the  satisfaction  of the
                 Vancouver  Park   Board  and   the  General   Manager   of
                 Engineering Services; and

          (vi)   submission of an  acoustical consultant's report assessing
                 noise  impacts   on  the   site  and  recommending   noise
                 mitigation measures to achieve noise criteria.

   (c)    That,  prior  to enactment  of  the CD-1  By-law, the  registered
          owner shall, at no cost to the City:

          (i)    execute agreements to the satisfaction of the Director  of
                 Legal Services pertaining to the proposed Crime Prevention
                 Office as follows:
                                                                 APPENDIX B
                                                                Page 2 of 2



          -      Greystone will  turn over to  the City free  of charge the
                 designated  grade-level  retail  unit  situated  on  Joyce
                 Avenue, near Vanness (with  a minimum floor area of 139.35
                 m
                                   2 (1,500 sq.  ft.) as noted on drawings dated  January 25,
                 1996, together with three parking stalls, with legal title
                 satisfactory to the Director of Legal Services;

          -      Greystone will install improvements   of not less than $25
                 per sq. ft. (1995 dollar) of construction cost; details of
                 the improvements to be worked out later;

          -      Greystone will pay to the City a cash sum of $35,000 (1995
                 dollar)  to be  used towards  the operation  of  the Crime
                 Prevention Office;

          -      Greystone will reimburse the City any GST cost incurred in
                 the above transactions; and

          -      the   above-mentioned  amounts   should   be   indexed  to
                 inflation.

          (ii)   execute an agreement, to the satisfaction of the  Director
                 of  Legal Services, to  not discriminate  against families
                 with children in the sale of residential units;

          (iii)  consolidate the site; and

          (iv)   make suitable  arrangements, to  the  satisfaction of  the
                 Engineering Services, for any new electrical and telephone
                 services  to be  undergrounded within and adjacent  to the
                 site from the closest, existing suitable service point.

                                                                 APPENDIX C
                                                                Page 1 of 2


             SITE , SURROUNDING DEVELOPMENT, PROPOSED DEVELOPMENT 
                            AND NON-MAJOR ELEMENTS


   Site

   This  0.20 ha  (0.5 ac.)  site  comprises four  parcels of  land  at the
   southeast  corner of  Vanness Avenue  and Joyce  Street.   The northerly
   three parcels are vacant, with the remaining parcel accommodating a two-
   storey building,  which provides  a temporary  storefront for  the Joyce
   Community Crime Prevention Office.   The site slopes about 1.5  to 2.1 m
   (5  to 7 ft.) from  north to south.  Secondary  access is available from
   the existing lane.   No trees exist  on the site or  within the sidewalk
   allowance.

   The site was  rezoned from  C-1 to C-2C  as part of  the original  Joyce
   Station Area  Plan in  June, 1988.   Greystone Properties,  formerly the
   Vancouver Land  Corporation (VLC), had  originally included the  site as
   part of  their planning  for Collingwood Village,  but deleted  the site
   because  it was  not under  their  control (either  owned or  optioned).
   Greystone has subsequently managed to purchase the site.

   Surrounding Development

   To  the north  of the  site  is the  Joyce Street  Skytrain  Station and
   elevated  guideway.    Immediately  to  the  south  are  two,  low-scale
   commercial buildings,  which occupy the  remainder of the  block between
   Vanness Avenue and Crowley Drive.  Further south along Joyce Street is a
   newer  20-storey  residential rental  building  with a  small  amount of
   retail  use at  grade,  and the  new  Collingwood Village  Neighbourhood
   House, gymnasium  and child day care facility.   To the east, across the
   existing lane, is the Phase I enclave of Collingwood Village, consisting
   of a mix of low-rise (4  to 6-storeys) and three high-rise (20  storeys)
   residential developments.   To the  west, across Joyce Street,  are one-
   and two-storey commercial buildings, the recently constructed St. Mary's
   Roman  Catholic  Church  and  the  11-storey  Columbus  Tower  apartment
   building.   Three high-rise  buildings of 12-,  13- and  14-storeys have
   been  recently  developed west  of Joyce  Street, immediately  north and
   south of the Skytrain Station.
                                                                 APPENDIX C
                                                                Page 2 of 2

