ADMINISTRATIVE REPORT
Date: June 10, 1997
Dept.File No.1.40.97.07
CC File: 1801-1
TO: Vancouver City Council
FROM: General Manager of Engineering Services
SUBJECT: Award of Contract No. 9708, for the Supply and Installation of
Distribution Watermain
RECOMMENDATION
A. THAT Contract No. 9708 for the supply and installation
ofdistribution watermain be awarded to the low bidder meeting
the contract requirements, Pedre Contractors Ltd., for a total
tender price of $757,642.13; with the source of funds to be
account code 17/36/1004/999.
B. THAT the bid bonds of the unsuccessful tenderers be returned.
C. THAT the General Manager of Engineering Services, in
consultation with the Director of Legal Services, be
authorized to enter into a construction services contract with
Pedre Contractors Ltd., for Contract No. 9708, for the Supply
and Installation of Distribution Watermain.
GENERAL MANAGER'S COMMENTS
The City Manager RECOMMENDS approval of A, B and C.
COUNCIL POLICY
Construction contracts over $200,000 are to be awarded by Council.
Contracts are to be awarded on the basis of best value for fee.
PURPOSE
This report recommends that the contract for the construction and
related work of the distribution watermain at 48th Ave. from Main to
Fraser, 50th Ave. from Ontario to Main, 18th Ave. from Oak to Laurel,
18th from Windsor to Glen and 17th Ave. from Glen to Inverness be
awarded to the low bidder, Pedre Contracting Ltd.
BACKGROUND
The 1997 Waterworks Capital Budget provides $8.3 Million funding for
distribution watermain replacement. This work was chosen to be
contracted due to additional commitments by City forces to construct the
Dedicated Fire Protection System, approximately 25% more work than
usual. The watermains have reached the end of their service lives, and
their proper operation is essential to provide a continuous supply of
water for both domestic consumption and fire protection.
DISCUSSION
In anticipation of the above award, advanced designs and contract
documents were prepared by Engineering Services staff. Bids have now
been received for a construction contract that will see the replacement
of 9 City blocks of watermain. The work will be administered under a
lump sum/unit price type, construction services contract. As requested,
the contractors have submitted unit prices and lump sums, which will be
used to calculate interim progress payments. The final cost of the
contract will vary slightly as a result of variances from the estimated
quantities of work, or from extra work, but it is anticipated this
variation will be small.
Three contract bidders submitted tender packages, including bonding
requirements. A summary of the bids received is as follows:
Contractor Bid Price
Pedre Contractors Ltd. $757,642.13
Ponte Bros Contracting Ltd. $763,601.00
B. Cusano Contracting Inc. $959,300.00
Therefore, the tender submitted by Pedre Contractors Ltd. is the low
bidder and meets all the contract requirements, including bonding and
completion date. Pedre Contractors is well qualified to complete this
work, having demonstrated experience with watermain installation on a
number of similar projects in a satisfactory and timely manner.
FUNDING AND COST
The low bid for Contract No. 9708 is within the preliminary engineer's
estimate of $903,000. Funding for this contract is available in account
No. 17/36/1004/999, "Distribution Watermain Replacement"
* * * * *