ADMINISTRATIVE REPORT


                                                        Date: July 14, 1995

   TO:       Vancouver City Council

   FROM:     Director, Risk and Emergency Management Division for Emergency
             Management  Committee  (City  Manager,  Chief  Constable,  and
             General  Managers  of Fire  and  Rescue Services,  Engineering
             Services,  and  Parks  and  Recreation) and  General  Manager,
             Corporate Services

   SUBJECT:  Development  of the  Emergency  Operations and  Communications
             Centre

   RECOMMENDATIONS

        A.   THAT Council authorize the planning for and construction of an
             Emergency Operations and Communications Centre (EOCC),  as set
             out  in this  report,  at a  cost of  $14  million, source  of
             funding to be as outlined in Recommendation G to J, following.

        B.   THAT Council authorize participation  of other agencies in the
             EOCC, at  no additonal cost to  the City on the  basis of each
             agency bearing a proportionate share of the total building and
             common facilities costs according to their  space requirements
             and system utilization.

        C.   THAT participating  agencies pay the costs  of any independent
             communications facilities they may require.

        D.   THAT the City Manager be authorized to negotiate participation
             agreements  with other  agencies,  subject to  report back  to
             Council for approval.

        E.   THAT Council instruct the  City Manager to prepare  and report
             on a long term plan for the City communications system, with a
             view to including funding for elements of the plan in the 1996
             Capital Plan.

        F.   THAT Council  authorize the  City Manager to  award consulting
             contracts for detailed design of the EOCC and for  development
             of  the  long  term communications  plan  up  to  $200,000 per
             contract during the Council summer break.

        G.   THAT Infrastructure  Program funding  approved by the  Federal
             and Provincial governments, totalling $6,666,000 be applied to
             the  design and development of  the City portion  of the EOCC,
             land costs excluded.



        H.   THAT the Director of  Legal Services bring forward a  bylaw to
             vary   the  purpose  of   $2,360,000  of  debenture  borrowing
             authority so  that funding  approved in the  1994-1996 Capital
             Plan to replace Firehall 18 may be applied to the EOCC.

        I.   THAT  Council  apply  the  fire insurance  proceeds  from  the
             Sterling Shipyard fire, in  an estimated amount of $2,500,000,
             to the EOCC.  

        J.   THAT Council authorize the  allocation of $2,474,000 from City
             infrastructure funds approved in the 1987-1990 Capital Plan to
             the EOCC.

   CITY MANAGER'S COMMENTS

   The  City  Manager RECOMMENDS  approval  of  the above  recommendations,
   noting that they  are fully supported the Emergency Management Committee
   and the General Manager of Corporate Services.

   COUNCIL POLICY

        There is no specific Council policy which mandates the construction
        of the EOCC.  However, Council has consistently supported effective
        emergency  communications,  both  for  daily   operations  and  for
        response to a  major emergency.  Emergency Planning  was previously
        identified  as a corporate priority,  and is reflected  in the City
        Objectives approved by Council.

        Where  Council  wishes to  vary the  purpose  of funds  borrowed by
        plebiscite,  the Charter  provides authority  to do  so by  a bylaw
        approved by two thirds of Council.

        The City Manager is  authorized to award consulting contracts  to a
        maximum level of $30,000.

   SUMMARY

   The  City's  emergency  services'  communications systems,  like  others
   throughout the  region, are outdated.   As a  result inter-communication
   among and within response  agencies is limited.  Our ability  to respond
   effectively  to any major disaster will be compromised by the weaknesses
   in our present  communications system.  Much of  the system will require
   replacement in the next few years.

   The  City is  building  a new  Emergency  Operations and  Communications
   Centre  (EOCC) which will  centrally locate  emergency dispatch  and 911
   systems  as  well  as  the  City's  Emergency  Operations  Centre  in  a
   seismically secure building.  It makes sense to develop a strategy 


   to upgrade present communications systems in conjunction with the design
   of the new facility.

   The  City and others would  benefit significantly from  a broader multi-
   agency participation in the EOCC.  Co-location offers economies of scale
   and  enhances broader  coordination  of  response  for daily  and  major
   emergencies.    Communication upgrades  could  be  developed and  funded
   across  a  broader  base,  ensuring  both  inter-operability  and  cost-
   effectiveness.

   This  report recommends approval of  funding sources to  fund the City's
   component   of   the   EOCC  and   supplement   the   federal/provincial
   Infrastructure  Program funding  already received.   It  also authorizes
   negotiation  of participation  in  the EOCC  by  other agencies,  at  no
   additional  City cost  and  directs  the  development  of  a  long  term
   communications plan in conjunction with the EOCC project.

