Agenda Index City of Vancouver

ADMINISTRATIVE REPORT

TO:

Standing Committee on Transportation and Traffic

FROM:

General Manager of Engineering Services and Directors of City Plans and Central Area Planning in Consultation with the Director of Finance

SUBJECT:

Transportation Priorities and Resource Needs - Overview Report

 

RECOMMENDATIONS

B. THAT the Rapid Transit Project Office be requested to share in the cost of the Engineering Services associated with the planning, design and implementation of the East-West Rapid Transit Line and the cost of providing planning information to the Rapid Transit Project Office and the Special Commissioner - SkyTrain Review.

a) the detailed work program and funding to complete the Downtown Transportation Plan; and

GENERAL MANAGER'S COMMENTS

CITY POLICY

Council has approved a number of transportation policies which serve to guide the establishment of priorities and funding. These include:

On May 27, 1998 Council approved a number of policies in the Vancouver Transportation Plan as follows:

- Prepare a Transportation and Circulation Plan for the Downtown, including a complete review of the downtown transit system to improve services and choice, improve regional connections and airport links, evaluate alternative transit vehicles (such as minibuses), establish priorities for "great streets", improve route and destination signage, create pedestrian priority areas and implement bike lanes and street improvements.

- Undertake regular monitoring and reviews of transportation services and use, to establish how transportation patterns are developing, and to recommend additional polies and measures needed to achieve the Transportation Plan policies and targets.

- Undertake a regular review of Transportation Plan implementation, which will be the basis for recommendations for transportation components in the City's three year Capital Plan.

- Review building lines in the context of the Plan with a view to removing those that are unlikely to be needed and adding others where priorities have developed.

On September 8, 1998 Council approved the following:

- That the City will collaborate with the Province on the planning for the ART route, alignment, station locations and station area planning, while continuing to resolve issues through the GVTA about cost sharing and completion of the entire T-Line.

- To report back on the terms of reference and cost of an independent consultant study, reviewing the basic decision of the SkyTrain technology and corridor.

PURPOSE

There are a number of transportation initiatives underway or in the planning stages for the remainder of this year and 1999. These initiatives have significant staff resource and funding implications. The purpose of this report is to bring them together so that Council can view the full work program in order to establish priorities and funding.

DISCUSSION

There are currently a number of major transportation initiatives underway or in the planning stages. These arise largely from active projects such as rapid transit, or from action steps arising out of the transportation plan. These projects, to be successful, will require a commitment of new resources.

In addition, there are a number of other transportation projects or programs which are part of ongoing initiatives or have been previously committed.

The time lines established for the Rapid Transit Project are incredibly short and place unreasonable demands on the City to respond. In addition, our response is undertaken with inadequate data and limited public consultation. Nonetheless, our response and the resources recommended attempt to cope with this reality.

Finally, the proposals in this report represent our understanding of the situation today and our response, including costs, may have to be adjusted in the future.

A brief description of each of the major and ongoing projects follows:

Rapid Transit Project

1. Phase I - East-West Boundary to VCC

2. Phase II - East-West VCC to Arbutus

3. Phase III - East-West Arbutus to UBC

4. North-South Richmond - Downtown

Further information on the work program and resources required to respond to the Province's 1998 and 1999 Rapid Transit Program are outlined in a companion report. The total funding identified at this time is $1,794,000 for Phases I and II.

RAPID TRANSIT TECHNOLOGY AND ALIGNMENT STUDY

At its September 8, 1998 meeting, Council requested staff to report back on the basic terms of reference and costs of an independent consulting study reviewing the basic decision of SkyTrain technology and corridor. A companion report summarizes this material and suggests that this study is taking on increasing relevance for the section of the Rapid Transit Project west of Commercial Drive, including an extension to UBC.

Staff recommend that a study be funded in the amount of $200,000 to undertake a review of the Phase II Rapid Transit Project and Corridor. While the City needs to direct this work in order to ensure its independence, it is proposed that cost sharing be sought from the RTPOand the GVTA. The Study would be closely tied to the review of a UBC extension that Council recently approved.

TRANSPORTATION PLAN ACTIONS

In May 1997, Council approved the Transportation Plan, including a number of action steps to implement its policies. Council was advised that most of the actions could be undertaken within existing staff resources and budgets if phased in over a number of years. However, two major actions were identified that require additional staff resources in order to complete; the Downtown Transportation Plan and the Transportation System Monitoring Proposal.

Staff have been preparing detailed proposals on these major actions and these are summarized below:

1. Downtown Transportation Plan

2. Transportation Plan Monitoring

3. Building Line Review

OTHER TRANSPORTATION PROGRAMS/PROJECTS

There are a number of other committed transportation programs/projects which are underway or are scheduled to commence in the near future. While many of these programs do not require significant resources, they nonetheless constrain our ability to respond. A partial listing of these projects include the following:

· Major Roads criteria and network designation.

