ADMINISTRATIVE REPORT

                                           Date:  April 8, 1997
                                           File No.  2122-5  
                                           C.C. File No.: 5553-1



   TO:       Standing Committee of Council on Planning and Environment

   FROM:     Manager of Engineering Services, in consultation with the
             Director of Central Area Planning and the Manager of Parks and
             Recreation

   SUBJECT:  Waterfront Pedestrian/Bicycle Route Design - Bayshore
             Development


   RECOMMENDATION

        A.   THAT  Council  approve  the revised  design  of  the shoreline

             protection  works  for the  Bayshore  development as  shown in
             Appendix A.

        B.   THAT   Council   approve   the   design   of   the  waterfront
             pedestrian/bicycle route for the Bayshore development as shown
             in Appendix A.

        C.   THAT  Council approve  the  design of  handrails  as shown  in
             Appendix B,  along the  entire length  of the  walkway/bicycle
             path.

        D.   THAT Council authorize  staff to obtain a  right-of-way to the

             satisfaction of  the City  Engineer, on the  west side  of the
             Bayshore   Gardens   project   in   order   to   connect   the
             walkway/bicycle path with Stanley Park.

        E.   THAT Council authorize staff to  obtain a 1.5m right-of-way on
             the  east  side   of  the  Bayshore  Hotel   for  the  bicycle
             path/walkway when a development permit application is made for
             the hotel.


   GENERAL MANAGER S COMMENTS

        The General Manager of Engineering  Services recommends approval of

        A through E.


   COUNCIL POLICY

   -    On  March  25,  1997,  Council   approved  the  report,  Waterfront
        Pedestrian/Bicycle Widths - Coal Harbour,  Bayshore and False Creek
        North,  which revised  the widths  of the  Bayshore pedestrian  and
        bicycle pathways.

   -    On  October  24,  1991,  Council  approved the  report,  Conceptual
        Shoreline  Designs  -  Coal  Harbour and  False  Creek  North,  and

        requested that, with  respect to the detailed  design, Council only
        review issues which represent changes to the approved proposals and
        principles.  

   -    On  October  24,  1991,  Council  approved the  report,  Waterfront
        Pedestrian/Bicycle  Route Concept  Plan  -  Bayshore, Marathon  and
        False Creek  North Developments,  and requested  that staff  report
        back on the  detailed design  of the waterfront  pedestrian/bicycle
        system through  False Creek North  prior to any  development permit
        approval in a waterfront sub-area.

   -    On August 13, 1991,  Council approved the rezoning of  the Bayshore
        Site.  As  a condition  of rezoning, the  developer is required  to

        design and construct  shoreline protection  works and a  waterfront
        pedestrian/bicycle pathway.


   PURPOSE

   This  report seeks  Council  approval  of the  design  of the  shoreline
   protection works and the pedestrian/bicycle system for the Bayshore Site
   and approval  of the  location and  design  of the  handrails.   Council
   approval is  required  as a  condition of  the  issuance of  development
   permits for the waterfront sub-areas in the Bayshore development.



   DISCUSSION

   Shoreline Protection Works

   Council requested  a report  back on detailed  design for  the shoreline
   protection  works only  if  the design  differs  significantly from  the
   approved  proposals  and  principles.    The  design  of  the  shoreline
   protection works along Cardero Park are generally in accordance with the
   design  concept approved by Council.  However,  the design in the Marina
   and  Charter  Boat  sections  has   changed  to  accommodate  staff  and
   Fisheries' concerns.  


   The  approved design concept includes precast  panels hung from the deck
   to low water level  in the Marina section and to mean  tide level in the
   Charter Boat section.   The precast concrete  panels have been  replaced
   with a simpler, more elegant fascia panel and the slopes above low water
   level have been  treated with a specially  placed rock finish.   To meet
   Fisheries' requirements, the slope in the Charter Boat  section has been
   revised.  As a result, the vertical distance between the deck  level and
   the rock slope increased from 3m to 4m.  

   Staff  recommend  approval  of the  revised  shoreline  protection works
   design,  as shown  in Appendix  A  as the  design  meets the  principles
   approved  by Council,  the  design objectives  of  staff and  Fisheries'

   requirements. 

   Handrails

   The design of  the handrail along the  walkway, shown in Drawing  L13 of
   Appendix A, is similar to the approved Marathon  handrail.  The handrail
   is high quality, difficult to climb and minimizes view blockage.  
   Staff are seeking  Council's direction on the extent  of handrails to be
   used  along  the walkway.    This  issue involves  the  need  to balance
   aesthetic objectives against safety concerns and potential liability for
   the City.  Council approved, in the conceptual Shoreline Designs  report
   in October,  1991, "THAT shoreline handrails  be kept to a  minimum", so
   views  are not obstructed.   However,  the Building By-law  requires all

   drops over 600mm (2 feet) to have guards.