   PURPOSE

   This  report   identifies  the   essential  nature  of   City  emergency
   communications systems, both for daily operations and for use in a major
   emergency.  It describes the proposed EOCC and the advantages which will
   flow to the City from its construction.  It  notes the benefit of multi-
   agency participation in the proposed centre and recommends that the City
   seek the involvement of other agencies in its development and operation.

   The report identifies  the cost of the City component of the EOCC at $14
   million, and sets  out sources  of City funds  ($7,334,000) required  to
   supplement  the  funding of  $6,666,000  Infrastructure Program  funding

   approved for the project.

   BACKGROUND

   The City of  Vancouver Fire  and Police Communications  Centres and  the
   Emergency  Operations Centre are located  in buildings (312  Main and #1
   Firehall)  which are vulnerable to damage from earthquake.  In addition,
   since  virtually all  of the  City's communications  infrastructure flow
   through a single  location, it  is vulnerable to  a major, single  point
   failure.  Fire and  Police communications are not  inter-operable, which
   is a significant limitation in an emergency situation.  Further, they do
   not provide  communications capability for work  groups and inter-agency
   task   forces  to  operate  independently.     Police  forces  and  fire
   departments across the region do not  have systems which enable them  to
   communicate effectively with one another in many circumstances.
   These issues have been identified in a number of reviews and reports:

        -    The   Oppal  Commission  identified   the  need  for
             regionally based communications systems;


        -    The B.C. Police Commission review of the Stanley Cup
             riot identified  the need for  improved inter-agency
             communications and an improved  Emergency Operations
             facility;

        -    The Vancouver Police review  of the Stanley Cup riot
             identified  the  need  for  improved  communications
             (some issues have been dealt with);

        -    The Vancouver Fire Department after-action report on
             the  Stanley  Cup  riot  identified   the  need  for
             improved communications.

        -    Council authorized an application for infrastructure
             funding  for a new EOCC, at an estimated cost of $12
             million  excluding land (consistent with the current
             estimate of $14 million for the total project);

        -    Council authorized an initial allocation of $100,000
             to  develop   the  architectural  program   for  the
             required City operations in the EOCC.  This study is
             presently  being  undertaken by  Aitken Wreglesworth
             Associates  in  conjunction   with  Charles   Drulis
             Architects and  is  scheduled  to  be  completed  by
             August 31, 1995.

        -    Vancouver Fire Department outside  agency debriefing
             meeting regarding  the Coast  Guard fire of  July 8,
             1991 recommended the need  to be able to communicate
             with other agencies.

        -    Council   authorized   a   review  of   the   City s
             communications  systems in 1993,  which identified a
             number  of  the  deficiencies  referred  to in  this
             report; and

        -    The  Attorney-General s  Ministry  has indicated  it
             wants to see police  communications in the GVRD move
             to  a  system  which  allows  communications between
             agencies when required.

   For  the most part, emergency  communications systems in  the region are
   outdated,  if not obsolete, and most agencies  will be moving to upgrade
   their systems within the next  few years.  The RCMP has  proposed both a
   new   communications  system  and  consolidation  of  existing  multiple

   dispatch centres to  two to serve  the lower mainland from  Vancouver to
   Hope.   Some municipalities are considering  contracting their Fire dis-
   patch operations  to others.   If significantly  improved systems  which
   provide  the capability for inter-agency  communication on a broad scale
   are to be  implemented, coordinated decisions will  have to be taken  in
   this direction  in the next few years, or a series of independent system
   upgrades  will  perpetuate  the   present  situation  and  preclude  the
   possibility of compatible communications  systems for a very long  time.
   The development of the  Vancouver EOCC offers an opportunity  to achieve
   significant movement  towards this objective, bringing  benefits to both
   the City and other participants.

   DISCUSSION

   The EOCC

   Replacement of the City  dispatch centres, key communications facilities
   and  emergency operations centre in a secure, post disaster building has
   been identified  as a high priority.   Experience in  other cities which
   have suffered  major disasters has  demonstrated the  critical need  for
   good  operational communications.  The  lower mainland is  overdue for a
   major earthquake, and  scientists are unanimous  that the questions  now
   are "when", not  "if", and how big  will the earthquake be.   The recent
   experience  in Oklahoma has demonstrated that no area is immune from the
   potential for  a major  emergency.   Even  the Stanley  Cup  riot --  by
   international  standards,  a  relatively  minor event  --  strained  our
   present communications capabilities.

