ADMINISTRATIVE REPORT

                                           Date:  July 14, 1997 
                                           Dept. File No. 1.40.97.08
                                           CC File No.: 1805

   TO:       Vancouver City Council

   FROM:     General Manager of Engineering Services

   SUBJECT:  Award of Consulting Contract:  Value Engineering Services
             for Dedicated Fire Protection System


   RECOMMENDATION

        A.   THAT the contract for Value Engineering Services to review the
             DFPS pipeline conceptual and detail design be awarded to Value
             Management Strategies Inc., at an estimated fee of $75,000
             including GST.  Funds are available from the project budget 
             Account Code 18/37/2300/999.

        B.   THAT the General Manager of Engineering Services be authorized
             to enter into a Professional Services Agreement contract with
             Value Management Strategies Inc. in consultation with the
             Director of Legal Services.

   COUNCIL POLICY

   Consultant contracts over $30,000 are to be awarded by Council.

   Contracts are to be awarded on the basis of best value for fee.

   Council approved the Dedicated Fire Protection System for implementation
   on April 16, 1992.


   PURPOSE

   This report recommends that the contract for Value Engineering Services
   for the Dedicated Fire Protection System be awarded to Value Management
   Strategies Inc.


   BACKGROUND

   The preliminary design for the DFPS was approved for implementation in
   1992 at an estimated cost of $40 million.  This design included the
   construction of two pump stations downtown (False Creek and Coal
   Harbour) and one in the Kitsilano area.  The preliminary design also
   called for approximately 7.5 kilometres of pipeline downtown, five
   kilometres of pipeline to service the Kitsilano area, valve stations,
   and hose tender trucks.

   To date, pump stations are complete at False Creek (also the control
   centre) and Coal Harbour.  City crews are currently completing the 3
   kilometre-long pipeline to link these two stations, providing a
   "backbone" for the system downtown (see Appendix A).  This pipeline will
   be complete by the end of 1997.

   As reported in the specific contract award reports, design and
   construction costs for both pump stations and for the pipeline downtown
   are above the initial estimated costs outlined in the 1991 conceptual
   design report.  In addition, an increase in scope of work was approved
   to re-construct the repeater station at Grouse Mountain in 1994.

   The project team believe that the design standard chosen for the system
   is appropriate to meet the project goals.  The pipeline connecting False
   Creek and Coal Harbour is critical to the viability of the overall
   system, thus it was recommended that the existing design standard be
   maintained for that section of pipeline.

   With both downtown pump stations now complete, and the critical
   connecting pipeline between them nearing completion, we are at an
   appropriate stage to reassess the design concept and solutions to
   determine the best way to meet the basic functional requirements for the
   remainder of the system.

   DISCUSSION

   Value Engineering is a proven management technique using an intensive,
   systematic, and creative study to seek the best functional balance
   between cost, reliability, and performance.  The process delivers
   improved value to project owners.

   Value Engineering is now being used more often in Canada.  The GVRD has
   conducted a number of studies for water and sewerage projects.  The GVWD
   recently completed a Value Engineering study on the design of the water
   filtration plant at Seymour Dam.  District staff were very pleased with
   the results.  Numerous proposed alterations were accepted by the design
   team, resulting in approximately $20 million in project savings.

   A Value Engineering (VE) study uses a team of professionals from various
   design disciplines that meet, under the guide of a Team Leader
   (Certified Value Specialist), with the original design team to review
   the project design.  The team then works on its own to further review
   the design and propose alternative methods (along with approximate cost
   impacts) for the design teams consideration.  At the end of the study
   both groups get together to review the proposals and decide which ones
   will be implemented in the design.

   The goal of this VE study is to review and suggest improvements or cost
   savings in the DFPS water distribution system design.  The study topics
   will range from the conceptual level to detailed pipeline design, to
   ensure that the design will continue to meet our needs in the most cost
   effective manner.  

   Five Value Engineering consultants were invited to submit proposals for
   this work.  These proposals were evaluated by four reviewers, that
   followed an objective list of evaluation criteria which fall into the
   major categories of: capability to carry out work (experience of
   Certified Value Specialist), management of work (scheduling, cost
   control, quality control, comprehension of objectives), methodology
   proposed, and quality of proposal (clarity and logic).  Within each of
   the major categories there are specific questions.  The evaluation was
   based on Engineering Services policy that indicates consultants should
   be selected on a best value basis.

   All proposals were well prepared.  Two proposals (U.S. Cost & Value
   Management Strategies) were of similar quality and stood out for the
   selection team.  We have recently discovered that the proposed Team
   Leader (Certified Value Specialist) at U.S. Cost has left the firm,
   leaving the proposal from Value Management Strategies as the best
   available.

   The consultants estimated fee of $69,571 plus GST covers the cost of the
   team leader, six team members, and the final report through the VE
   study.  The actual cost will vary depending upon the specific make-up
   and final number of team members, which is subject to our review and
   final approval.  Alterations in proposed team composition will change
   the fee structure.  Changes to the exact duration of the study may also
   adjust the total cost.  To cover these uncertainties, we are
   recommending that $75,000 be approved for this award.

   In keeping with the City's best value policy, the review panel felt
   Value Management Strategies' proposal best represented the services
   required.  The General Manager of Engineering Services, therefore,
   recommends that Value Management Strategies be awarded this contract.

   The study is expected to be complete by the middle of October, 1997. 
   This will allow sufficient time to incorporate any recommendations for
   design changes into next year's work on the project.


   APPENDIX A (Map) on file in City Clerk's Office

                               *   *   *   *   *