A9

                             ADMINISTRATIVE REPORT

                                            Date:  February 27, 1996
                                            Dept. File No. :  650182

    TO:       Vancouver City Council

    FROM:     General Manager, Engineering Services

    SUBJECT:  1996 Provincial Cycling Network Program
              - Preliminary Work

    RECOMMENDATION

         THAT   $215,000 be allocated  for preliminary work  on the Arbutus
         Bike  Corridor,  S.W. Marine  Drive  Bike  Corridor, and  commuter
         connections and upgrades for the 7-Eleven  Bike Path, as described
         in  this report,  to  be funded  from  the Streets  Basic  Capital
         Unappropriated  Account  #12/31/6903/999,  with  report   back  on
         detailed design after consultation with affected communities.

    COUNCIL POLICY

    The Vancouver Comprehensive Bicycle  Plan (1988), the Clouds of  Change
    Report  (1990), the  City-wide Bicycle  Network (1992)  and the  recent
    Greenways  Program  establish  the   City's  policy  of  promoting  and
    encouraging cycling as a transportation alternative.

    PURPOSE

    The purpose of this report is to inform Council about the award of 1996
    Provincial   Cycling  Network   cost-sharing   funding,   to   allocate
    preliminary funding  for the 1996 Provincial  Cycling Network projects,
    and  to inform  Council  about  four  applications  made  to  the  1997
    Provincial Cycling Network Program.

    BACKGROUND

    On  June 15,  1995,  the Honourable  Jackie  Pement, then  Minister  of
    Transportation and Highways, announced a Cycling Network  Program.  The
    Cycling  Network  Program  provides  funding for  the  construction  of
    cycling infrastructure  on provincial and local roads, the latter being
    50% cost-shared with local  municipalities up to a maximum  of $200,000
    per  project.   The intent  of the program  is to  encourage additional
    cycling infrastructure, not to replace existing municipal funding.  For
    the  fiscal year 1996/97, approximately $2 million was allocated by the
    B.C. Transportation  Financing Authority.  Municipalities  are required
    to  have  a comprehensive  cycling network  plan  in place  to qualify.
    Applications for the  1997 program had to be  submitted to the Ministry
    by February  12, 1996 and all  construction must be  completed by March
    31, 1997.On February 27,  1996, Council approved $334,000 to be used in
    conjunction with Provincial  and existing monies to  fund three cycling
    projects; the Arbutus Bike  Corridor, S.W. Marine Drive  Bike Corridor,
    and Commuter connections and upgrades for the 7-Eleven Bike Path.

    DISCUSSION

    1996 Provincial Cycling Network Program

    As part of the 1996 Provincial Cycling Network Program the Ministry  of
    Transportation and Highways  awarded $360,000 to the  City of Vancouver
    to be applied towards three cost-shared bicycle projects.  Of the seven
    project applications submitted the following were approved:

    1.   Arbutus Bike Corridor
    2.   S.W. Marine Drive Bike Corridor
    3.   Commuter connections and upgrades for the 7-Eleven Bike Path

    These  three projects are similar to existing Bikeways and are detailed
    in Appendix A.  The total cost for these three projects is estimated at
    $830,000, and will be funded by City and Provincial monies.

    Allocation of $215,000 is  requested for preliminary work on  the three
    projects  approved for  the 1996  Provincial Program.   This  work will
    include pavement improvements, upgrading existing  signals with cyclist
    push-buttons, and route  signs.   This work is  similar to  preliminary
    work  done  on  previous  bikeway  projects.    Also  included  in  the
    preliminary work  is funding for  an Engineering Assistant,  level III,
    for six months at a cost of $20,000.

    Engineering  will report back to  Council for approval  of the detailed
    designs and  funding allocation  for all  three projects  after further
    consultation with affected communities.  

    1997 Provincial Cycling Network Program

    The  City   has  approved  bicycle   plans  in  place,   including  the
    Comprehensive  Bicycle Plan,  the Bicycle  Network Plan,  and Greenways
    Plan.  From  these, the  following bicycle projects  were reviewed  and
    prioritized,  in consultation  with the  Bicycle Advisory  Committee to
    Council:

    1.   37th Avenue Bike Corridor
    2.   Bikeway Links
    3.   Kent Avenue Bike Corridor
    4.   West-End/Downtown Cycling Improvements 

    A detailed description of each project can be found in Appendix B.
    The above applications were submitted to the 1997 Cycling Network Cost-
    Share Program and the total estimated  project cost is $1,469,000.   If
    all four projects are approved the City's share would be $816,000.