   Much  of  our  emergency  communications  equipment  requires upgrading.
   While the Fire Dispatch centre has recently been upgraded, virtually all
   the Police dispatch  consoles and  hardware needs to  be replaced.   Our
   present Emergency Operations Centre consists of rooms which are in daily
   use in a seismically vulnerable building, without any of the information
   handling and display  capability contained in  a modern centre,  without
   adequate  work areas,  and without  the support amenities  for prolonged
   operation in the event of a disaster.   The separation of the Police and
   Fire centres  by several city blocks  complicates communications between
   the  two  headquarters.     There  is  little  in  the  way   of  backup
   communications facilities.
   The new  EOCC will address all  these issues.  It  will provide adequate
   space and the communications hardware within the centre will be upgraded
   to a high standard.  The Police and Fire computers will be housed in the
   centre.    Backup power  and  redundant systems  will  ensure continuing
   operation.   Systems to handle and display emergency information will be
    built in .  Just the  fact that Fire and Police communications  will be
   in the  same building and  will be sharing  information in a   situation
   room   will assist  in inter  agency  communication in  the  event of  a
   significant emergency.

   Communications Systems

   Existing  City  communications systems,  like  most in  the  region, are
   outdated.  Much  of our  equipment is well  beyond its normal  operating
   life.   While it continues to operate successfully, channel loadings are
   excessive;  there is  limited  capability to  service inter-agency  work
   groups  or  even  set  up  tactical  communications  for  a  significant
   emergency.  Our systems are vulnerable to incidents which may impact our
   communications plant, which is concentrated in a single location.  We do
   not have provision at  this point for back up  satellite communications.
   Our computer aided  dispatch does  not have the  capability to  transmit
   graphic images.

   Much of this system will  require replacement in the next few  years, at
   considerable cost.   We will need  to consider how  best to provide  the
   capability,  security,  and  redundancy   required  for  good  emergency
   communications.  Some of these decisions may impact on decisions we will

   need to make in regard to the new EOC, particularly with respect to  the
   City s underground plant and the location of the new EOCC.

   Communications technology has developed  significantly.  New trunked and
   digital  radio   systems  offer  substantial  improvements.    Automatic
   location  of units, for  example, enhances  personnel safety  and offers
   operational efficiencies.   Geographical information systems  can now be
   linked to communications systems  to provide image data to  mobile units
   in  the  field.     The  integration  of   communications  and  computer
   capability, even at the level of  computerized telephone systems, offers
   significant enhancements over what currently exists.

   In  addition to enhancing emergency  response, new technology offers the
   opportunity to reduce costs.  For  example, reports can be entered  from
   the field, reducing the need for  staff to spend valuable time reporting
   to the office.   Improved information  in mobile  units will make  field
   operations more efficient thus reducing lost crew time.

   Our systems will require replacement soon as a result of age and lack of
   capacity.   Costs will  be significant  -- perhaps in  the order  of $20
   million -- but we will  have the opportunity to put new  technologies to
   work to increase effectiveness.   Although the need for  replacements is
   not driven  by the new EOCC,  it is sensible  to develop a plan  for the
   redevelopment of our systems  in conjunction with construction of  a new
   EOCC, to maximize the benefit from these expenditures.

   Much  of the required information  to develop a  communications plan has
   been  provided in  a  consultant study  completed in  1993.   This study
   should now be updated,  and a multi year implementation  plan developed,
   with a view to including  appropriate funding in the 1996  capital plan,
   so  that new equipment can  be specified and  purchased for installation
   concurrent with the completion of the EOCC.

   Participation by Other Agencies

   Post disaster  buildings are  more expensive  to construct  than regular
   buildings, and the computer and communications  technology to serve them
   is more complex and costlier.  Co-locating and  consolidating operations
   offers  economies of  scale to  all  participants.   More significantly,
   coordination  of  response   to  daily  and  major  emergencies  can  be
   significantly enhanced.

   Discussions  within  the last  few weeks  have  confirmed that  the B.C.
   Ambulance  Service wishes to participate  in the development  of the new
   EOCC and locate both its regional office and its dispatch  centre there,
   if their financial and operating requirements can be met.  They are also
   requesting that we add the capability to provide computer aided dispatch
   to their units with our existing systems.

   Representatives  of  both the  Provincial  Emergency  Program (PEP)  and
   Police  Services in the Ministry of the Attorney-General have advised us
   that significant  participation by other agencies  could offer operating
   improvements  and efficiencies.   The  Director of  PEP believes  that a
   regional coordination centre where representatives of all municipalities
   and a number  of related agencies  could meet would  be invaluable in  a
   major  emergency.  He has indicated he would seriously consider locating
   the PEP regional office in the new EOCC.  Police Services officials have
   advised that the Ministry  wants to ensure that a  regionally compatible
   police communications system is developed, and  that so long as there is
   an adequate back up facility, consolidation of dispatch operations would
   provide reduced costs and offer the potential for better coordination.
   Staff  from  several  municipalities  have  suggested  that  a  regional
   coordination  centre should be a high priority for the recently approved
   Provincial-Municipal  Liaison Committee  on  Emergency Planning.   Other
   agencies,  such  as  utility   companies,  have  expressed  interest  in
   obtaining  space   for  their  representatives  in   the  new  Emergency

   Operations Centre.

