ADMINISTRATIVE REPORT


                                                Date: June 14, 1995


    TO:          Vancouver City Council

    FROM:        Director of Social Planning

    SUBJECT:     Capital Grant for Kiwassa Neighbourhood House
                 Phase II Expansion



    RECOMMENDATION

        THAT  City  Council  approve  a  Capital  Grant  of  up  to
        $155,000  to Kiwassa Neighbourhood  Services Association to
        pay  for   one-third  the  cost   of  construction  of   an
        additional  2,400 sq.  ft.  of  activity space  at  Kiwassa
        Neighbourhood  House; source  of  funds  is the  City-owned
        Social  Service  Facilities component  of the  1995 Capital
        Budget.


    GENERAL MANAGER'S COMMENTS

        The General  Manager  of  Community  Services  submits  the
        foregoing for CONSIDERATION.


    COUNCIL POLICY

    Approval  of grant  recommendations requires  eight affirmative
    votes.


    PURPOSE

    The  purpose of  this  report is  to  recommend approval  of  a
    capital  grant   for  a  2,400  sq.  ft.  addition  to  Kiwassa
    Neighbourhood  House.   This  expansion  was  planned for  when
    Kiwassa was first approved and is now necessary to meet program
    demands.


    BACKGROUND

    Construction of Kiwassa  Neighbourhood House (KNH),  located at
    2425  Oxford Street, was completed in June  1992.  It was built
    as part  of a joint social  housing/neighbourhood house project
    on City-owned land.



    The   neighbourhood  house   has   a  total   floor  space   of
    approximately  11,000  sq.  ft.  in   a  two-storey  wood-frame
    building, although only a portion of the second storey has been
    completed.   This facility contains a licensed group daycare, a
    "family  place", a  seniors  centre,  office spaces,  community
    kitchen, and a number of meeting and activity spaces of varying
    sizes.

    When the House was constructed, approximately  2,400 sq. ft. of
    space was deleted from  the plans for the second  floor because
    there  was insufficient funding  available.  This  space was to
    contain  four activity rooms, two  washrooms and a lounge area.
    However,  KNH was constructed in such a manner as to facilitate
    the addition of this  space at some further date,  with minimal
    changes required to the existing building.

    KNH has  initiated the completion of  construction drawings for
    this project, and they  applied for, and received  (on February
    16,  1995) a  development  permit.   With assistance  from City
    staff from Facilities Development,  a firm construction  budget
    has  been established and a fixed price contract will be signed
    with  Tri-Power  Construction Ltd.    Pending  approval of  the
    required funding, construction is scheduled to begin as soon as
    possible to  minimize impacts on KNH programs  and the adjacent
    school during the summer.


    DISCUSSION

    Since the new KNH  was completed, there has been  a substantial
    increase  in the  services and  programs provided.   The  total
    operating budget  grew from  approximately $700,000 in  1990 to
    just under $2 million in 1994.  More than a  dozen new programs
    have been  established and  a minimum  of  3-4 local  community
    groups per  week use  the facility  during the  evenings and/or
    weekends.

    However, the  limits of a space that is smaller than needed are
    beginning  to show.   It now  looks like  one of  the adult ESL
    classes will  have to be  dropped in the  Fall, and one  of the
    non-profit groups which was operating  out of Kiwassa has  been
    asked  to relocate - all because of  a lack of space.  Requests
    for  new programs or use of space by community groups have been
    refused or put  on hold.  All levels of government are pursuing
    models  of integrated  service  delivery, yet  the one  obvious
    location  for  establishing  such  programs,  Kiwassa,  is  not
    available because of insufficient space.







    FUNDING

    As of December 31, 1992, total expenditure for the new KNH were
    $1,890,000.  The sources of funding were:

        City of Vancouver              $  367,000
        GO B.C.                            575,000
        Kiwassa fund-raising              948,000
                                       $1,890,000


    The  site and  building are owned  by the  City.   The site was
    purchased  with  City  funds  which were  reimbursed  from  the
    disposition  of the previous KNH site, resulting in no net cost
    to the City.  Thus, for an investment of $367,000, the City has
    acquired  an asset  worth  almost $2,000,000.   Similarly,  the
    relatively  small Community  Services Grant  ($51,000 in  1995)
    given annually to  KNH supports an  operating budget almost  40
    times as large.

    The  budget for the phase II expansion is $465,800, broken down
    as follows:

        Construction                      $404,650
        Architect and consultant fees       43,500
        Administrative costs                11,400
        Equipment and furnishings           22,750
                                          $482,300
        Minus GST rebate                    16,475
                                 Total    $465,825


    KNH has  already secured 2/3 of  the needed funding.   It has a
    firm commitment for  federal-provincial infrastructure  funding
    up to a maximum of $310,550, subject to securing the balance of
    $155,275 from other sources.

    The  City   1994-1996   Capital  Plan   specifically   provides
    $2,225,000 (1993 dollars) for the development, redevelopment or
    relocation  of City-owned social  service facilities.   Council
    allocated $450,000 of this amount for 1995 projects.  Staff had
    anticipated  that an application from  Kiwassa would be part of
    the 1995 program, and  are recommending approval of a  grant of
    up to $155,000.






    Approval of this grant will not set a precedent with respect to
    other groups which may  have received infrastructure funding as
    none of the other groups which have been  funded qualifies as a
    social service  facility.   Council  set aside  funding in  the
    Capital Plan  specifically for  City-owned social  services and
    the Kiwassa application is clearly an eligible facility.

    Kiwassa could,  in  theory,  be  asked to  fundraise  money  in
    addition to the  2/3 funding  it has already  secured.   Social
    Planning staff concur  with KNH's assessment that this would be
    very difficult  since Kiwassa  raised $948,000 less  than three
    years ago and is currently doing ongoing operating fundraising.
    There   are  also  other  major  capital/operating  fundraising
    campaigns currently  underway (e.g., Vancouver  Public Library,
    Collingwood Neighbour-hood House, YWCA Capital  Program), which
    could compete with a second Kiwassa campaign.

    Approval of the City grant at this time will allow construction
    to occur over  the summer,  minimizing effects on  KNH and  the
    adjacent school.

    The actual amount of the  City grant will be determined  on the
    basis  of reimbursement of one-third of actual costs, up to the
    maximum approved.  In keeping with past practice on the payment
    of  Capital Grants, we propose  to provide half  the grant when
    construction  begins,  and the  remainder,  up  to the  maximum
    amount approved, will be paid upon completion of the project.


    CONCLUSION

    Although  the  new  Kiwassa  Neighbourhood  House facility  was
    completed  only  three  years  ago,  it  was  known  then  that
    additional space would  be required  to meet the  needs of  the
    neighbourhood.  It is now possible that the  complete facility,
    as  originally  planned,  can  be finished.    The  recommended

    funding from the City will make this plan a reality.



                           *   *   *   *   *