· Richmond Rapid Bus follow-up and implementation.

· HOV proposal review and response.

· Proposal to review street furniture design.

· Pedestrian priority area planning.

·
Rail rights-of-way review.

There also are large staff commitments to on-going programs such as implementation of the bikeway plan, neighbourhood traffic calming and greenways. It is not recommended that efforts be diminished in these areas. Furthermore, with the implementation of the GreaterVancouver Transportation Authority, there may be additional staff resources required, particularly as we develop closer relationships with the transit function. This need has not been programmed into the work plan.

It should also be noted that some resources have already been diverted into the transportation area at the expense of non-transportation related projects.

FUNDING CONSIDERATIONS

The total costs of the transportation study needs exceed current resources by a considerable margin. Table 1 summarizes the costs:

TABLE 1

PROGRAM

TOTAL
COSTS

OTHER
SOURCES

NET
COST

COMMENTS

Rapid Transit Project

- Phase I East-West
(Boundary to VCC)

- Phase II East-West (VCC to Arbutus)

Staff $1,050,400

Expenses 513,600

Expenses 230,000
Total $1,794,000

Existing Staff
$333,000

$1,461,000
less utility
engineering
$ 117,200
$1,343,800

RTPO share to be determined, but $117,200 in utility engineering would not be undertaken unless cost shared.

- Phase III East-West
(Arbutus to UBC)

$ 30,000

$ 15,000 appr
$ 15,000 UBC

0

Already funded.

- Phase IV North-South
(Richmond to Downtown)

0

   

Awaiting further information on timing.

Rapid Transit
Technology

$ 200,000

 

$200,000

Possible cost sharing by RTPO or GVTA

Transportation Plan
Initiative

-Downtown
Transportation Plan

- Plan Monitoring Program

- Building Line Pilot Project

Staff - $365,000
Expenses - 235,000
Total 600,000

$280,000

Staff - $ 40,000
Expenses 5,000

Existing Staff

Existing Budget
$168,000


$ 40,000

Preliminary cost still being refined and discussed.

$112,000


$ 5,000

18 month program scheduled over a 2 year time frame.

Annual costs with special studies scheduled over next 10 years.

TABLE 1 (Continued)

There are two basic options for Council to consider in funding this work:

1. Fund all or a portion of the work.

2. Reallocate further existing resources in Engineering and Planning.

3. Defer participation in corridor and station-area studies.

The second option is not recommended as staff have already been allocated to this project at the expense of ongoing activities. To allocate further staff would undermine the existing work program resulting in the deferral of important ongoing programs or in missed commitments. If Council wants to explore this option further, staff can provide further details.

The last option is not recommended, as this work should not be deferred given the Project schedules and is too important to not address the impacts of the Rapid Transit system.

Rather, staff recommend that the Rapid Transit work be undertaken including Phase I, Phase II, and Phase III and the Technology/Alignment Study.

The work associated with the Transportation Plan follow-up actions, specifically the Downtown Transportation Plan and Monitoring Program, can be deferred. This deferral is not without a cost. Important transportation issues in the downtown core will not be addressed in a timely manner and there may be lost opportunities. Similarly, the plan monitoring program is designed to provide information on the performance of the transportation system and the effectiveness of the City's policies and programs. Again, opportunities for corrective actions may be missed. Nonetheless, this work can be delayed and reviewed in 1999.

FUNDING SOURCE

This report recommends that Council provide funding for the Rapid Transit Study at a cost of $1,543,800. The 1999 Operating Budget envelope approved by Council on October 22, 1998 does not provide funding for this work. As a result, funding for any work that Council does approve will require a further increase in property taxes or a reallocation of funding within the envelope.

If Council wishes to proceed with the work program recommended in this report, the Director of Finance recommends that funding be provided from a reallocation of the Capital from Revenue provision in the 1997-1999 Capital Plan. The annual provision for Capitalfrom Revenue is allocated to specific program areas or to individual projects. Reallocation of those funds means that Council will have to eliminate or, at least defer for future consideration, work of equal value that had been approved as part of the current Capital Plan. This step has already been take once during the current plan when funding for downtown south park acquisition was reallocated to higher priority programs/projects.

If Council approves the Advanced Rapid Transit planning project, $33,000 related to 1998 expenditures will be funded from the 1998 Operating Budget (Contingency Reserve). The cost of the 1999 portion of the program ($1,510,800) is recommended to come from a reallocation of Capital from Revenue, as follows:

Approval of the projects submitted for Council consideration (Consideration Items E, F and G), will require reallocation of additional capital funding. If Council chooses to proceed with these projects, the Director of Finance should be requested to report back with a funding source prior to proceeding with the work.

* * * *


tt981103.htm


Comments or questions? You can send us email.
[City Homepage] [Get In Touch]

(c) 1998 City of Vancouver