SUPPORTS ITEM NO. 2  
                                                      CS&B COMMITTEE AGENDA
                                                      JANUARY 11, 1996     


                              ADMINISTRATIVE REPORT


                                                   Date:  November 30, 1995
                                                   Dept. File No. 190 739  


     TO:       Vancouver City Council

     FROM:     General Manager of Engineering Services

     SUBJECT:  Relocation of Asphalt Plant and
               Aggregate Handling Operations


     RECOMMENDATION

          A.   THAT  Council  approve  the   relocation  of  the  Aggregate
               Handling and Asphalt Plant operation from the Cambie Yard to
               a new Yard on the Fraser River.

          B.   THAT a  new Works Yard  design include a  recycling facility
               for aggregate, asphalt, and concrete.

          C.   THAT to  cover the  land cost  of a new  Fraser River  site,
               Council approve  the disposal  of the Sterling  Shipyard and
               Commissioner Yard.   A  shortfall, if  any, would  be funded
               from the  aggregate/asphalt operations  through a loan  from
               the Solid Waste Fund.

          D.   THAT  a  preliminary  project  budget,  estimated  at  $13.3
               million,  be established  for the  design, construction  and
               commissioning of the new Works Yard and the  updated project
               budget and financing  plan will be reported back  to Council
               for approval after the preliminary design is completed.

          E.   THAT Council  approve $150,000  from the Project  Budget and
               authorize  the General  Manager  of Engineering  Services to
               call  for proposals  and select  consultants to carry  out a
               preliminary design for the new Works Yard.


     COUNCIL POLICY

     1.   Council  approved  the south  shore of  False  Creek as  a let-go
          industrial  area  in  July  1990,  and  made  provision  for  the
          relocation of  the land  based  operations from  the Cambie  Yard
          through the purchase of the former Burlington Northern Rail (BNR)
          Yards in the East False Creek Flats in 1992.



     2.   Council, in 1979, made provision for the future relocation of the
          water-based  aggregate  operation and  related  asphalt plant  in
          Cambie Yard by securing the former Sterling  Shipyard property on
          Burrard Inlet.

     3.   On July 26,  1995, Council  approved the relocation  of the  Fire
          Training Facility from the  Main Street site to the BNR yard, and
          put a hold on the property at the south foot of Main Street until
          Engineering Services reported back on its future Yards plan.


     PURPOSE

     This  report  reviews a  proposal  for relocating  City  aggregate and
     asphalt  plant operations  and  recommends that  a  new aggregate  and
     asphalt  facility, with expanded  recycling capabilities, be developed
     on a site  on the Fraser  River in order  to realize major  financial,
     technical and operational gains for  the City, in the short  and long-
     term.


     SUMMARY

     The Cambie Yard in False Creek will be planned and redeveloped to non-
     industrial uses over the next few  years.  The current land-based Yard
     Operations will be relocated, most likely to  the proposed Yard at the
     former BNR  site, pending the results  of a major yard  study which is
     expected  by  mid-1996.    The  water-based  operations  also  require
     relocation  and  this report  proposes  a  relocation and  development
     process and a financing strategy.
      
     A  detailed  study   of  the  aggregate  handling  and  asphalt  plant
     operation, identified major savings to the City by continuing existing
     operations.   Without a City-run operation, prices would be subject to
     market forces and  costs would  increase.  The  study also  identified
     additional  savings  to  be made  by  adding  a  construction material
     recycling facility to the aggregate and asphalt plant operation.

     The costs  for the  relocation to the  Fraser River  are estimated  at
     $13.3 million  for Yard development and $5.0 to $6.0 million for land.
     The site at Main  Street is owned in the PEF,  and arrangements can be
     made  to  secure  it for  yard  use.    It  remains possible  that  an
     alternative site might  be located  and final details  on a  preferred
     site will be reported back in early 1996.






     BACKGROUND

     The  proposed redevelopment  on the  South Shore  of False  Creek will
     require  the City's  Cambie  Works Yard  to  relocate.   Property  was
     purchased in the former  BNR Yard, to accommodate the  land-based yard
     operations.  A site at the former Sterling Shipyard is  being held for
     the water-based  aggregate and  asphalt operation, but  further review
     identified potential  community and  site concerns as  reasons not  to
     locate there.   An alternate City-owned  site on  the Fraser River  at
     Main Street is available.  Council recently approved the relocation of
     the Fire Department's Training operation from the Main Street site and
     put  a  hold on  that site,  subject  to a  report  back on  City yard
     requirements.

