SUPPORTS ITEM NO. 1
                                                P&E COMMITTEE AGENDA
                                                FEBRUARY 29, 1996   


                             ADMINISTRATIVE REPORT


                                                    Date: February 13, 1996
                                                    Dept. File No.         

   TO:            Standing Committee on Planning and Environment

   FROM:          General Manager, Park Board

   SUBJECT:       Hastings Park Planning

   RECOMMENDATION

        A.   THAT the attached Hastings Park Program (Appendix 1) be
             approved as the basis for the development of a conceptual
             design plan.

        B.   THAT $35,000 be approved for commissioning an adaptive re-use
             study for three buildings:  the Forum, the Garden Auditorium
             and Rollerland; source of funding to be the Hastings Park
             Reserve.

   COUNCIL/BOARD POLICY

   City Council and Park Board are both committed to the greening of
   Hastings Park.  Council approves the budget available for this project.

   BACKGROUND

   In 1990, City Council reaffirmed its intention to resume control and
   operation of Hastings Park from the Provincial Government, and further
   define its commitment to restore Hastings Park "to dominant park use
   with abundant park space and trees instead of asphalt and buildings". 
   The Park Board (March 6, 1995) and City Council (March 16, 1995) passed
   the following resolutions:

        A.   THAT the Hastings Park planning process, as outlined in this
             report be approved.

        B.   THAT City Council be requested to approve $350,000 for the
             implementation of this planning process, with the funding to
             be provided from the Hastings Park reserve.

   The planning process commenced in 1995 identified five phases:

        -    preparation
        -    programming
        -    conceptual design
        -    design development
        -    plan adoption

   The preparation phase was completed in September 1995, and with the
   approval of this program document, the programming phase is complete.

   DISCUSSION

   Public Involvement

   The public involvement program in framing up this document has been
   quite extensive and has:

   1.   Involved the distribution of two newsletters to 9,000 area
        residents.  

   2.   The two community conferences(May and October 1995) attended by 100
        - 130 people each. 

   3.   About forty meetings of the six Forums (Racetrack, Hastings
        Residents, Vancouver Residents, Environment, Arts & Culture, and
        Sports).

   4.   Eighteen meetings of the Hastings Park Working Committee.

   5.   Consultation with a wide variety of community groups.

   When Council approved the public involvement structure it was foreseen
   that there would be 8 interest based forums.  These forums were intended
   for people with similar interests to provide input into the planning
   process.  Council also assigned the number of representatives that each
   of the Forums could have on a coordinating group known as the Hastings
   Park Working Committee.  The number of representatives were as follows:

        Hastings Residents  5
        Racetrack           3
        Site Employees      2
        Vancouver Residents 1
        Sports              1
        Environment         1
        Arts & Culture      1
        Youth               1
        Business            1

   Two of the forums did not materialize:  Business and Youth.  Despite an
   intensive effort to organize Hastings Street merchants, there was
   insufficient interest to form a group.

   Similarly the Youth Forum proved impossible to establish despite several
   efforts.  Instead the co-design workshops which were a part of the
   original work program were exclusively focussed on secondary school
   students in the immediate catchment area.  This proved successful in
   obtaining a youth perspective on the future of Hastings Park.


   The site employees remained a part of the Working Committee but at their
   choice participated only in a few of the meetings.

   The process has resolved a number of the issues identified at the outset
   of the program, and some other issues have been distilled into distinct
   options which require further evaluation in the context of the
   conceptual design studies.

   Greening of Hastings Park

   The program document establishes the basis for developing highly
   creative designs aimed at restoring Hastings Park "to dominant park use
   with abundant green space and trees instead of buildings and asphalt",
   in accordance with Council's direction.  Statistically of the 162 acre
   site, 51 acres are leased to the Racetrack, and further 17 acres would
   be taken up with parking areas and buildings to be retained, leaving
   about 94 acres to be devoted to green space.

