Agenda Index City of Vancouver

POLICY REPORT
URBAN STRUCTURE

TO:

Vancouver City Council

FROM:

Director of City Plans and General Manager of Engineering Services

SUBJECT:

ALRT Consultation and Work Program

 

RECOMMENDATION

CONSIDERATION

CITY MANAGER'S COMMENTS

COUNCIL POLICY

On April 30, 1998, Council adopted a number of principles to guide planning the light rapid transit system in the Broadway corridor, attached as Appendix A.

On July 21, 1998, Council resolved that: "THAT Planning staff report back with an action plan for the Broadway and Commercial area that identified issues and opportunities for change that could be undertaken in conjunction with the planning process for the new rapid transit line, within the time frame and resources that are available."

On July 30, 1998, Council resolved that: "THAT Council run its own public process regarding the Province's LRT Proposal, and co-ordinate with the Provincial process, and an advertisement be placed advising the public of this decision."

PURPOSE

This report outlines options for a consultation strategy for Vancouver's portion of the Rapid Transit Project, and recommends that the City proceed with a collaborative planning process with the Province to determine route alignment and station locations subject to concerns about cost and phasing being resolved.

BACKGROUND

1. Provincial Rapid Transit Project

Figure 1: Transit Routes Announced by Province, June 24, 1998

2. Provincial Project Management and Decision-Making

DISCUSSION

1. Provincial Project Assumptions

2. RTPO Consultation Process

CONCLUSION

The Rapid Transit Project Office is embarking on a community consultation process based on the Skytrain technology. There is also a commitment by the Province to complete the full T-line, but this requires a new set of cost-sharing negotiations between the Province and the GVTA. The GVTA is not committed to cost share in the Project unless there is agreement on the scope, design and cost of the Project.

It is recommended that the City participate with the Project Office in the planning for the Project subject to successful Provincial/GVTA negotiations. Through a joint planning exercise involving the public, the City can most effectively bring its agenda to the table. This will achieve a far better product at the end of the day. It is important that the Skytrain alignment and stations are properly integrated into the communities with mitigation of the negative impacts. This was not achieved on the original Skytrain Project.

It is not recommended that the City undertake separate and parallel studies evaluating the Skytrain technologies. It is believed that this will reduce the City's effectiveness in the planning process for Skytrain and send very mixed confusing messages to the communities involved in the planning and design activities. This would be a costly venture drawing limited City resources from the Project activities. There are many unanswered questions on Skytrain, but these are better evaluated by the GVTA or GVRD.

PROPOSED PRINCIPLES FOR LRT PLANNING IN VANCOUVER:

Principle 1: Supply a High Level of Transit Service. The LRT system should provide transit services to meet existing and expected growth, as detailed in the Vancouver Transportation Plan and Transport 2021. LRT ridership capacity and service should be provided to help to meet the mode split targets set out in the Transportation Plan.

Principle 2: Serve the City's Land Use, Not Shape It: LRT should support the planned development pattern and form of Vancouver's Broadway Corridor which already provides for significant residential and commercial development. LRT is not intended to justify significant increases in residential densities or significantly alter the City's
land use pattern along the line.

Principle 3: Provide a High Standard of Urban Amenity: LRT should enhance the emerging urban design character and pedestrian amenity of Central Broadway. It should recognize central Broadway as a "Great Street".

Principle 4: Enhance Local Transit Service: In Vancouver, the transit system should provide a high level of local service to supply sufficient capacity to satisfy demand and to encourage transit use. Upon entering Central Broadway, the system should offer closer-spaced stops to encourage frequent use for all kinds of trips.

Principle 5: Linkage to Transit Services: The system must allow for effective connections with existing and future transit services, including future possible LRT extensions to downtown Vancouver, UBC and southern communities.

Principle 6: Minimize and Mitigate Impacts: Adverse community, pedestrian and traffic impacts should be minimized, and the cost of impact mitigation should be included in overall project costs. Evaluate the magnitude of and rationalize the displacement of local, circulating and through traffic on Broadway and north-south streets.

Principle 7: Provide for Meaningful Involvement of Affected Parties: The public consultation process should address the different ways that communities and other stakeholders may be affected by implementation of LRT in the City of Vancouver.

Principle 8: A Collaborative City Role: The preferred working relationship between the LRT project and the City is viewed as one that will permit timely and thorough City involvement in planning for and review of LRT route options and selection of a preferred option.

Principle 9: Minimize the Impacts of Construction: A project of this magnitude will take several years to construct with the potential for impacts on adjoining land use and traffic. A plan is required to minimize this disruption.

CITY ROLE IN TRANSIT PLANNING AND CONSULTATION PROCESS

[NOTE FROM CLERK: GRAPHIC NOT AVAILABLE - ON FILE IN THE OFFICE OF THE CITY CLERK]

PHASE 1: COMMUNITY INFORMATION

Purpose: to provide basic information to the public about Provincial assumptions:

Timing: September, 1998 to November, 1998

Format: mall displays, press, open houses

Staff role: monitor Provincial information-sharing; advise community of existing City policies and concerns; conduct community meeting to hear issues, concerns and opportunities; report to Council

City Role: Continue to negotiate cost-sharing, etc through GVTA; challenge Provincial assumptions as required. Province has ultimate decision-making authority over technology, corridor, phasing , etc.

Commentary: The RTPO and its consultants will lead this information phase with a similar format of open houses for the entire line. However, City staff will provide opportunities for concerns, issues to be raised and reported to Council.

PHASE 2: COMMUNITY ADVISORY

Purpose: to elicit public input and preferences into considerations of :

Timing: November, 1998 to early 1999 (length of this phase still being determined)

Format: open houses, workshops, newsletters and questionnaires

Staff role: collaborate in information and consultation process providing policy framework and analysis to the community on options

City Role: The RTPO has indicated that decisions about alignment,.station location, program and amenities will be made jointly although in the context of larger route/technology.

Commentary: In this phase City staff will share the lead the workshops with the RTPO to get direct community input on issues and preferred options and will report these to Council with commentary on consistency with City policy, feasibility, cost, etc.

PHASE 3: COMMUNITY JOINT PLANNING

Purpose: to seek community preferences about:

Timing: January 1999 - for up to two-year period

Format: open houses, workshops, newsletters and questionnaires

Staff role: Staff will lead the station area planning process with RTPO liaison

City Role: Council has decision-making authority regarding land use policies and City streets. Staff will report on mitigation measures, land use changes, traffic calming, pedestrian linkages, etc.

Commentary: The City will control this phase of the process but will need to continue to liaise with the RTPO on system station construction, construction mitigation and provision of implied promised amenities by the Province, etc. At this time, it is not clear if the present budget is adequate for mitigation measures, since impacts have not yet been identified.

APPENDIX C

DRAFT OF NEWSPAPER ANNOUNCEMENT

[NOTE FROM CLERK: APPENDIX C NOT AVAILABLE ON LINE - ON FILE IN THE OFFICE OF THE CITY CLERK]

* * * * *


ag980908.htm


Comments or questions? You can send us email.
[City Homepage] [Get In Touch]

(c) 1998 City of Vancouver