POLICY REPORT
                                URBAN STRUCTURE

                                           Date: July 17, 1997
                                           Dept. File No. PB
                                           CC File: 5301

   TO:       Vancouver City Council

   FROM:     Director of Community Planning

   SUBJECT:  RS Options - Kitsilano RS-1S Area


   RECOMMENDATIONS

        A.   THAT the Director of Land Use and Development be instructed to
             make application to rezone the Kitsilano RS-1S area shown in
             Figure 1 from RS-1S to RS-5S and the application be referred
             to Public Hearing; and

             FURTHER THAT the Director of Legal Services be instructed to
             prepare the necessary by-law for consideration at the Public
             Hearing.

        B.   THAT the Director of Community Planning be instructed to
             report to Council development applications which are contrary
             to the proposed zoning amendments for possible withholding
             pursuant to Section 570 of the Vancouver Charter.

   GENERAL MANAGER'S COMMENTS

        The General Manager of Community Services RECOMMENDS approval of A
        and B.

   COUNCIL POLICY

   On June 6, 1995, Council asked staff to report back on interim measures
   to deal with neighbourhood requests for character zoning until such time
   as staff are able to go back into those neighbourhoods to work with them
   on the CityPlan Neighbourhood program.

   On May 17, 1996, Council instructed staff to proceed, in co-operation
   with neighbourhood groups, with a consultation process to determine
   neighbourhood support for an interim zoning in single-family areas in
   advance of CityPlan's Neighbourhood Visioning program, to proceed with
   RS-6 as an interim zone available to RS-1 and RS-1S single-family
   neighbourhoods and, where there is demonstrated community support, to
   include RS-5 as a possible interim zone for single-family
   neighbourhoods.

   SUMMARY AND PURPOSE

   This report recommends referral to Public Hearing of RS-5S zoning for
   the portion of Kitsilano currently zoned RS-1S illustrated in Figure 1
   below.

   A multi-language random sample telephone survey of area residents and
   property owners was conducted in the area. The survey indicated that
   there was roughly 64% support for a zoning change to deal with concerns
   about the design of new developments and landscaping. Of those in favour
   of a zoning change, 59% preferred RS-5S zoning.

   RS-5S zoning encourages new development and additions to be compatible
   with the neighbourhood by providing a floor space increase if the
   RS-5/RS-5S Design Guidelines are followed. If followed, the design of
   new houses and major additions along with site landscaping would be
   derived from the design of properties near to the development site.

   Figure 1. Proposed RS-5S District - Kitsilano RS-1S District

   BACKGROUND

   On May 17, 1996, Council adopted a process to implement the interim
   zoning program requested by Council on June 6, 1995. The program
   addressed issues of external design and site landscaping in RS-1/RS-1S
   neighbourhoods. RS-6/RS-6S zoning is offered with the additional option
   of RS-5/RS-5S zoning where there is demonstrated community interest in
   that zone.

   RS-5 and RS-5S zones (RS-5S is a new zoning approved at Public Hearing
   on July 8, 1997, to replace RS-1S zoned areas) encourage new houses and
   additions to be compatible with existing houses and landscaping by
   providing a floor space increase in exchange for going through a design
   guideline review process. Buildings which meet design guidelines derive
   their design from nearby houses and site landscaping. "Impermeability"
   regulations prohibit excessive paving of the site. When the guidelines
   are used, the permit process in this zone typically takes two to three
   months for a development permit, one to three weeks for the building
   permit. For those who do not seek a floor space increase but build to an
   above basement floor space slightly less than the maximum permitted
   under RS-1, no design review occurs and applicants are only required to
   follow district schedule regulations. For these applications, joint
   planning/building permits take approximately one to three weeks.

