Appendix 1

           
          Appendix 1
           
           
           
    2000-2002 2000 2000
    Capital Plan (1) Budget Borrowing Revenue
    $000's $000's $000's $000's
           
Public Works          
  Streets & Bridge Infrastructure $10,715 $3,980 $3,700 $280
  Pedestrian and Cycling Facilities $9,900 $3,370 $3,320 $50
  Transit and Safety Improvements $12,430 $4,910 $4,670 $240
  Local Area Improvements $13,000 $5,010 $3,325 $1,685
  Communications & Street Lighting $5,147 $1,412 $473 $939
  Sewers $51,045 $17,015   $0
  Yards $15,928 $3,000 $3,000 $0
Total Public Works   $118,165 $38,697 $18,488 $3,194
           
Parks & Recreation          
  Recreation Facilities $13,046 $3,110 $2,672 $438
  Park Development $13,504 $6,776 $6,624 $152
  Land Acquisition $3,325 $1,045 $1,045 $0
  Debenture & Overhead Charges $1,625 $550 $550 $0
Total Parks & Recreation   $31,500 $11,481 $10,891 $590
           
Public Safety          
  Fire - Hall Replacement/Upgrading $3,050 $710 $710 $0
  Police - Outfit CIS Building $857 $857 $857 $0
  Police - Dog Squad Relocation $450 $450 $0 $450
Total Public Safety   $4,357 $2,017 $1,567 $450
           
Community Service Initiatives          
  Social and Cultural Facilities $4,100 $475 $0 $475
  Affordable Housing $2,500 $0 $0 $0
  Downtown Eastside Initiatives (2) $2,500 $315 $0 $315
  Public Art on Capital Projects $750 $250 $0 $250
Total Community Services Initiatives   $9,850 $1,040 $0 $1,040
           
Other          
  Library Facilities Planning $500 $0 $0 $0
  Civic Theatres Upgrade $350 $350 $0 $350
  Facilities Development $1,500 $820 $0 $820
  Civic Property Maintenance $5,900 $2,150 $0 $2,150
Total Other   $8,250 $3,320 $0 $3,320
           
Supplementary Capital   $5,000 $1,906 $0 $1,906
           
Total - Capital Plan / Capital Budget Funding   $177,122 $58,461 $30,946 $10,500
           
  Waterworks $58,950 $18,350 $18,350 $0
           
Total, Including Waterworks   $236,072 $76,811 $49,296 $10,500
           
           
1. The 2000-2002 Capital Plan and 2000 Capital Budget summaries include the following funding carried forward from prior Capital Plans:        
           
  1991-1993 Capital Plan - Grandview Cut Bridges   $1,038,500    
  1994-1996 Capital Plan - Granville Bridge Safety Improvments   $226,500    
  1994-1996 Capital Plan - Outfit CIS Building   $857,000    
      $2,122,000    
           
2. On March 16, 2000, Council allocated $315,000 from the Capital Plan allocation for Downtown Eastside Initiatives to two economic        
  development initiatives, the Tenant Improvement Assistance Program and the Lease Subsidy Program.