SUPPORTS ITEM NO. 2 
                                                P&E COMMITTEE AGENDA
                                                FEBRUARY 29, 1996   

                                 POLICY REPORT
                           DEVELOPMENT AND BUILDING

                                                    Date: February 20, 1996
                                                      Dept. File No. 5008.1


   TO:       Standing Committee on Planning & Environment

   FROM:     Manager of  Facilities Development and Manager  of Real Estate
             Services, on behalf of the Emergency Management Committee

   SUBJECT:  Emergency Operations and Communications Centre - 
             Site Rezoning

   RECOMMENDATION

        A.   THAT  Council authorize  staff  to proceed  with the  rezoning
             application for the site selected for  the EOCC - Lots 1 to 15
             and  26 to 32 inclusive of Block 60, Town of Hastings Suburban
             Lands,  Plan  330, bounded  by  Pender,  Rupert, Hastings  and
             Cassiar Streets as indicated in Appendix  B. 

             AND  FURTHER  THAT Council  instruct  the  General Manager  of
             Community Services to assign  a priority status for processing
             the  rezoning application so as to meet the City s commitments
             under the agreement for the Infrastructure Grant.

        B.   THAT Council authorize staff  to commence negotiations for the
             purchase of the  three privately-owned lots  (Lots 27, 28  and
             29) forming part of the site in A, the source of funding to be
             the Land Purchase Fund.

        C.   THAT Council  instruct  the  General  Manager  of  Engineering
             Services to finalize an agreement for transferring Lots 15 and
             26 from  the Ministry  of Transportation  and Highways to  the
             City.

   CITY MANAGER'S COMMENTS

        The City Manager RECOMMENDS approval of A, B, and C.

   COUNCIL POLICY

   There is no applicable Council policy.



   PURPOSE

   This report provides Council  with information on the current  status of
   the EOCC site selection process and a synopsis of the public information
   meetings  held with  the Hastings  Community  Centre Board  and Hastings
   Community  with  regard  to   the  Rupert/Hastings  site,  and  requests
   authorization to proceed with a rezoning application for said site.

   BACKGROUND

   In  May   1995,  the  City  of   Vancouver  received  federal/provincial
   infrastructure  funding towards  the  cost of  constructing a  Vancouver
   Emergency Operations Centre.

   On  July 25,  1995, City Council  considered a  report on  the Emergency
   Operations and  Communications Centre (EOCC)  and approved  a number  of
   recommendations authorizing:

   -    construction of the Vancouver Emergency Operations Centre;
   -    participation of other agencies on a cost-shared basis;
   -    negotiation with other agencies in the details of participation;
   -    preparation  of  a  long term  plan  for  the  City s communication
        systems, in anticipation of a Capital Plan submission for a related
        upgrading of the City s radio systems;
   -    award of consulting contracts, and
   -    funding sources for the EOCC project.

   On September 28, 1995, Council  passed resolutions endorsing a continual
   leadership role by Vancouver in the Centre and maintaining a target date
   for completion  at December 1997. Council also  approved the appointment
   of the consultants for the project.

   DISCUSSION

   General Description of the Project

   As  presently envisaged the EOCC, subject to confirmation by the outside
   agencies, will contain the following components:

   -    Vancouver Fire Dispatch Centre (VFD)
   -    Vancouver Police Dispatch Centre (VPD)
   -    Regional 9-1-1
   -    RCMP Dispatch Centre
   -    Vancouver Emergency Operations Centre (VEOC)
   -    BC Ambulance Dispatch Centre (BCAS)
   -    BC Ambulance Regional Office (BCAS)
   -    Provincial Emergency Program (PEP)
   -    Regional Emergency Coordination Centre (RECC)
   -    Ministry of  Transportation and Highways Traffic  Management Centre
        (MOTH)

   On the  basis of  the functional  study undertaken by  the City  for the
   Vancouver portion of the  Centre and functional areas provided  by other
   users, it is estimated that the EOCC will be comprised  of the following
   approximate areas:


        Components                 Gross Areas (SF)
        VEOC, VFD, VPD, 9-1-1           30,000
        RECC (20)                        3,000
        RCMP                             6,000
        PEP                              2,500
        MOTH                            18,500
        BCAS                            14,000
        Total                           74,000

   Site Evaluation

   Approximately  twenty (20) sites,  both City-owned  and privately-owned,
   were identified  and evaluated by the  project team on the  basis of the
   following criteria:

   1.   Geotechnical:       Suitability  to  sustain  a   major  earthquake
                            including post-disaster requirements.