   RS-6 and RS-6S zones (RS-6S hasn't as yet been chosen by an RS-1S
   neighbourhood nor has it been referred to Public Hearing) require or
   prohibit certain design features, and encourage site landscaping in
   order to establish a minimum standard of design quality and foster a
   greater variety of design than under RS-1 zoning. "Impermeability"
   regulations prohibit excessive paving of the site, and a modest floor
   space increase is provided if landscape design guidelines are followed.
   The combined Development Permit and Building Permit process in this zone
   takes approximately three to five weeks.

   The Council-approved planning process for the interim rezoning program
   involves three steps:

   1.   Phase I - This phase determines the general level of neighbourhood
        support for a change in zoning. Only after neighbourhood support is
        demonstrated does Planning commit significant time and resources to
        a rezoning process. This first step is therefore carried out in
        co-operation with resident groups who assist in notifying area
        residents/ property owners of the planning program. A post-returned
        "expression of interest" survey is then conducted among all area
        residents and property owners. This survey is monitored or carried
        out by Planning staff. If the survey achieves a 25% response rate,
        and if 60% of the respondents to the survey support a change in
        zoning, then staff proceeds with Phase II.

   2.   Phase II - This phase determines the type of single-family zoning
        which the neighbourhood supports. Staff distribute more detailed
        information on RS-1/RS-1S, RS-5/RS-5S and RS-6/RS-6S zoning to all
        area residents and property owners and hold an open house.
        Following this, an independent consultant is used to conduct the
        Phase II survey as a multi-language random sample telephone survey.
        Typically, for a neighbourhood of roughly 2,000 households, 700 are
        contacted leading to the completion of approximately 400 interviews
        (taking into account people who are not home or who refuse to be
        interviewed). This yields statistical results at a 95% confidence
        level with a plus or minus 5% margin of error. A 60% support rate
        for a new zoning is adequate for staff to refer a rezoning report
        to Council.

   3.   Staff report back to Council on the Phase II survey results with a
        recommendation on the area zoning and, where appropriate, referral
        to Public Hearing.

   DISCUSSION

   1.   Planning Process

   (a)  Phase I Resident Surveys

   Phase I surveys were conducted in Kitsilano in May of 1997. The results
   of the Phase I survey can be summarized as follows; the response rate
   (i.e., total surveys returned/total surveys delivered) was 28%:

    Question 1: Which     a) Retain the  b) Seek an   c) Undecided
    option do you         current RS-1S  alternative
    prefer?               zoning         zoning

                               35%           64%            1%

   The results of the Phase I survey indicated that there was sufficient
   support in these areas to proceed onto Phase II of the Interim Zoning
   process: there was a greater than 25% response rate and more than 60% of
   those responding supported a change in zoning.

   (b)  Phase II Telephone Surveys

   In June of 1997, staff distributed detailed information on RS-1/RS-1S,
   RS-5/RS-5S and RS-6/RS-6S zoning to all residents and property owners in
   the Kitsilano RS-1S area (see Appendix A). Contained in the information
   package were staff phone numbers in order that questions could be asked
   and responses given. Multi-lingual "call back" lines were set up for
   people with English as a second language. All distributed material was
   translated into Chinese. An open house (with translation services) was
   held in the area to answer questions and display additional, more
   detailed information about the zoning.

   The random sample telephone survey of area residents and property owners
   was conducted by an independent consultant towards the end of June. With
   approximately 500 completed phone surveys in the Kitsilano RS-1S area,
   the accuracy of the resulting statistics is roughly plus or minus 4% at
   a 95% confidence level. The survey results are as follows; a full
   detailed report is available from the Clerk.


    Question 1: Which     a) Retain the  b) Seek an   c) No opinion
    option do you         current RS-1S  alternative
    prefer?               zoning         zoning
                               31%           64%            5%


    Question 2: If you    a) RS-5/       b) RS-6/     c) Undecided
    preferred to seek an     RS-5S          RS-6S
    alternative zoning
    [1(b) above], which
    zoning option do you
    prefer?