   Proposed Development

   The proposed 16-storey development consists of:

   -      685.4 m› (7,378 sq. ft.) of ground floor retail use and  139.4 m›
          (1,500 sq.  ft.) of  ground floor  area for  the Joyce  Community
          Crime Prevention Office;
   -      2  723.5 m› (29,316  sq. ft.) of office  use on the second, third
          and fourth floors; and
   -      114 dwelling units on the first to sixteenth floors.

   The residential units comprise studio, one-bedroom, one-bedroom and den,
   two-bedroom units  and a single  three-bedroom unit.   On-site amenities
   include a 74.3 m› (800 sq. ft.) amenity room at grade with direct access
   to a semi-private landscaped open area, together with  semi-private roof
   deck areas  at the fourth floor level.   Pedestrian access to the retail
   and  office uses is from  Joyce Street, while  access to the residential
   tower is from  Vanness Street.  Vehicular  access to three  and one-half
   levels of  underground parking is  from the  existing lane (See  Plans -
   Appendix E; Statistics - Appendix F).

   Non-Major Elements

   Use:   The  Joyce Station Area  Plan called  for zoning of  this site to
   provide for  a mix of retail, office and  residential use.  The proposal
   is consistent with that intent.

   Parking  and  Loading:   The  proposed  development  will provide  motor
   vehicle parking  and loading  spaces, and  bicycle space, in  accordance
   with Parking By-law standards.

   Trees and  Landscaping:  Street  trees are proposed within  the existing
   sidewalk  allowance along  Joyce Street  and Vanness Avenue,  subject to
   Park Board  and Engineering approvals.   Additional plant  materials are
   proposed for the development's semi-private garden  and roof deck areas.
   Staff recommend a detailed landscape  plan as a condition of development
   application approval [see condition (b)(v) of Appendix B].

   Social and Environmental Implications

   With the exception of the positive benefits of a permanent space for the
   Joyce Community Crime Prevention Office,  there are no major positive or
   negative social or  environmental implications to this  proposal.  There
   are no implications  with respect to the Vancouver  Children's Policy or
   Statement of Children's Entitlements.                         APPENDIX D
                                                                Page 1 of 6

                        COMMENTS OF REVIEWING AGENCIES

   Notification

   Signs erected on site:                  October 6, 1995

   699 early notification                  October 13, 1995
   letters mailed out:
                    
   Public Comments

   Greystone has worked  closely with residents of the  Joyce Station area,
   and the inclusion of space for the crime prevention office has long been
   supported by the community.

   During the processing of this application, staff received  two telephone
   calls (one  in favour/one not in favour) and  a counter enquiry from one
   individual  expressing concern  about private  view loss  from  a nearby
   high-rise residential development.  In addition, staff received a letter
   with  36 names  listed  (without  signatures  or  addresses)  expressing
   opposition to the proposal and concerns about the number of existing low
   and highrise  towers in the  community, as well  as those planned  to be
   constructed in the larger Collingwood Village development.

   On November  2, 1995  the applicant held  a public  information meeting,
   which  about 40  persons attended.    Most individuals  expressed strong
   support for the  proposed rezoning and the need for  the Joyce Community
   Crime Prevention  Office to be  located in this  particular development.
   Some  concerns were expressed  about parking and  traffic circulation in
   the immediate vicinity of the site.

   Reviewing Agency Comments

   Engineering Services:   "Engineering Services  has no  objection to  the
   proposed rezoning provided the following concerns are addressed prior to
   by-law enactment:

   1.     Consolidation of Lot R, Plan 20906, Lot "A", Plan  LMP 24057, Lot
          5,  Except Part in Explanatory  Plan 13036 and Lot 6, Except Part
          in Plan LMP 19693, All of Block  158, District Lot 37, Group One,
          New Westminster District.

