ADMINISTRATIVE REPORT
Date: January 12, 1998
Author/Local: J. Griffin/7928
CC File No. 5802
TO:Vancouver City Council
FROM:General Manager of Engineering Services
SUBJECT:Local Improvements Subsequent Procedure -
Court of Revision February 3, 1998
RECOMMENDATION
A.THAT the projects "by petition" in Court #582 be approved.
B.THAT the projects by "Initiative Principle" in Court #583 be approved except for the defeated items and special items #4, #24, #34, #42 and #43 as explained in this report.
COUNCIL POLICY
Policies governing the Local Improvement process are set out in the Vancouver Charter and the Local Improvements Procedure by-law.
PURPOSE
Projects by Petition and on the Initiative Principle have been advanced under the provisions of the Local Improvements Procedure By-law and will come before a Court of Revision on February 3, 1998.
The projects are identified as follows:
Court Item Type
Petition
#582 1-27 Lane Lighting
28-29 Pavement, Curbs & Trees, Higher Zoned
30-35 Pavement, Curbs & Trees, Local Residential
36-37 Lane Pavement, Higher Zoned
38-60 Lane Pavement, Local Residential
61-64 Speed Humps
65 Pedestrian Collector Sidewalk
66 Sidewalk
Items
Court Item Defeated Type
Initiative
#583 1-4 1 Pavement, Curbs & Trees, Higher Zoned
5-9 6 Pavement, Curbs & Trees, Local Residential
11-15 Lane Pavement, Higher Zoned
17-18 Speed Humps
19-38 19,21,25,33, Pedestrian Collector Sidewalks
36,37
39,40,42-46 39,44,45,46 Sidewalk Reconstruction
SPECIAL ITEMS
Court #583, Item #4, Pavement, Curbs & Trees
Pandora Street from Salsbury Street to Victoria Drive
Objections for the above project have met the minimum number required for defeat, (10 out of 18) but the assessed value represented by these objections have not met the required 50% of total assessed value. Due to the majority of property owners objecting, we recommend this project not proceed.
This project was recommended, along with other improvements, by the Neighbourhood Integrated Service Team of this area to help reduce the prostitution trade. The Team also agrees that this improvement should not proceed if a majority of the property owners are opposed.
Court #583, Item #24, Pedestrian Collector Sidewalk
Inverness Street, West Side, from 64th Avenue to S.E. Marine Drive
It is being recommended that this project be reduced in scope to Inverness Street, West Side, from the lane south of 64th Avenue to S.E. Marine Drive. There are two owners on this project, one owner is opposed and the other owner supports the project.
The following three projects are being recommended not to proceed. Due to the mail strike, there was insufficient time to advise owners of a revision to the original notification.
Court #583, Item #34, Pedestrian Collector Sidewalk
42nd Avenue, North Side, from Montgomery Street to the lane west of Oak Street
Court #583, Item #42, Sidewalk Reconstruction
Clark Drive, East Side, from Kingsway to the lane south of Kingsway
Court #583, Item #43, Pedestrian Collector Sidewalk
Kingsway, South Side, from Knight Street to the west property line of Lot 2 of C & D of 1-3 Block 13 DL 301 Plan 8410
Capital Funds
Funds for the City's share of the projects are available from existing Engineering Department Basic Capital Accounts or are subject to approval of the 1998 Streets Basic Capital Budget.
* * * * *