     The aggregate handling and asphalt plant operations are very important
     components  of  the  City's   Capital  and  Maintenance  Programs  for
     infrastructure.   They provide an efficient (both in time and dollars)
     materials supply and production  facility dedicated to serving Sewers,
     Waterworks, and Streets  Operations.  The estimated  400,000 tonnes of
     aggregate handled at the Yard each year are purchased through a public
     tender  process and costs are low because of the high volume.  Most of
     the aggregate materials are distributed to work sites in a combination
     of City trucks and privately owned hired trucks.  Approximately 25% of
     the aggregate is used to produce asphaltic concrete (asphalt) products
     for street construction and repair.  
     Currently,  the aggregate  and asphalt  plant operation  employs three

     full time staff  and contributes to  major savings in  excess of  $1.4
     million  per  year, over  contracted  aggregate  delivery and  private
     asphalt supply.

     The  aggregate  operation works  well, but  can  be improved  with new
     handling  equipment.   The asphalt  plant, installed  in 1967  with an
     expected  life  of  25  years,  has  served  the  City  well,  but  is
     experiencing  increased maintenance  costs  and cannot  meet the  peak
     volume demands of the paving operation.

     With  the timing of  development of False Creek,  the condition of the
     existing   plant,  and  the  need  to  be  even  more  competitive,  a
     comprehensive review  of the  City's aggregate and  asphalt operations
     was done.  The following discussion reviews current and future demands
     for aggregate and asphalt, compares current practice  to other options
     for supply  and production, and recommends continuing  operations in a
     new facility on the Fraser River.







     DISCUSSION

     A detailed study  was done  of the  current and  future aggregate  and
     asphaltic concrete  needs of the  City and how  best to  provide them.
     The   complete  study  is  available  from   the  General  Manager  of
     Engineering  Services and has been reviewed by Corporate Services, who
     agree  with the study conclusions.   The study  answered the following
     questions:

     (a)  how  do City  operations  compare to  other aggregate  suppliers,
          asphalt suppliers and production options? 

     (b)  how will City operations  handle, and what changes  are necessary
          to meet, future demands?

     (c)  what other ideas could be implemented to reduce costs and improve
          the efficiency of the operations?


     The following sections summarize the study findings.

     Aggregate Handling

     Currently,  because  of  the  large  demand  for  aggregate  materials
     generated  by   City  operations,  approximately  400,000   tonnes  of
     aggregate are purchased annually  by the City through a  public tender
     process.  The aggregate is delivered by barge to Cambie Yard, where it
     is off-loaded and made available  for pick up to all  City operations,
     including  Parks  and  Recreation.    Distribution  from  the  central
     facility is by trucks dispatched by the user branches.

     The aggregate operation employs one equipment operator and one half of
     a  foreman.  In the existing facility, trucks are required to off-load
     some  barges because there is  insufficient handling equipment.  Barge
     deliveries  are coordinated  by Materials  Branch staff,  as required.
     The low overhead and  no profit requirement, make this  operation very
     competitive.

     Numerous reviews have been  done over the years that  clearly indicate
     the  costs for aggregate materials and delivery  are lower with a City
     operation,  than  by private  contract.   An  analysis of  City versus
     private aggregate supply and delivery to job sites, identified savings

     (estimated at $750,000 annually) with the City operation.

     The  current volumes of material used in City operations will continue
     into   the   future,  given   the   requirements   for  infrastructure
     construction and maintenance.  The overall operation is efficient, but
     could be  improved.  A new  Fraser River Yard to  replace Cambie Yard,
     offers an  opportunity to install new material  handling equipment and
     improve  efficiency.   Recycling  of concrete  rubble  is proposed  to
     reduce  dependency  on new  aggregate  materials  and this  option  is
     discussed under Recycling.


     Asphalt Production

     The City produces approximately 100,000 tonnes of asphalt each year in
     the existing plant.   The Streets Operations Branch uses  the majority
     of the  asphalt produced  for new  construction  and maintenance,  and
     repair of streets.   The plant employs one  equipment operator and one
     half of a foreman.  As with aggregate supply, the  City is competitive
     in its asphalt operation due to the low labour and equipment costs and
     the non-profit  operation.  In addition  to the benefits of  low cost,
     there  are benefits from the plant location which give flexibility and
     quick response to demand.

     The  current  costs  to  produce  asphalt  were  compared  with  other
     municipalities and  private contractors.   The lowest cost  asphalt in
     the region was in Matsqui (now Abbotsford),  where the price is $35.60
     per tonne,  compared with  our  price of  $28.86 per  tonne  at a  new
     facility.   This  conservatively  translates to  an  annual saving  of
     $675,000  per year  over private  supply.   However, local  prices are
     higher, in the range of $45.00 per tonne, suggesting real savings over
     $1.5 million annually.

     The  analysis   showed  that  the  existing   operation  is  extremely
     competitive and that replacement of the plant and addition of improved
     storage facilities, can make it even  more so.  Reduced dependency  on
     new  aggregate through  increased recycling  of asphalt  would further
     reduce costs.