   2.     Parking  is to be  provided at a  minimum of  one space  per unit
          plus one space for each 200 m› of gross floor area.

   3.     Commercial loading is to  be provided as per the Parking  By-law;

          and one additional loading bay is required for  each 200 dwelling
          units.
                                                                 APPENDIX D
                                                                Page 2 of 6


          Note: the  current proposal is deficient  in both commercial  and
          residential loading bays.

   4.     Bicycle parking is to be provided as per the Parking By-law.

   5.     Provision of a separated loading access from the parking access.

          Note: the parking numbers  are too high to permit trucks  backing
          through the parking access to the loading docks.

   6.     Undergrounding  of   all  utilities  from  the  closest  existing
          suitable pole.

   7.     Provision of street trees  to the satisfaction  of the  Vancouver
          Park Board and the General Manager of Engineering Services."

   Department of Permits and Licenses:  The Environmental Protection Branch
   advises that an assessment for soil contamination is not required.

   Vancouver  Health  Board:   The  Director  of  Environmental Health  has
   reviewed this rezoning application and provides the following comments:

   "1.    The City's Acoustical criteria shall form part of  the Zoning By-
          law, and  an Acoustical  Consultant's  report  shall be  required
          which assesses  noise impacts  on the  site and recommends  noise
          mitigating measures.

   2.     The Noise Control By-law requires amendment at time  of enactment
          of  Zoning By-law to include this CD-1 or  new zoning district in
          Schedule B."

   Police Department:   The  Police Department  has reviewed this  rezoning
   application and provides the following comments:

   "The revised submission is significantly improved and has addressed many
   of  the issues  identified  in the  earlier CPTED  review.   The  design
   showing separation of the commercial and residential is considered to be
   positive.  Further improvements required include:

   -      Design development to delete  door from commercial to residential
          lobby on ground floor.
                                                                 APPENDIX D
                                                                Page 3 of 6
   -      Provide clarification of stair located at the lane loading area.

          Note to Applicant:  An  open exit stair is  this location will be
          vulnerable  to  mischief,  create  fear  and  will  provide  non-
          legitimate access to underground parking.

   -      Design development to reduce opportunities for break and enter.

          Note  to Applicant:   The  ground level  units  facing this  well
          travelled  lane  will  be   vulnerable  to  break-in  and  entry.
          Additional  target  hardening such  as  security  systems,  small
          paned  windows,  fully  secured  doors  (preferably  not  sliding
          doors) should be considered  for these units.  Design of  outdoor
          areas  adjacent   to  these   units   should   reduce  areas   of
          concealment."
    
   Urban Design Panel

   On  January 31,  1995,  the  Urban Design  Panel  reviewed the  proposed
   rezoning and offered the following comments:

   "Evaluation:  Support (8-2)

   -      Introduction:    The Rezoning  Planner,  Rob Whitlock,  presented
          this  rezoning  application,  describing  the  proposal  and  its
          immediate context.  The  proposal was not supported by the  Panel
          when it was reviewed in October 1995.  Mr.  Whitlock reviewed the
          concerns raised  previously by the Panel.   He noted the  project
          has seen considerable improvement  since that time, and described
          the  current scheme.   In  addition to  overall  comments on  the
          revised scheme,  the Panel's advice  is sought on the residential
          entrance treatment, the Joyce Street  elevation, and whether  the
          revised scheme  is now  successful as  a  gateway to  Collingwood
          Village.

