ADMINISTRATIVE REPORT


                                                      Date: August 22, 1995
                                                      Dept. File No. H764-8


     TO:       Vancouver City Council

     FROM:     General Manager of Engineering Services

     SUBJECT:  Award of Contract No. 9508 -
               Granville Bridge Seismic Upgrading Phase III



     RECOMMENDATION

          A.   THAT  Contract No.  9508  for the  Granville  Bridge  Seismic
               Upgrading Phase  III be  awarded to the  low tenderer,  Peter
               Kiewit  Sons Co.  Limited, in  the amount  of  $4,974,430.00,
               being  the  total tender  including  options,  subject  to  a
               contract satisfactory to the Director of  Legal Services.  No
               legal rights  shall arise hereby and  none shall arise  until
               execution of the Agreement.

          B.   THAT  additional  funding  of  $860,000.00  be  allocated  to
               Granville Bridge Seismic Upgrading  Phase III from  available
               surplus  funding  in Streets  Basic  Capital Accounts  listed
               under Costs and Funding in this report.

          C.   THAT the Director of Legal Services  execute the contract  on
               behalf of the City.


     GENERAL MANAGER'S COMMENTS

          The costs  of the Granville  and Burrard Bridge  seismic upgrades
          have  escalated beyond  those  estimated in  the 1989  consultant
          study.   This is primarily  due to  the lessons learned  from the
          recent  Kobe and  Loma  Prieta  earthquakes  and  based  on  more
          detailed review of the bridge structure.

          The  previously  completed  Phase I  and  Phase  II  work on  the
          Granville Bridge  ensured that  the structure would  not collapse
          during the design seismic event.  Phase III is intended to ensure
          that the bridge will be serviceable within a short time following
          an   earthquake.     Given   the   Granville  Bridge's   critical
          transportation function and                                      
                                                                           
                      its importance with respect  to emergency access,  it
          is  recommended that A, B and C  be approved.  This will complete
          all Phase III work (in fact, all seismic work) for  the Granville
          Bridge.

          Phase III  work for Burrard  Bridge can  be deferred to  the next
          capital  plan.   At  that time,  the  priority for  this  seismic
          upgrading can  be evaluated  in  light of  other capital  program
          priorities.


     COUNCIL POLICY

     Construction contracts over $200,000 are to be awarded by Council.



     PURPOSE

     The purpose  of this  report is to  obtain Council  approval to  award
     Contract  No.   9508  for  the  Granville   Bridge  Seismic  Upgrading
     Phase III.


     BACKGROUND

     The Granville  and Burrard  Bridges are  being retrofitted  to improve
     their performance during  a major earthquake.  In 1991,  under Phase I
     of the seismic upgrading,  the piers supporting the steel  truss spans
     of  the  Granville  Bridge  were  strengthened.    Phase  II  involved
     strengthening  the  steel  trusses  on  both  bridges,  and  this  was
     completed  in 1993.   Yet  to be  completed is  Phase III,  which will
     consist of upgrading the concrete approach spans on both bridges.

     Phase I and II upgrading  designs and cost estimates were prepared  by
     Buckland and Taylor  Ltd.  The same consultant was  engaged in 1994 to
     provide  the   detailed  engineering   design,  and  to   perform  the
     construction administration and inspection for Phase III.  The  design
     has been completed  for both bridges, and tenders were  called for the
     Granville Bridge.  The work consists of  upgrading the north and south
     concrete approach  spans by  modifications to the  expansion bearings,
     installation   of  new   bearings,   dampers  and   longitudinal  deck
     restrainers, steel and fibreglass jacketing of some columns, and post-
     tensioning and concrete encasement of pier cap beams.

     CONSTRUCTION TENDERS

     Tenders  for Contract  No.  9508  for  the  Granville  Bridge  Seismic
     Upgrading Phase  III were opened on July 19, 1995, and referred to the
     General Manager of Engineering Services.

     All  tenders have  been  checked for  completeness  and accuracy.    A
     tabulation  of the  lump sum  tender  prices is  shown below  with the
     lowest tender underlined.

               Additional     Total
             Base   Optional       Tender
            Tender    Work        Price

     Peter Kiewit Sons Co. Ltd. $4,054,430  $  920,000  $4,974,430


     Canron Construction    $4,398,282   $1,287,023   $5,685,305
      (A Division of
       Canron Inc.)

     Pro Industrial
      Contractors Ltd.  $4,831,323   $  730,200   $5,561,523


     The Consultant's  estimated cost  of the  contract work including  all
     options was $4,836,400.  This is  a lump sum contract with unit prices
     for  additions and deletions.   Each Contractor has  submitted a total
     lump  sum tender price including the  GST for the basic contract work.
     In addition and as  required, the Contractors have submitted  separate
     lump sum  prices for five items of optional work, being  the amount by
     which the total lump  sum tender price would increase for inclusion of
     that  optional  work  item.   This  optional  work  consists of  steel
     jacketing  of nine bridge  columns, concrete encasement  of three pier

     cap beams, and post-tensioning of one pier cap beam.

     These options  are items  of work  that have  been  identified by  the
     Consultant  as deferable, meaning they could be done separately in the
     future if sufficient funding were not  available now.  If they are not
     done  now,  the affected  portions of  the  bridge would  probably not
     collapse in an earthquake,  but would suffer much more  severe damage.
     That would cost more to repair and would likely take the bridge out of
     service until the  repairs were  complete.  These  options would  cost
     about $1.10 M including City work and overhead.  It is recommended the
     options be done now with additional funding from Streets Basic Capital
     Accounts as described under Cost and Funding.