   In view of the timing  of the EOCC, it offers a  significant opportunity
   to bring a number  of elements together, which will  provide operational
   and cost benefits to all participants.  We are recommending that Council
   authorize us to negotiate with interested parties  to obtain commitments
   to participate in the EOCC at the earliest possible opportunity, on  the
   basis that: 

        -    each  agency  bear  a  proportionate  share  of  the
             building  and common  facilities costs  according to
             their space requirements and system  utilization, on
             either a lease or a capital-prepayment basis, and

        -    participating   agencies  pay   the  costs   of  any
             independent   communications  facilities   they  may
             require.

   Funding

   The cost  estimate for the new  EOCC, at $14 million  including land, is
   unchanged from the initial report to Council recommending an application
   for infrastructure  funding.  Discussions  with the Province  during the
   application review process led to a reduction in the elements covered by
   our request, but the overall project estimate remains unchanged.

   With  infrastructure  funding of  $6,666,000,  the  City share  for  the
   project,  scaled to  meet  City needs  only, stands  at $7,334,000.   We
   recommend funding the City share from three sources:


        -    City Infrastructure Borrowing Authority - $2,474,000

   As part of the 1987-1990 Capital Plan, the electorate approved borrowing
   authority of $10 million to fund the City share of an anticipated senior
   government infrastructure program to reconstruct various City works.  To
   date,  $4,657,000 of that borrowing authority has been allocated to fund
   the  City share  of  infrastructure grants  under  the current  federal-
   provincial  program.     This  report  proposes   allocating  a  further
   $2,474,000 to the EOCC.

        -    Reallocation  of  Fire  Hall  Borrowing  Authority -
             $2,360,000

   As part of the 1994-1996 Capital Plan, the electorate approved borrowing
   authority of $2,860,000 for the reconstruction of Firehall 18 (1375 West
   38th Avenue).  This project while  still of critical importance will  be
   deferred until next  Capital Plan  when voter approval  will be  sought.
   The Fire Chief recommends that the funding  be directed to the EOCC as a
   higher priority for voter approved Fire Capital funds at this time.

   Varying the purpose of  capital funds approved by plebiscite  requires a
   bylaw  approved  by  a two  thirds  majority  of Council.    This report
   recommends the Director  of Legal Services bring  forward an appropriate
   bylaw.

        -    Fire Insurance Proceeds

   As a consequence of the fire at the City owned Sterling Shipyards, there
   are insurance proceeds projected  to total $2,500,000.  These  funds can
   be applied to the EOCC.

   Timing

   The  infrastructure program requires that expenditures  be made within a
   limited  period.    Our current  program  calls  for  completion of  the

   facility before the end of 1997.  This will meet the requirements of the
   program,  but leaves  little  time for  the  development of  partnership
   agreements.  We believe that most major partnership agreements will have
   to be concluded by October-November of this year in order for design and
   construction to be completed in time.

   At  this stage  of the  project,  consultant contracts  will have  to be
   awarded  in the  next six  weeks.   In the  absence of  Council meetings
   during  the  break  period, we  are  recommending  the  City Manager  be
   authorized to  award such  contracts, up  to a  maximum of  $200,000 per
   contract.

   In an  earlier report  Council approved  the  award of  the study  phase
   consulting services  to Aitken  Wreglesworth Associates  (architects) in
   association  with   Charles  Drulis  Architects   (EOC  specialist)  and
   Teleconsult Limited (telecommunication).  This study is underway and  is
   expected  to  be  completed in  August  1995.    Given the  satisfactory
   performance of the study team to date it is recommended that their scope
   of work be expanded to include the detailed design phase of the project.
   Aitken  Wreglesworth Associates  have been  requested to  seek proposals
   from structural, mechanical, electrical  and costing consultants for the
   detailed design phase for award in August 1995.

   CONCLUSION

   The development of a new EOCC is a  high priority, and should proceed as
   soon  as  possible.   The provision  of  infrastructure funding  and the
   reallocation of existing City  funding as outlined in this  report makes
   the project possible.  In concert with this project, a plan to redevelop
   the  City s communications infrastructure will ensure that the City gets
   the greatest possible benefit from the expenditure of the EOCC funds and
   the funds which will be required in the near future for upgrades  to the
   communication system.

   Given the  opportunity to enhance regional  communications and response,
   to the benefit  of all agencies including  the City of  Vancouver, major
   efforts should be made to ensure all relevant agencies are  aware of the
   opportunity to partner in the new facility.

   The recommendations of this report set out the basis for the development
   of  the new  facility,  the  opportunity to  develop  it as  a  regional
   facility on a partnership  basis, and identify the required  funding for
   the City portion of the site.



                                  * * * * *