    ENVIRONMENTAL IMPLICATIONS

    There is a  positive environmental impact because  a non-polluting form
    of transportation (bicycles) would be promoted as an alternative to the
    automobile, while discouraging automobile use along Bikeways.

    PERSONNEL IMPLICATIONS

    1996 Provincial Cycling Network Program

    The July 4th Administrative Report, Provincial Cycling Network Program,
    stated that  additional staff may  be required if two  or more projects
    were  approved.   Based on  this  year's award  for three  projects, an
    additional staff member (Engineering Assistant, Level III), is required
    for six months to ensure that  the work is completed by September 1996,
    the  Provincial deadline.   The  additional staff  member's work  would
    include drafting/design, traffic counts,  graphics and some project co-
    ordination.

    Computer  equipment is also required for use by the Bicycle Coordinator
    and  the temporary  staff  member as  existing  computer resources  are
    limited.   The computer equipment would be used for drafting, graphics,
    communications  (fax/email),  schedules,  budgets,  correspondence  and
    report writing.

    1997 Provincial Cycling Network Program 

    Personnel implications for  the 1997 application would be  dependent on

    the number of  projects approved for  cost-sharing.  If there  are more
    than two projects approved, staff resources will need to be reviewed to
    ensure the  project completion date of  March 31, 1997.   This could be
    accomplished within the proposed Capital Program for cycling.

    FINANCIAL IMPLICATIONS

    a)   1996 Provincial Cycling Network Program
         The estimated costs for the three approved 1996 projects are:

         Arbutus Bike Corridor...............................      $510,000
         S.W. Marine Drive Bike Corridor.....................      $120,000
         Commuter Upgrades for the 7-Eleven Bike Path........      $200,000
                                       Total                       $830,000
         The  funding sources for the three projects under the 1996 program
         are as follows:

         Existing Funds......................................      $136,000
         Funding Approved Feb 27, 1996.......................      $334,000
         Provincial Share....................................      $360,000
                                       Total                       $830,000

         $215,000  is requested  now for  preliminary work  and Engineering
         will  report back with  proposed allocation  on the  balance after
         detailed design is completed.

         The cost estimates for the preliminary work are as follows:

         Pavement Improvements...............................      $110,000
         Push Button Upgrades................................      $ 40,000
         Route Signs.........................................      $ 35,000
         Temporary Staff and Computer Equipment..............      $ 30,000
                                                 Total             $215,000

         Funding for the total  project, $830,000, is available in  Streets
         Basic Capital Unappropriated Account (12/31/6903/999).

    b)   1997 Provincial Cost-Share Program
         Details of the four projects have not been finalized yet;
         however,  based  on  past  bicycle  projects  the  total  cost  is
         estimated to be $1,469,000.  If all four projects are approved for
         Provincial Cycling Network Program funding, the City's share would
         be  $816,000.   Sufficient funds will  be submitted in the 1997 to
         1999 Capital Program to fund these and other bicycle projects.  If
         the  Capital  Program submission  is  approved  by voters  in  the
         plebiscite, then sufficient funds will be  available for the cost-
         sharing Cycling Network Program.

         Matching funds  for the  downtown portion  could also be  provided
         from Concord-Pacific with funds provided in lieu of parking.

         The estimated cost per project is as follows:

         1.   37th Avenue Bike Corridor....................      $  550,000
         2.   Bikeway Links................................      $  413,000
         3.   Kent Avenue Bike Corridor....................      $  356,000
         4.   West-End/Downtown Cycling Improvements.......      $  150,000
                                                 Total           $1,469,000

    BICYCLE ADVISORY COMMITTEE COMMENTS

    The Bicycle Advisory Committee  was involved in the selection  of these
    projects, has reviewed  this report  and finds it  consistent with  the
    objectives of the committee.

                           *     *     *     *     *