   The program for the greening of Hastings Park is premised on
   restoration, integration, connection and experimentation.  The park
   program intends to restore its overall green character and, in
   particular, focus on the daylighting of one of the two streams that once
   traversed the site.  The park's green sanctuary will be defined by this
   stream and a series of associated waterbodies.  Extending outwards from

   the stream, there will be layers of increasing activity which will
   include a variety of sports, recreational and cultural activities.

   The following objectives are key elements in the greening of Hastings
   Park:

   . Restore the park's stream.
   . Restore the park's natural features.
   . Restore a green sanctuary.
   . Focus community pride.
   . Connect the park to the neighbourhood.
   . Connect with adjacent parks.
   . Integrate active and passive park uses.
   . Integrate the old with the new.
   . Integrate Racetrack within the park.
   . Experiment with new ideas.
   . Create a safe park.

   Buildings

   Council's direction with regards to the buildings was that all major
   buildings except for the Garden Auditorium, the Agrodome, and the
   Coliseum be removed in order to make way for green space.  During the
   process there was considerable discussion about this matter.  The
   heritage classification of the Garden (A), Forum (B), Food (B), and
   Rollerland (B) buildings were noted, and some stakeholders initially
   felt that many of these buildings held potential for a variety of arts,
   cultural, and recreational pursuits.  A consensus was eventually arrived
   at by noting that adaptive reuse studies should be done for three
   buildings, namely the Forum, Rollerland, and the Garden Auditorium. 
   These studies would examine the costs and benefits of renovating these
   buildings to a range of possible uses.

   In the case of the Forum, the principal use involves community ice.  A
   consultant study on the demand for community ice concluded that there
   presently is a firm demand within Vancouver for at least 60 hours a week
   out of a capacity of 110 hours.  Participation in minor hockey, the
   principal user of the community ice rinks, is at an all time historical
   high, and is expected to remain strong though it may ease off somewhat
   over time.  While a good portion of the additional demand is generated
   on the west side of the City, it is possible that if the Forum can be
   adapted at a relatively modest cost, the Forum may in fact be a viable
   option.  However the Park Board would also have other options available
   to meet the additional demand for ice time, should the demand continue. 
   These options include twinning an existing rink (low operating costs,
   high capital) or renting ice time for minor hockey in private rinks
   (greater travelling distances for players).  The study also notes that
   24 private rinks have recently been added in the region, plus a further
   12 are in various stages of design and permitting.

   The proposed uses for the Garden Auditorium and Rollerland overlap
   substantially.  A range of community recreation activities such as
   indoor volleyball, basketball, aerobics and other general gymnasium
   uses, community arts and cultural activities, including a performance
   space and rehearsal spaces for music, theatre, as well as workshop space
   for community arts activities such as the Public Dreams Society could be
   accommodated in these buildings.

   Therefore, a separate adaptive research study is recommended to:

        a)   verify the demand for the proposed community arts,
             cultural/recreational uses,
        b)   identify the best fit between buildings and uses,
        c)   identify the costs associated with adapting the buildings to
             the proposed uses, meeting all applicable building code
             requirements.

   An adaptive re-use study is expected to be in the order of $35,000.  The
   earlier Council report had identified a total of $350,000 for the
   Hastings Park Planning Process, but noted that the budget allocation for
   building redesign was only minimal.  A more extensive study, as now
   proposed, would therefore require some additional funding.

   Agrodome:

   The Agrodome is to operate as a community ice rink, while hosting the
   occasional spectator event, not unlike the Kerrisdale Arena.


   Coliseum:

   Council expressed its intent to maintain the Coliseum and have a private
   operator run the facility.  An initial proposal call was held, but no
   operator was selected.  Enquiries about the building continue to be
   received indicating some private sector interest in the facility.  It is
   expected that once GM Place has operated for one or more years, a larger
   number of operators may be interested in submitting proposals.  Impacts
   of Coliseum operations on the community and the park should be carefully
   evaluated, with community consultation to be a part of the process. 
   Should the eventual Coliseum use overlap frequently with horse racing
   events, the need for additional parking (an extimated 2,500 stalls at
   16,500 occupied seats) will require either structured parking, more off
   site parking or a greyer rather than greener Hastings Park.  (See also
   discussion under parking).