   -      Applicant's  Opening Comments:    Brian McCauley  explained  that
          Greystone  has now  purchased  the last  lot  on the  block,  and
          negotiations are continuing with  the owners of  the centre  lot.
          If Greystone  succeeds in acquiring both  lots it would be  their
          intention  to proceed with an application under the existing C-2C
          zoning which  permits retail at grade  with two floors of  office
          above, at  2.0. FSR.   Combined with  the subject proposal,  this
          would bring the overall FSR for the block  to about 4.4 FSR.   He
          noted  they  have  been  working  with  the  Joyce  Station  Area
          Planning Committee which  supports the revised  scheme as well as
          the  relocation  of  the  Crime  Prevention  Office  from Vanness
          Avenue  to  Joyce  Street.   At  grade  amenity  space  has  been
          introduced  at the  sixth  floor which  opens onto  a  landscaped
          podium.
                                                                 APPENDIX D
                                                                Page 4 of 6

          Mark Whitehead,  Architect, explained the  design rationale,  and
          Randall  Sharp,  landscape  Architect,  described  the  landscape
          plan.

   -      Panel's  Comments:    After  reviewing   the  model  and   posted
          drawings, the Panel commented as follows:

          The Panel  supported this  rezoning application.    It was  noted
          there has been  significant response to concerns raised with  the
          earlier submission,  and a  major attempt  has been  made to  re-
          think the project.

          The Panel  supported the  improved  landscape plan,  particularly
          the  raised  terrace  on  the  lane  side.    There  may   be  an
          opportunity  to  space  the trees  closer  together on  the south
          portion  of the  retail component.   The  rooftop  would be  more
          useful  if  some  kind   of  overhead  structure  is  introduced.
          Provision of  a small, defensible space  for children's play  was
          also recommended.

          Better  definition  of  the  uses  is  needed.    The delineation
          between residential and commercial is  ambiguous.  The  entrances
          are  confusing,  and  the  concrete  arch  over  the  residential
          entrance should be reconsidered. 

          The Panel  recognized  that  this is  a key  site  in the  entire
          project, and  agreed it needs  a response  that is distinct  from
          the towers that have been built to  date.  Concern was  expresses
          that  the proposal  is still  not responding  appropriately.  The
          economic realities  of this project  are acknowledged.   However,
          the  Panel felt  there  should  be  serious  investigation  of  a
          massing alternative that  is somewhat higher and slimmer, with  a

          smaller floorplate.  There  was major concern expressed about the
          sameness  of  the  floorplates  in  all  the  Collingwood Village
          towers seen to date, to the extent that  they appear overbearing.
          It  was  strongly  suggested  that  the guidelines  allow  for  a
          taller,  narrower  diagram.   An  increase  in height  up  to  20
          storeys,  with a smaller  floorplate, was considered appropriate,
          subject to  input from the neighbourhood.   The way the  building
          relates to the street will be very  important to creating a sense
          of  community,  and  a  smaller  floorplate  would help  in  this
          regard.

   -      Applicant's  Response:   Mr. McCauley  noted they  struggled with
          the issue  of the size  of the  floorplate vs. the  height of the
          tower.   To  a certain point  they are bound by  the height limit
          established  by  the  Collingwood rezoning,  and  indications are
          that there  would be  a strong neighbourhood  resistance to  this
          b   u   i   l   d   i   n   g       g   o   i   n   g       t   o

                                                                 APPENDIX D
                                                                Page 5 of 6



          20 storeys.  Present floorplate size  is approximately 6,400  sq.
          ft.  and it  is not  economically viable  to  reduce further  and
          achieve the goal of  affordability.  He added, they are  prepared
          to work with Planning  and the community to make improvements  to
          the massing, including the addition of another one,  two or three
          storeys.  Mr. McCauley  noted that they, too, struggled with  the
          notion of "gateway"  for this building, and recognized more  work
          is  needed to  acknowledge the  importance of  this  site.   With
          respect to the streetscape, they will also be working to make  it
          a more people friendly place."


   Applicant's Comments

   Greystone  Properties  have had  the  opportunity to  review  the policy
   report for  the  above noted  project dated  April 1,  1996  and are  in
   general agreement with staff's comments and findings.  There are however
   the following items  which Greystone would like  Council's consideration
   of at the time of referral or Public Hearing.