     The final cost of  the Contract may vary as  a result of additions  or
     deletions, or extra  or `force account' work if required.   There will
     also be various costs incurred which are not included in the Contract.
     These  will include  work by  City Forces  such as  temporary signing,
     street light removal and replacement, and street reconstruction around
     bridge piers, and City overhead.

     It  is recommended  that  Peter Kiewit  Sons  Co. Limited  be  awarded
     Contract No. 9508 on the basis of their low tender and their company's
     experience with  the type of work required.   This company has several
     years experience in related bridge construction work,  and we consider
     their qualifications adequate for this Contract.


     RELATED ISSUES - GRANVILLE BRIDGE

     There  are several issues pertaining  to the Contract  which have been
     addressed  as follows.  Some of the  construction work at the entrance
     to  Granville  Island  will  require  temporary  street  closures  and
     rerouting  of the  traffic to  Granville Island.   These  closures are
     precautionary to  protect the public during the  lifting of structural
     steel and working platforms.   Granville Island Trust will  only allow
     closure of Anderson Street at night between the hours of 2:00 a.m. and
     7:00 a.m..  The  Contract requires that the noise during  this time be
     minimized.  An  exemption to the  Noise Control  By-Law for this  work
     will be applied for.

     The work at  the north end of  the bridge will  impact on the  parking
     areas and  a leased area  under the  bridge.   There will  need to  be
     temporary elimination of some street parking on Granville Street under
     the bridge.   Also, an area under the bridge  north of Pacific Avenue,
     leased to  Blacktop Cabs,  will  have to  be used  by the  Contractor.
     Under  the lease agreement the City has  the right to use the land for
     bridge related work, and Blacktop Cabs have been advised.


     SEISMIC UPGRADING COSTS

     Tenders  for Seismic Upgrading Phase  III for the  Burrard Bridge have
     not been called, as  it became evident from the  consul-tant's revised
     cost estimate based on  the final designs, that the  funding available
     would  be inadequate to  complete work on  both bridges.   A tabulated
     summary of construction costs for both bridges follows:
               Construction Costs - Granville and Burrard Bridges
                                                                         
     Granville                   Burrard
         Item                      Costs                     Costs 
                                                                    Basic
     Tender Granville       $4.054 M               $2.665 M
     Final Estimate Burrard
     Options                     $0.920 M                   ---

     Contingency, City Work,

     Overhead                    $0.726 M              $0.435 M

     TOTALS                      $5.700 M              $3.100 M

     Funding Available           $4.840 M (1995 Streets        ---         
        Budget)


     At this time, the  estimated costs to complete the Phase III Upgrading
     is   $5.70  M  for  Granville  and  $3.10  M  for  Burrard,  including
     contingencies, City overhead and work by City Forces.  These costs are
     substantially  higher   than  those  based  on  preliminary  estimates
     submitted  by Buckland  &  Taylor in  their  November 1989  report  on
     Preliminary Bridge Seismic Modifica-tions.  Those costs, increased for
     City  work and  overhead, were  $4.00 M  for Granville  and $0.75  for
     Burrard.  These figures  plus an inflation allowance formed  the basis
     of the funding included in the 1994-96 Capital Plan.

     The cost  increases are due to modifications made by Buckland & Taylor
     in the design  concepts of the seismic upgrading work.   This was done
     in   an  effort  to  ensure  a  more  predictable  and  less  damaging
     performance of the bridges during a major earthquake and resulted from
     new information from more recent quakes in California and Japan.   The
     largest cost  increase is $2.35 M  on the Burrard Bridge,  where it is
     now  proposed to  strengthen  the seven  most  critical piers  on  the
     concrete approach spans by  completely encasing them in new  concrete.
     This was previously not included.

     In  consideration of the  fact that the  Granville Bridge is  the more
     important transportation  facility for  access to the  City's downtown
     core, it is proposed that all available funding be utilized to upgrade
     Granville  Bridge, and  to defer  the final  upgrading of  the Burrard
     Bridge to the next  three year Capital Plan. Alternatively,  Phase III
     seismic  upgrading of Burrard Bridge could be done in conjunction with
     the proposed  bicycle/ pedestrian pathway improvements  to effect some
     economy in construction  if surplus funding from  that project becomes
     available.   This  will be  reviewed when  the final  concept for  the
     bicycle/pedestrian pathway has been selected.

     COSTS AND FUNDING - GRANVILLE BRIDGE

     The total  cost  related to  the Granville  Bridge, Seismic  Upgrading
     Phase  III,  including the  construction  Contract No.  9508  with all
     optional  work, associated work by  City Forces, City  Overhead, and a
     contingency, is estimated at $5.70 M.

     Funding of  $4.84 M for Phase  III Upgrading has been  provided in the
     1995 Streets Basic Capital Budget.  Additional funding of $860,000 for
     Phase III Seismic Upgrading can be provided from the following Streets
     Capital Accounts:


     14/02/0397/999     $103,000 Surplus Construction Funds -
                                 V i c t o r i a    D r i v e    B r i d g e
                                 Reconstruction

     14/02/0901/999     $457,000 Unused Phase II Seismic Upgrading
                                 Funds - Granville/Burrard

     14/33/0012/999     $100,000 Surplus Construction Funds -
                                 Granville           Bridge           Safety
                                 Improvements

     14/33/9811/999     $200,000 Surplus Design Study Funds -
                                 Granville           Bridge           Safety
                                 Improvements

                        $860,000


     These  funds  are available  as surplus  as  these projects  have been
     completed at costs below the budgeted funding.




                              *   *   *   *   *