City of Vancouver




                                  Inter-Office Correspondence



   ENGINEERING SERVICES                                    File No. 120 630


   DATE:     June 11, 1997

   MEMO TO:  Standing Committee on Transportation and Traffic

   FROM:     Dave Rudberg, General Manager of Engineering Services

   COPY TO:  Ken Dobell, City Manager
             Ann McAfee, Director of City Plans
             Peter Judd, Transportation Plan

   SUBJECT:  Burrard/Cypress Traffic Plan - Further Information

   At the May 14, 1997 meeting of the Standing Committee on Transportation
   and Traffic, the Committee requested further information on some of the
   issues.  The following responds to questions asked at the meeting.

   I)  Left turns at 1st Avenue

       In the p.m. peak hours, the left turns from Burrard to 1st Avenue
       are approximately 120/hr northbound to westbound and 100/hr
       southbound to eastbound.  This number is lower than prior to the
       installation of the pedestrian signal at 1st and Burrard (Volumes
       had been 240/hr westbound and 130/hr eastbound).  Volumes have
       declined because it is more difficult to turn left at a signal,
       with no left-turn bays or left-turn arrow in place.  Many of the
       displaced turns have relocated to 2nd, 3rd, and Cypress Street. 
       However, although volumes have decreased, the accident rate has
       increased significantly at 1st and Burrard, which is now the worst
       pedestrian signal location in the City.  Left turns at both 2nd
       Avenue and 3rd Avenue in the p.m. peak are approximately 110/hr
       northbound to westbound and 50/hr southbound to eastbound). 
       Observations show that one third of the northbound left turns at
       1st Avenue are destined to Kits Point.  The remaining two thirds
       are destined to the immediate commercial area and the residential
       area south of Cornwall.

   ii) Truck Traffic on 1st Avenue

       Molson's, a major source of trucking in the area, reports that
       approximately 40 trucks per day serve its brewery.  These trucks
       presently use 1st Avenue and Fir Street to access 4th Avenue, which
       has created noise impacts for residents along 1st Avenue.  This
       routing is a problem because of the noise, and the City and
       residents have requested that the trucks use Burrard instead.  This
       would require the pedestrian signal at 1st and Burrard be upgraded
       to a full signal.  Molson's has indicated that if a signal is
       installed at Burrard and 1st, its trucks would not follow the
       1st/Fir route.  

   iii)                            Supplemental Report - Option K

       The supplemental report dated April 30, 1997, proposed a minimum
       3.7m curb lane on Burrard to reduce property costs and impacts. 
       The attached Figure 1 shows this option.  The following provides
       some background for this supplemental report:
           The Comprehensive Bicycle Plan of 1988 recommended 3.7 metre
            curb lanes,
           On July 21, 1994, the Bicycle Advisory Committee asked and
            Council approved 4.3 metre curb lanes where possible,
           the original report proposed 4.0 metre lanes as a compromise,
            to reduce property impacts, but some delegations indicated they
            found the extra width unhelpful.
           therefore a 3.7 m curb lane (option K) was presented as a
            cost-saving alternative for consideration

   iv) A T-intersection proposal for Burrard and Cornwall

       Background

       A T-intersection has been proposed by the Transportation Planning
       Team, Planning staff, and members of the public who attended the
       Committee meetings as a way to reduce pedestrian crossing
       distances, slow traffic entering Cornwall, and increase green
       space.  This concept is still in a preliminary stage and a thorough
       analysis can not be done without a detailed design.  However, some
       general comments and a preliminary assessment has been conducted
       and is shown below.  It is also worthwhile to highlight some of the
       history of the public process related to Burrard/Cornwall:

           Spring of 1994    -    Initial meetings and studies to consider
                                   traffic calming on Cypress.
           Fall of 1994  -   Cypress residents propose an arterial
                              connection (left-turn bay) from Burrard to
                              Cornwall.
           June 1995     -   Open House to evaluate traffic calming on
                              Cypress and left-turn bays on Burrard
                              (including a bay at Cornwall).
           November 1995     -    An Engineering report on traffic calming
                                   (Cypress) and arterial changes (Burrard)
                                   is presented to the Traffic Commission. 
                                   Based in part on input from the Cypress
                                   Residents' Group, the Commission
                                   deferred a decision on left-turn bays
                                   until the future of the Burrard Bridge
                                   upgrade is known.
           Spring 1996   -   The Burrard Bridge upgrade is deferred
                              pending further study.  Residents of Cypress
                              request that left-turn bays on Burrard be
                              considered separately from the Bridge
                              proposals.  The Traffic Commission agreed.
           Fall 1996     -   Project notification signs were installed and
                              a survey was delivered to a broad area
                              proposing left-turn bays on Burrard,
                              including a bay at Cornwall (which received
                              75% support).

   As indicated, the development of a T-intersection (including design
   options, analysis and public input) has not been possible in the time
   available.  However, the following overview is intended to assist in
   determining the appropriate option. (Figure 2 shows a sketch of the
   left-turn bay design and Figure 3 shows a sketch of a T-intersection
   design.  Figure 4 shows an aerial photo of the existing intersection and
   Figures 5 and 6 show an overlay of the left-turn bay design and the
   T-intersection design.):

   Pedestrian and Bicycle Issues.