                               59%            37%           4%

   The Phase II survey indicates that the Kitsilano RS-1S area has
   approximately 64% support for a zoning change to deal with concerns
   about the design of new houses and landscaping. Of those in favour of a
   zoning change, most preferred RS-5S zoning. Staff, therefore, recommend
   referral to Public Hearing of RS-5S zoning for the Kitsilano RS-1S area.

   3.   Impact on Property Values

   The Manager of Real Estate Services advises that under current market
   conditions, there should be no significant impact on property values in
   the short term if RS-5S zoning is adopted.

   ENVIRONMENTAL IMPLICATIONS

   The RS-5S zoning encourages site landscape planting which will
   positively affect the city's micro-climate and air quality. This zoning
   also regulates the maximum site coverage by impermeable materials which
   would also have positive effects on micro-climate, and reduce runoff
   thereby decreasing flooding potential and reducing combined sewer
   overflows. Each of the zones provide some moderate incentive for
   renovating existing houses which could result in lessening the burden on
   landfill sites from the demolition of existing houses on sites where new
   houses are proposed.

   SOCIAL IMPLICATIONS

   The Children's Policy and the Statement of Children's Entitlements are
   not applicable to this amendment.

   PERSONNEL IMPLICATIONS

   RS-5S zoning is more complex than RS-1S zoning. Processing of
   applications will generally involve extra staff time for checking
   applications, meetings with applicants, meetings with staff (e.g.,
   landscaping and engineering), telephone enquiries, file searches,
   correspondence, site visits, and providing information to residents and
   prospective applicants. Compared to RS-1S applications, RS-5S
   applications will affect staff in the following areas:

    Development Planners or Planning Facilitators (12 to 16 hours per
     application);
    Plan Checking Technicians (20 to 25 hours per application--bulk of
     research, correspondence, and neighbourhood applicant and staff
     liaison duties are handled by this position);
    Development Information Officers (additional 2 to 3 hours per
     application);
    Landscaping Technicians (additional 0.5 hour per application);
    Building Inspectors (additional 2 hours per application); and
    Property Use Inspectors (additional 0.5 to 1.0 hours per application).

   Since October of 1996, Council has rezoned West Kerrisdale and MacKenzie
   Heights to RS-5 and made one- and two-family dwellings conditional in
   some RT-4 and RT-5 areas. RS-5, RS-5S or RS-6 zoning has been adopted by
   Council in parts of Dunbar, Douglas Park, and West Southlands, along
   with North and South Kerrisdale. RS-5 zoning has been referred to Public
   Hearing for West Pt. Grey (scheduled to reconvene on July 28, 1997).
   Taking into account the changes made or proposed above, with referral to
   Public Hearing of RS-5S zoning for Kitsilano, a potential of roughly 198
   person-weeks (note: 13 additional person-weeks for Kitsilano) could be
   added to staff's workload.

   The implications of the increase in staff workload for Planning has been
   discussed in a memorandum dated March 25, 1997, which has come before
   Council from the Director of Land Use and Development. The memorandum
   concludes that given space constraints in accommodating additional staff
   and a declining number of development applications, staff will monitor
   development activity in the forthcoming months and review staffing
   levels when additional neighbourhoods are brought forward for possible
   rezoning.

   The City Building Inspector and the Manager of Property Use Inspection
   Branch note that the additional workload for building inspectors and
   property use inspectors will be accommodated with existing staff,
   although future area rezonings will likely bring about a request for
   additional staff in order to maintain current levels of service. There
   may also be some additional workload placed on property use inspectors
   because of post-occupancy complaints, particularly with respect to the
   impermeability regulations and site landscaping guidelines associated
   with the RS-5/RS-5S and RS-6 zoning. Staff will be monitoring the
   situation through the course of this year and will report back to
   Council should additional staff be required.

   CONCLUSION

   This report recommends referral to Public Hearing of RS-5S zoning for
   the Kitsilano RS-1S area.

                                   * * * * *