   Racetrack

   Considerable discussion took place about the integration of the
   racetrack into the park.  Current edges of the track are solid and offer
   few opportunities for people to view the intense and varied activities
   associated with training and maintaining thoroughbred race horses.  The
   track is committed to making the edges more permeable consistent with
   security requirements.  Elevated viewing points and, in some areas,
   waterbodies (rather than walls and fences) are intended to satisfy these
   objectives.

   The PRA has commissioned an adaptive reuse study of the Livestock
   building with the view of accommodating horses in a renovated Livestock
   building instead.  The impacts on the park design are significant and
   therefore the landscape consultant will be asked to evaluate both
   building new stables east of the Racetrack and renovating the Livestock
   building.  Retention of the Livestock building would be subject to a
   land swap aimed at creating a wider green strip on the eastern edge of
   the racetrack.  The conceptual design study will assume some flexibility
   in the ultimate configuration of the Racetrack boundaries.  

   The edges of the Racetrack may also require some landscape or site
   planning treatment, which would necessitate minor boundary adjustments. 
   Some flexibility of future track boundaries during the design process is
   recommended.  

   The PRA has also indicated that in the long term it may wish to revisit
   the proposal which was made by the B.C. Jockey Club some years ago,
   which involved straddling McGill Street with a concrete structure that
   would permit the expansion of the track itself.  This concept would be
   enhanced with a crossing to New Brighton Park and possibly a railway
   station that would permit direct access from the Vancouver/Mission Rail
   Line to Hastings and New Brighton Parks.


   Connection to Adjacent Parks

   The connection to New Brighton Park is also deemed to be an important

   part of the park's long-term success and most of the potential
   connections are in the vicinity of, or on the Racetrack lease area.  In
   the short run, the connection will likely be on the eastside of the
   track and then through the Bridgeway tunnel.  There is concern among
   some Forums that the width of the property between the PRA boundary and
   eastwards towards Cassiar Street may not be wide enough to accommodate
   both a stream, riparian areas, walkways and bikeways, particularly if
   the PRA proceeded with the construction of new stables.

   Connections to Hastings Community Park and Callister Park are also
   important.

   Parking

   The issue of parking has been a contentious one, since large amounts of
   surface parking quickly dilute the remaining amount of potential
   greenspace.  There are presently about 3,500 on site, plus a further 800
   off-site south of Hastings Street and 150 north of McGill Street.  The
   program calls for a total of 2,200 to be provided, on and off-site.  The
   fundamental principles in providing parking are:

        -    minimize the amount of parking to be provided south of Miller
             Drive and north of Hastings (i.e. future park sanctuary)
        -    maximize potential event related parking on Renfrew Street and
             Bridgeway Street
        -    maximize opportunities for park patron and racetrack related
             parking to overlap
        -    use off-site lots to meet some demands.

   A surface parking option and a structured parking option are to be
   evaluated.

   In order to assess the availability of parking over and above 2,200
   stalls, the park design consulting team, which will include a
   transportation engineer, is requested to examine opportunities through
   the creation of additional off-site parking lots, possibly associated
   with shuttle bus services and the provision of larger amounts of
   structured parking.  Neighbourhood impacts are to be evaluated.

   In comparison to the major parking requirements, the additional parking
   required for the park itself can largely be accommodated most times on
   the spaces to be created for the Racetrack.  Some small pockets of
   parking are envisaged close to some of the buildings to be retained,
   such as the Agrodome and the Garden Auditorium.

   The City Engineer recommends that the scope of the proposed traffic
   study be broadened to better ascertain the future parking needs and the
   possible impacts on the surrounding neighbourhood. The estimated parking
   demands may be underestimated. In addition, options should be developed
   to account for the possibility of additional parking demands,
   particularly with the retention and operation of the Coliseum.

   Next Steps

   The next steps in the Hastings Park Planning Process are:

        a)   retain landscape architectural team (see also Appendix 2)
        b)   retain adaptive reuse study team
        c)   generate concept plan (September)
        d)   complete design development (January)
        e)   commence building demolition (January)
        f)   commence landscape construction (Spring 1997)



                                   * * * * *