   2.   Accessibility:      Public   transit,    vehicular   accessibility,
                            proximity   to   major    arteries   and    air
                            accessibility. The facility  will operate on  a
                            24-hour basis.

   3.   Communication:      Land  line,  telephone, radio,  ducting, fibre-
                            optic cabling,  linkage, line  of sight  to the
                            North Shore mountains.

   4.   Hazard/Risk:        Probability   of   occurrence   for   flooding,
                            dangerous  goods,  explosions   and  gas,   and
                            available  mitigation   measures  against  such
                            risks.

   5.   Development Cost:   Land cost, network  systems, construction  cost
                            premiums,  servicing and  massing -   preferred
                            height of 2-storeys maximum.

   6.   Development Timing: Property  acquisition, rezoning  and relocation
                            costs.

   Sites  which  did not  meet  one  or more  of  the  major criteria  were
   considered to be  unsatisfactory and  were eliminated. On  the basis  of
   this  evaluation  five sites  were short  listed:  two on  Kingsway, the
   Renfrew/McGill parking lot, the  Renfrew/Hastings site (S.E. corner) and
   the Rupert/Hastings site.

   Staff concluded that the  Renfrew/McGill and Renfrew/Hastings site would
   impact  on the proposed Hastings  Park plan, hence  these two sites were
   deleted from the list of potential sites. The remaining three sites were
   short listed for detailed evaluation.

   On the basis of a detailed analysis by the planning team which included:
   hazard and risk assessment by EmergeX Planning Inc., massing analysis by
   Architectura, communications analysis by Teleconsult Limited and seismic
   overview  by Macleod Geotechnical Ltd., it was concluded that while none
   of  the  sites  ideally  meets  all  of  the  design  requirements,  the
   Rupert/Hastings site  best fits the project  requirements. (See Appendix
    A )

   Thus,  it is recommended that  the Rupert/Hastings site  be selected for
   the project and a rezoning application be initiated.

   Rupert/Hastings Site

   The  Rupert/Hastings site  is bounded  by Pender,  Rupert, Hastings  and
   Cassiar Streets. It consists of a street end and a  parking lot that are
   City-owned, and three single family homes that are privately-owned  (see
   Appendix  B ). The parking lot (200  stalls) is presently used as a park
   and  ride  operation,  which  is significantly  under  utilized  in  our
   opinion. Anther surface lot  west of Rupert Street (460  stalls) is also
   used  as  a  park  and  ride  lot,  and  will not  be  affected  by  the
   development. Purchase of the three privately-owned lots (Lots 27, 28 and
   29) would likely be required to accommodate the full program.

   The site  is below the grade of Hastings Street and the adjacent freeway
   connector.  It is presently zoned  CD-1/RS1-S. The  usable   area of the
   site  including  the  street   end,  and  the  three  private   lots  is
   approximately 100,000 SF.

   The City-owned  portion of the site  is classed as Capital  Asset - PNE,
   and is  not included  in the  Trust  Lands designated  for the  proposed
   Hastings Park.

   Synopsis of the Public Information Meetings

   On January 18, 1996, the members of  the EOCC team met with the Hastings
   Community Centre  Board to discuss the project. The Board  asked general
   questions about the facility and its  operations. Issues raised included
   traffic, parking  and the existing  zoning. Board members  had questions
   about the site selection process and the choice of location.

   Two public information meetings were held on January 31 and  February 1,
   1996 at  the Hastings Community  Centre. The January  31 meeting was  to
   hear the concerns  of the  immediate neighbours. Four   hundred  notices
   were  hand-delivered to  households within  a four-block  radius  of the
   site. A total of five people attended  the January 31 meeting expressing
   concerns  about view  impacts and  traffic. One  resident felt  that the
   proposed location was the best place in the community for such facility.

   The  February 1  meeting  was  intended  to  give  the  larger  Hastings
   community an opportunity  to learn about the project and  comment on it.
   Notices were delivered by Canada Post admail to over 6,000 Hastings area
   residents. A  total of  seventeen residents attended  this meeting.  The
   meeting was advertised in the Vancouver Echo, Vancouver Courier, and the
   Chinese  media of  Sing  Tao  and  Ming  Pao.  Chinese  translation  was
   available at both the meetings.

   Some residents attending the February 1 meeting were concerned about the
   impact  that  this facility  may have  upon  the Hastings  Park Planning
   Process,  particularly  with regard  to  off-site parking  for  the Race
   Track.  Questions related to the site selection process were asked. Some
   residents were  interested  in the  possibility  of a  community  police
   facility within the development.

   The EOCC design team promised that additional meetings will be held with
   the  community prior to a  rezoning application being  filed, to discuss
   the building design, greenway  linkages into Hastings Park, traffic  and
   view impacts.

