ADMINISTRATIVE REPORT

                                             Date:  June 26, 1995
                                             Dept. File No.   AMH


   TO:       Vancouver City Council

   FROM:     Associate Director of Planning, Land Use and Development 

   SUBJECT:  Re-Approval of Strata Title Conversion - 869-883 East Hastings
             Street

   RECOMMENDATION

        A.   THAT the application  to convert the premises  at 869-883 East
             Hastings Street  (Lot C,  Block 61, D.L.  181, Plan  13940) to
             strata title ownership  be re-approved in principle,  but that
             pursuant  to  Section   9(1)  of  the  Condominium   Act,  the
             Certificate  of Approval (Form 10)  shall not be issued unless
             the following  condition has been  met within one year  of the
             date of this re-approval in principle:

             Completion  of  all   work  required  by  the   City  Building
             Inspector, under the required permits, at no cost to the City,
             and  issuance  of  an Occupancy  Permit,  in  order that  this
             previously-occupied building  substantially complies  with all
             relevant by-laws.

   GENERAL MANAGER'S COMMENTS

        The  General Manager of  Community Services RECOMMENDS  approval of
        the foregoing.

   COUNCIL POLICY

   Council policy is  reflected in the City's Strata  Title and Cooperative
   Conversion Guidelines, which outline factors which Council will consider
   in reviewing  applications for converting  previously-occupied buildings
   to strata title or cooperative ownership.


   PURPOSE

   Council  re-approval is  requested  for the  application to  convert the
   previously-occupied building  at 869-883  East Hastings  Street (Lot  C,
   Block 61, D.L. 181, Plan 13940) to strata title ownership.

   BACKGROUND

   The  site is  zoned M-1 and  is developed with  a three-storey building,
   constructed in 1984,  consisting of  retail uses on  the main floor  and
   offices above.  The location of the building is illustrated in Figure 1,
   below.

                                   Figure 1


































   On  June  14,  1994,  Council   granted  approval  in  principle  to  an
   application  to convert  this building  to  21 strata  lots, subject  to
   completion of upgrading work required by the City Building Inspector and
   issuance of an Occupancy Permit.  That condition has not been satisfied,
   and pursuant  to Council's policy,  the approval in principle  lapsed on
   June  14,  1995.   On  June  21,  1995, the  architect  for  the project
   submitted a request for Council's  re-approval in principle, to be valid
   for a further year.

   The architect has advised staff that he  has been unable to complete the
   required renovations of the building  due to his difficulty in gathering
   information on  the original  construction methods  in the  building and
   performing   new  calculations  with  respect  to  loading  and  seismic
   restraint.  The  architect also cites a  delay in the processing  of the
   building permit application for the upgrading work as a reason that  the
   applicant has been  unable to complete  Council's condition of  approval
   within the one-year time period given.

   STAFF ANALYSIS

   The intent in establishing the one-year limit for completion of Council-
   imposed conditions was not to necessarily expect that-in every instance,
   all conditions  of approval could be  completed within a year.   Rather,
   the  intent was  to terminate  approvals  in principle  where applicants
   clearly had no plans to proceed toward final approval  by completing the
   required works.  Staff were  concerned that either revisions to relevant
   City by-laws  or the possible introduction  of new tenants  who were not
   aware of the strata title approval in principle, could make the approval
   in principle passe.

   Strict interpretation of Council's  policy would lead to  requiring that
   the applicant submit a new  application for the strata title conversion,
   as the request for re-approval was not received within the one-year time

   period when Council's approval in principle was valid.  However, this is
   not a  residential building where  new tenants may have  been introduced
   without being  made aware  of the conversion  proposal.   Further, given
   that the  applicant submitted  an application for  a building  permit in
   March and that  it is now in  process, the City Building  Inspector does
   not believe  that a new  strata title conversion  application, requiring
   payment of  a fee and completion of new  inspections, is warranted.  All
   inspections of the  necessary work will be completed  under the auspices
   of the permits which will be issued.  

   Due to the extensive  nature of the renovations which are  to be carried
   out in  the building, the  City Building Inspector supports  the request
   for re-approval, to be valid for a further one-year period.

   CONCLUSION

   Based on the foregoing,  the Associate Director  of Planning - Land  use
   and Development, supports this application for re-approval.


                          *   *   *   *   *   *   *