     Recycling

     During  reconstruction  operations,  large  amounts  of  concrete  and
     asphalt rubble are removed and disposed of at landfills.  The existing
     Cambie  Yard site  was too  small and  incompatible with  the adjacent
     residential  uses,  to allow  comprehensive recycling  of construction
     materials.   With  the  proposed relocation  to  the Fraser  River,  a
     significant opportunity to re-use and recycle asphalt and concrete and
     carry  out  limited soil  and rubble  separation,  is created.   Waste
     asphalt can  be reclaimed and  added to  new asphalt  mixes to  reduce
     production costs by at least an estimated $350,000 per year.

     Concrete rubble  can be crushed  into aggregate-sized particles  to be
     used as  road base and trench fill.  This would reduce our requirement
     for  aggregate materials,  thereby saving  the aggregate  operation an
     estimated  $260,000 per  year.   In  addition, savings  in operations,
     estimated  at $560,000,  could  be realized  through reduced  trucking
     costs  and  dumping  fees currently  spent  to  dispose  of rubble  at
     landfills.    The  current  tender  award  for  mineral  aggregate  is
     recommending a recycled concrete product.

     A recycling operation re-uses  materials, reduces space demand at  the
     landfill, reduces truck  traffic in the region  and is environmentally
     sound business.

     The savings  identified  above,  are  based  on  a  thorough  economic

     analysis.    In  carrying  out  the comparative  review  with  private
     operations, market land lease rates were used to ensure that all costs
     were accounted for.   The Analysis Report, available from  the General
     Manager of Engineering Services, demonstrates that the continuation of
     City-run aggregate and asphalt  production operations and the addition
     of a recycling capability, are  in the best interest of the  City from
     operational, environmental, and economic perspectives.


     PROPOSED NEW YARD

     Cambie Yard  will  soon  be  discontinued.    The  existing  aggregate
     handling and  asphalt plant operations described  above are efficient,
     cost effective and provide best value to the City.  For these reasons,
     it is proposed  that the City develop  a new Work  Yard on the  Fraser
     River  to   replace  the  water-based  aggregate   and  asphalt  plant
     operations from Cambie Yard.

     A proposed Fraser River  Yard would accommodate the new  asphalt plant
     and associated  storage facilities, improved aggregate  handling and a
     new recycling  operation.   A modernized materials  testing laboratory
     would also be accommodated.  The preliminary design would identify the
     site  layout   and  geotechnical  conditions,  and   refine  the  cost
     estimates.  It is  recommended that consultants be selected  and hired
     at an estimated cost of $150,000 to carry out the design.


     FUNDING

     The conceptual  estimate  of the  Capital  Costs (excluding  land)  to
     develop the new Aggregate and Asphalt Facility on either site is:

        Asphalt plant                       $5,000,000
        Aggregate handling                   6,000,000
        Recycling                            2,100,000

                                   TOTAL   $13,300,000





     It is suggested that funding could  be provided from the Asphalt Plant
     Equipment Reserve (current balance  $3,200,000) and potentially a loan
     from the Solid  Waste Fund or  some other element of  private funding.
     An  updated cost  estimate and  financing plan  will be  reported back
     after preliminary design is completed.

     The Main Street  site is owned in  the PEF and could  be available for
     between  $5.5 million  to  $6.5  million.    The  General  Manager  of
     Engineering  Services  recommends  that   the  Sterling  Shipyard  and
     Commissioner  Yard  be marketed  and that  any  shortfall in  the land
     purchase price be funded through a  loan from the Solid Waste Fund, to
     be repaid from the Asphalt Plant and Aggregate operation.

     Commissioner  Yard would continue to operate  at its current location,
     until it is relocated to the proposed new yard at the BNR site.


     CONCLUSION

     The  existing asphalt  and aggregate  operations have served  the City
     well for  many years by providing  necessary products at  a lower cost
     than from other sources.  With the pending closure of the Cambie Yard,
     and with the value to the City that the aggregate handling and asphalt
     plant provide, it is now appropriate to redevelop  the facilities at a

     site on the Fraser River.

     The  estimated total savings in operating and capital budgets with the
     new asphalt plant and  asphalt recycling operation, will be  over $1.0
     million  annually  ($675,000  currently),  when  compared  to  outside
     purchase  of  asphalt.   The estimated  savings  in the  aggregate and
     aggregate recycling operation will  increase from the current estimate
     of $750,000 annually, to over $1.5 million annually. 

     The recommendations contained  in this  report will  allow design  and
     estimates to proceed,  with a report back in Spring  1996.  The target
     date for completion and start up is summer 1997.


                              *   *   *   *   *