   The Manager of Real Estate has initiated discussions with the owners  of
   the three properties within the boundaries of the site.

   Design

   Design is  presently at  an  early conceptual  stage. The  work that  is
   underway includes: preliminary massing analysis, site surveys, adjacency
   studies and  general discussion  with the City s  Engineering Department
   with  regard  to  parking requirement  and  accessibility  to the  site.
   Presently, it is  our desire that the principal entry to the site be off
   Hastings at Rupert Street so as to minimize vehicular  traffic on Pender
   Street through the residential area. 

   Pursuant  to the City s Greenway  Program, the design  will also include
   provision for a pedestrian s walkway and a bicycle route along the edges
   of the development, so as  to provide future greenway links between  the
   neighbourhood south of Hastings and the proposed Hastings Park.

   The  site would be well landscaped  with generous setbacks, particularly
   along  Pender Street, to provide visual screening between the Centre and
   the residential users to the south. The building itself will be faced on
   the Hastings Street side with the entry currently located  at the corner
   of  Hastings and Rupert.  We will also  be exploring the  feasibility of
   terracing  the building  to  the  south to  minimize  any mass  of  that
   particular building face.

   In view  of the natural slope  of the property and  surface grades below
   the grade of  Hastings and the adjacent freeway, it  is expected that in
   the  all-in  option most of the parking and mechanical equipment will be
   located in an underground parkade.  Once finalized, a preliminary design
   will be presented to  the neighbourhood at a Public  Information meeting
   prior to a rezoning application being filed.

   Schedule

   The  project schedule is primarily  being driven by  the requirements of
   the Infrastructure Program, and a need to house the Emergency Operations
   Centre  in a  suitable  facility. The  Infrastructure Program  initially

   called for a completion date by December 1997.

   Due to delays  in receiving  confirmation from BCAS  and MOTH  regarding
   their  participation, the schedule has slipped a couple of months, which
   was  of concern  in light  of our  commitments under  the Infrastructure
   Program.  Coincidentally,  the Province  has  since  confirmed that  the
   Federal  Government has agreed to  an extension in  the completion dates
   for  its more recently approved  projects, including the  EOCC, to early
   1998.

   The City of Vancouver is required, however, to  submit a revised program
   and budget  to the  Province  by February  29, 1996.  Assuming that  the
   program  can be finalized by the end of February, the following schedule
   should be adhered to in order to meet the completion dates:

        Finalize Program                 February 29, 1996
        Rezoning Process                 March 18 - July 09, 1996
        Public Hearing                   July 02, 1996
        Start Construction               April 1997
        Complete Construction            April 1998

   In  order to  maintain the above  schedule it  is necessary  to obtain a
   priority status  for the rezoning  process. This report  recommends such
   process be implemented.

   Comments of the Director of Land Use and Development

   If  the strategy is to  contemplate rezoning of the  site to a CD-1 with
   only nominal provisions  (i.e. use,  density and parking)  and with  the
   form  of  development  to  be  considered  at  a  later  date,  priority
   processing will have little impact on other rezoning work and  a June 27
   Public Hearing should be readily achievable.

   The disadvantage of this strategy is that the resultant zoning  does not
   in itself reflect or limit the site to a particular form of development,
   and  neighbouring residents often want not only a clear understanding of
   what is to be built under the zoning but assurance that  the zoning will
   not  allow  alternative  development  forms  without  a  further  Public
   Hearing. The notion that  what  you see during the rezoning is  what you
   will  get  is often very  important to rezoning applicants, neighbouring
   residents  and staff, but the rezoning process is consequently much more
   comprehensive and lengthy.

   Priority processing will be required to meet the time constraints if the
   EOCC rezoning application is to embody a particular form of development.
   This  will also divert staff resources and  delay one if not two private
   rezoning applications  in process, with  their timing to  Public Hearing
   slipping by  a  month or  two. A  June  27 Public  Hearing for  an  EOCC
   rezoning application would,  under this strategy, be achievable but only
   if  a complete  application  is submitted  by  March 18,  all  reviewing
   departments  and boards provide  commentary within  three weeks  and the
   staff report  is completed by the  end of April for  Council referral on
   May 14.

   The  Director of  Land Use  and Development  recommends submission  of a
   rezoning application without an accompanying form of development, noting
   the above-described  processing implications and  also recognizing that,
   in addition to Council still retaining authority for subsequent approval
   of the form of development, the  City will have control over development
   by virtue of site ownership.

   Copies of this report have been distributed to the Hastings Park Working
   Committee and the Board of Parks and Recreation.


                        *    *      *      *     *