   1.     Unit Count   Greystone seeks  some flexibility  in the number  of
          proposed residential units  in order  to respond to the  changing
          demands  of the  market place.    Therefore without  altering the
          overall gross building  area we request that  up to a maximum  of
          150  of  units may  be permitted.     This affords  Greystone the
          opportunity to seriously consider  providing rental units as part
          of this development.

   2.     Residential Parking  Ratios   Based on our  recent experience  in
          the Joyce  Station area with both  Wellington Mews and the  first
          phase  of  Collingwood  Village  we  are  finding  a  significant
          reduction in residential parking  stall demand from residents due
          to the proximity of the Skytrain.  Greystone  seeks approval from
          Council for  the provision of 1  stall per residential unit  plus
          an additional  0.1 stalls per  unit for  visitor rather than  the
          ratio proposed by Engineering  in the policy report.  We  propose
          to provide the commercial parking as per the parking.

   3.     Separate  Loading and  Parking Access   Given the  constraints of
          the narrow,  slopping site and Greystone's desire to maximize the
          ground level  outdoor amenity area  and landscaping  treatment on
          the podium which was  strongly supported by  the Advisory  Design
          Panel, it  is no  possible to achieve  Engineering's request  for

          separate loading and parking access from the lane.  Greystone 
                                                                 APPENDIX D
                                                                Page 6 of 6



          seeks Council approval to retain the  loading and parking  access
          in their current configuration  as indicated on the architectural
          plans.

   As noted in the policy report, this development is marginally viable and
   as such  any delay  in processing  this rezoning application  challenges
   Greystone's ability to deliver the  Crime Prevention Office and meet our
   obligations  to deliver  the  office  space to  committed  tenants.   We
   request Council's support for referral  of this report to Public Hearing
   at the earliest possible date.                                APPENDIX E
                                                                Page 1 of 1

   FORM OF DEVELOPMENT

   5104-56 JOYCE STREET

                                                                 APPENDIX F
                                                                Page 1 of 1

   APPLICANT, PROPERTY, AND DEVELOPMENT PROPOSAL INFORMATION

   APPLICANT AND PROPERTY INFORMATION 

            Street Address                    5104-56 Joyce Street
            Legal Description                 Lots A, R, 5 & 6, Block 158, DL 37, Plans 2750, 20906, LMP 24057  

            Applicant                         Brian McCauley, Greystone Properties Ltd.

            Architect/Plans by                Mark Whitehead, Musson Cattell Mackey Partnership
            Property Owner                    Greystone Properties Ltd.

            Developer                         Greystone Properties Ltd.

          SITE STATISTICS

                                                      GROSS                DEDICATIONS                  NET

            SITE AREA                               2 010 m›                   N/A                    2 010 m›
                                               (21,636.2 sq. ft.)                                (21,636.2 sq. ft)

          DEVELOPMENT STATISTICS

                                                DEVELOPMENT PERMITTED UNDER               PROPOSED DEVELOPMENT
                                                      EXISTING ZONING

            ZONING                                         C-2C                                   CD-1

            USES                                   Office/Retail Service                     Dwelling Units
                                                  Cultural & Recreational                 Office/Retail Service
                                               Dwelling Uses, Institutional              Crime Prevention Office
                                                  Utility & Communication                    Accessory Uses
                                                      Accessory Uses
            DWELLING UNITS                                  N/A                                    117

            MAX. FLOOR SPACE RATIO                        3.0                                      5.6

            GROSS FLOOR AREA                   6 030 m›  (64,908.5 sq. ft.)           1 1256 m› (121,162.7 sq. ft.)
            MAXIMUM SITE COVERAGE                           N/A                                    N/A

            MAXIMUM HEIGHT                           12.2 m  (40 ft.)                       47.9 m  (157 ft.)

            MAX. NO. OF STOREYS                              4                                     16

            PARKING SPACES                         As per Parking By-law                           184

            FRONT YARD SETBACK                              N/A                                    N/A
            SIDE YARD SETBACK                               N/A                                    N/A

            REAR YARD SETBACK                        4.6 m (15.1 ft.)