ADMINISTRATIVE REPORT

                                           Date: June 26, 1997
                                           Dept. File No.
                                           CC File No. 4251

   TO:       Vancouver City Council

   FROM:     Director of Civic Theatres and Manager of Facilities
             Development, in consultation with the Director of Finance

   SUBJECT:  Civic Theatres Capital Plan - Phase II Design


   RECOMMENDATION

        THAT Council approve allocation of $600,000 for Schematic Design
        and Design Development of the next phase of major capital upgrades
        to the Queen Elizabeth Theatre, Vancouver Playhouse and Orpheum;
        source of funds to be a loan from the Property Endowment Fund (PEF)
        to be repaid from the income to the Civic Theatres Capital Reserve,
        terms to be acceptable to the Director of Finance and Director of
        Civic Theatres.  

   CITY MANAGER'S COMMENTS

        The City Manager RECOMMENDS approval of the foregoing.

   COUNCIL POLICY

   Civic Theatres capital reserve funds are to be used for capital upgrades
   of the Queen Elizabeth Theatre, Vancouver Playhouse and Orpheum.

   PURPOSE

   Civic Theatres Department requests approval of the allocation of
   $600,000 for Schematic Design and Design Development of a group of
   upgrade projects (Phase II) for the three theatres, including the
   funding formula proposed by the Director of Finance.

   BACKGROUND

   From 1992 to 1994, Civic Theatres conducted a scope analysis and a
   feasibility study of renovations and upgrades needed to preserve,
   repair, improve and revitalize the three civic theatres.  Many
   presenters, including all of the resident performing arts companies,
   were consulted extensively throughout the study.  The resulting long
   range capital plan was presented to Council in a workshop in September,
   1994.

   This capital plan is structured on a modular concept.  Depending on
   funding that becomes available from time to time, groups of projects can
   be assembled for implementation in a progressive, coordinated manner. 
   When each project or block of projects is completed, the theatres are in
   a fully operational state and ready for future work to be undertaken. 
   The need to close the theatres during reconstruction is minimized.

   The first phase of capital projects based on the plan was implemented
   from June 1995 to November 1996.  The approved budget was $2.6 million;
   on completion the final cost was just over $2 million.  The projects
   were funded from the civic theatres capital reserve which accumulates
   revenues from the QET Parkade and from a ticket surcharge on all tickets
   above $8.00 in value.  Financing was arranged, with the assistance of
   the Director of Finance, as a line of credit drawn on the PEF.  Because
   capital reserve income continued through the construction period, the
   amount actually borrowed to finance this Phase was considerably less
   than $2 million.  Final pay down is expected to be made late this fall,
   approximately 9 months earlier than originally estimated.  

   Projects completed were:

   1.   Orpheum; auditorium ceiling - acoustic upgrade.
   2.   Stage sound systems upgrade - Orpheum and QET.
   3.   QET; stage lighting system - code and capacity upgrade.
   4.   QET; Parkade and Lobby elevators.

   The only operating costs resulting from these projects are the annual
   license and maintenance costs for the new elevators at the QET.  

   DISCUSSION

   In preparing for a second phase of upgrades, Civic Theatres met with a
   group of users including resident performing arts companies and
   commercial presenters.  The group concurred that it was important to
   focus on projects that will "improve the experience of the audience",
   recognizing a new competitiveness in the environment.  

   On May 29, 1997, Council endorsed a number of City-initiated projects
   for submission to the Enhanced Canada/B.C. Infrastructure Works Program
   in the category of "soft" infrastructure.  Included were two blocks of
   projects at Civic Theatres, as follows;

   Option #1;          $5,125,000

        1.   QET auditorium reconfiguration - Phase 1.
        2.   Playhouse lobby expansion.
        3.   Salon/Meeting room addition.
        4.   Technical equipment replacements and upgrades.

   Should this Option be unacceptable for any reason, a second Option has
   been prepared.

   Option #2;          $3,500,000

        1.   Items #2, 3 & 4 from Option #1, plus
        2.   Orpheum and QET concessions stations code and equipment
             upgrades.
        3.   Orpheum Smithe Street entrance re-design for traffic flow,
             audience comfort, flexibility for loading in, improved
             lighting, signage and safety.
        4.   QET canopy extension, lighting and signage upgrades and lobby
             air conditioning.
        5.   Renovations to Parkade stairwells for patron security.
        6.   QET, Playhouse and Orpheum security systems.

   Given the time lines imposed by the Infrastructure Program and the
   delays that can be anticipated in awarding of grants, it is essential to
   start the final design process now.  Civic Theatres requests approval to
   allocate $600,000 to contract the design and consulting team to proceed
   with schematic design and design development for the projects listed. 
   These funds are part of the estimated total costs of the options as
   noted above; they are not additional to the project costs estimated.

   The design and consulting team for Civic Theatres capital upgrades
   includes:

   Architect                Proscenium Architecture and Interiors
   Theatre Design &
   Architectural Lighting   Doug Welch Design
   Acoustics                Aercoustics Engineering
   Heritage                 Commonwealth Historic Resource Mngmnt.
   Cost                     James Bush & Assoc.
   Structural               Read Jones Christoffersen
   Electrical               Schenke/Bawol Engineering
   Mechanical               Keen Engineering
   Sound Systems            Engineering Harmonics
   Signage                  Gallop/Varley

   Project Management is provided by Facilities Development.


   FINANCIAL IMPLICATIONS

   The cost of $600,000 can be funded from unexpended balances and
   contingencies in previously approved projects that have been completed,
   augmented by a line of credit from the PEF against continuing Civic
   Theatres capital reserve income.  The maximum loan would not exceed
   $480,000.  Based on past average revenues to the capital reserve, this
   loan would be paid down by approximately fall 1998.  In reality, because
   money is only drawn when payments are made, the pay down should be
   earlier.  The loan is subject to interest in accordance with normal City
   policy, based on the City s average rate of earnings for short-term
   investments.  

   There will be minor increases in energy costs from air conditioning the
   QET lobby and from some increases in exterior and public area lighting. 
   Concessions stations upgrades will result in some labour savings.

   SOCIAL IMPLICATIONS

   All of the projects in both options support the operations and health of
   all of Civic Theatres users by improving the level of service to their
   audiences - especially important in the more competitive environment now
   prevailing.  Some address code, security and safety issues.


                                   * * * * *