   A T-intersection would reduce the pedestrian crossing distance and
   provide a more direct path across Cornwall and Burrard.  Pedestrian wait
   times and crossing times within the intersection would be reduced. 
   However, a T-intersection would result in a high volume of right-turners
   (presently 1300 per hour in the pm peak) from southbound Burrard to
   westbound Cornwall turning through the pedestrian crosswalk. (At
   present, pedestrians cross this traffic at a controlled pedestrian cross
   walk.)  This right-turn traffic (likely in a dual right-turn lane) would
   be a safety concern for pedestrians (similar to the situation at the
   north end of the bridge).  This could be addressed with a separate
   right-turn signal phase.  However, this could significantly reduce
   capacity of this manoeuvre and needs to be looked at in more detail.

   The existing situation can present difficulties for cyclists on the west
   sidewalk of the bridge proceeding southbound to Burrard Street since
   they must cross vehicle traffic destined for Cornwall.  A T-intersection
   will not necessarily improve this situation since high right-turn
   traffic can be difficult to cross (particularly a dual right-turn). 
   More work is needed to improve cyclist connections.  One proposal with
   the existing geometry is to provide a push-button and a special crossing
   for cyclists, next to the existing controlled pedestrian crossing.  This
   would provide a fully protected route to the proposed bicycle lanes on
   Burrard.

   Costs

   The cost of providing a T-intersection would vary depending on the final
   T-intersection design.  This cost cannot be estimated in detail but is
   expected to be in the range of $600,000 to $750,000.  If the left-turn
   bay (estimated to be $375,000) is installed beforehand and the
   T-intersection is phased in, the total project costs are estimated to
   range from $700,000 to $1,000,000.  It is emphasized that these costs
   are only a rough guide.

   Capacity and Queuing

   A detailed analysis of capacity changes and trip diversion can not be
   done at this point.  However, some general comments can be made about
   the effect a T-intersection proposal would have on capacity.  

   There is about 15% excess capacity in the intersection today.  The bay
   will use up this spare capacity.  The greatest impacts on capacity will
   be to southbound and eastbound vehicles because they will be stopped
   during the new left-turn phase.  As a result, queues for both southbound
   (Burrard Bridge) and eastbound (Cornwall Avenue) traffic would increase.

   Overall, the T-intersection would be expected to further reduce
   capacity.  However, the reduction will depend on the chosen design.  It
   is possible, with a T-design, to maintain the same number of lanes as
   exist today, but the sharp right-turn would lead to reduced capacity. 
   Furthermore, as discussed previously, a separate right-turn phase to
   Cornwall to address pedestrian concerns has been suggested, and would
   cause a significant, additional reduction in capacity.

   The vehicle storage of the left-turn bay design in the report before
   Council is 14 vehicles.  The T-intersection design would reduce storage
   to approximately 9 vehicles, which could mean that the signal phase for
   this turn would need to be increased.  Storage for the southbound
   right-turns destined to westbound Cornwall would also need to be
   considered.

   Traffic Calming on Cornwall.

   Due to the slower-speed sharp right turn, traffic speeds on Cornwall
   between the Bridge and Cypress Street would be reduced. This could also
   lead to a traffic reduction on Cornwall and reallocation of trips to
   arterial streets such as Burrard Street and 4th Avenue, and local
   streets such as 1st and 2nd Avenues.

   Green space

   Approximately 0.30 hectares of landscaped island and roadway could be
   consolidated  to the north side of Cornwall.  The planned "Welcome to
   Kitsilano" sign could be relocated to this area.

   Options

   Staff believe there are three potential courses of action and Council
   may wish to consider these:

   .   Approve and construct the left-turn bay design now, as recommended
       in the March 17, 1997 report.  Then, as part of the Burrard Bridge
       review, consider changes to the south end of the Bridge.  If a
       T-intersection is favourable, it could be phased in when the Bridge
       changes are made.

   .   Do not approve the left turn bay now, and instead, conduct further
       studies, possibly involving public input, to develop a
       T-intersection design for report back to Council later this year.

   .   Do not approve the left-turn bay now, and include study of a
       T-intersection as part of the changes to the Burrard Bridge.

   Staff View Points.

   Both Planning and Engineering staff agree that further study would be
   needed before a T-intersection could be recommended.

   Engineering staff believe that based on the long public process that has
   occurred and the strong support from the overall community, the
   left-turn bay should go ahead (as described in option a. above).  The
   T-intersection will impact the operation of the Bridge and it should be
   considered when the changes to the Bridge are made.  The left-turn bay
   could be constructed now and, if approved, the T-design can be phased-in
   later.  This would also provide the opportunity to evaluate the impacts
   of the left-turn connection before making more significant changes.

   Planning staff would prefer that the further study proceed now, before
   money is spent on the left-turn bay (as described in option b.).  This
   would potentially save costs and allow the final intersection design to
   be built in the near future.  Planning staff believe that the
   T-intersection would be compatible with any new bridge configuration.

   I hope that this memo will help Council.  If there are any questions,
   please contact me.





                          D. H. Rudberg, P. Eng.
                          General Manager of Engineering Services

   MRZ/jb
   st\06i01mz