   Council dealt with this issue  previously when considering the shoreline
   design  for the False  Creek North Area 2  (Roundhouse) development.  In
   that case,  after considering a number of criteria, Council approved the
   design without handrails in locations where the vertical  drop was 2.35m
   (almost 8 feet).  On the  Bayshore site the minimum drop from  any point
   along  the proposed walkway  to the rock  slope is 4.0m  (over 13 feet),
   therefore,,  the  developer  and  Engineering  staff  are   recommending
   handrails along the entire shoreline.

   Planning and  Park Board staff  are concerned that a  handrail along the

   Charter Boat section  of the walkway, north of the  Bayshore Hotel, will
   have a significant impact  on enjoyment of the northward  views and will
   not meet  Council s intent of minimizing  handrails.  Planning  and Park
   staff would prefer  the use of a  planter barrier along the edge  of the
   deck, shown  on Drawing L6 of Appendix A, to define the edge of the deck
   without impacting views.  

   Engineering staff are concerned that  the planter edge will not  provide
   an adequate  barrier for  preventing people,  especially children,  from
   potentially falling  over the  edge.  Therefore,  this design  cannot be
   recommended.

   Pedestrian/Bicycle Pathway


   The detailed design  for the  Bayshore Site pedestrian/bicycle  pathway,
   shown in  Appendix  A follows  the  concept and  standards  in the  1991
   Concept Plan report approved  by Council and the revised  pedestrian and
   bicycle pathway  widths approved  by Council  on March  25,  1997.   The
   surface  treatment,  lighting,  furniture  and  landscaping   have  been
   developed through  a process  involving input  from Parks,  Planning and
   Engineering staff, and the developer s design team.  The proposed design
   balances urban  design objectives and  maintenance costs and  provides a
   safe and enjoyable experience for pedestrians and cyclists.

   Marina and Charter Boat Section


   The pedestrian and bicycle pathways are separated by a landscaped buffer
   in  the Marina  section (north  of Towers E  & F)  and the  Charter Boat
   section (north of the hotel).  The pedestrian pathway is 5.2m  wide with
   a concrete paver  surface.  The bicycle  pathway is a 4.0m  wide asphalt
   surface with narrow paver bands defining the edges.

   In  order  to connect  this  end  of  the  walkway to  Stanley  Park,  a
   right-of-way on the  west side of the development will  be required from
   the  developer.  The size  of this right-of-way  will be negotiated with
   the developer to the satisfaction of the City Engineer.

   Marina Section West of the Hotel


   The pedestrian and bicycle pathways  are separated by a landscape buffer
   in the Marina section west of the hotel.  The pedestrian pathway is 5.2m
   wide with a concrete paver surface.  Bicycles share a 6.0m  wide pathway
   with service  vehicles for  the charter  boats and  proposed restaurant.
   The  pathway also  provides  fire fighting  access for  the hotel.   The
   bicycle/service road  is a 4.0m  wide asphalt  surface banded by  a 1.0m
   wide strip  of concrete pavers.   The bicycle  path follows the  eastern
   edge of the loading area at  the northwest corner of the hotel  in order
   to minimize conflicts between bicyclists and service vehicles.

   Cardero Park


   The pedestrian/bicycle  route is  a shared  pathway located  between the
   hotel and Cardero Park.  The shared pathway design is  made up of a 4.6m
   wide pedestrian  pathway beside the retail frontage (1.5m of which is on
   the hotel site), a 0.6m separating strip and a 4.6m wide bicycle pathway
   adjacent to the park.  In addition, the hotel will be set back 3.0m from
   the property line, providing  an additional 1.5m of pedestrian  area.  A
   3.0m wide secondary pedestrian pathway  runs along the west edge of  the
   park beside  the water.   The  surface treatment  of the pedestrian  and
   bicycle pathways through  Cardero Park will be concrete  pavers.  A 1.5m
   wide right-of-way for maintenance of the walkway and public access  will
   be required from the property owner prior to issuance of any development
   permit for the hotel site.


   This design  assumes that there will  be retail frontage  along the east
   side of  the hotel  development.   However, the  developer is  currently
   considering development on the  hotel site that does not  include active
   uses at grade along the eastern edge of the hotel.  This is not included
   in the zoning  for the site and,  therefore, is not being  considered at
   this time.  Any changes to the design will be considered  along with the
   development permit application for the hotel.  At that time, staff  will
   also obtain the 1.5m  right-of-way from the developer.

   Appendix B (drawings L1, sheets 9 and 10, and drawing L9B) shows how the
   walkway  would be  designed if  the hotel  development proceeds  without

   retail.

   Stone Caps

   Stone  caps  will  be  provided  along the  entire  walkway  to  provide
   continuity to the entire shoreline system and to reinforce the character
   of the original Stanley Park seawall.

   CONCLUSION

   The pedestrian/bicycle route design proposed  is generally in accordance
   with the  concept approved by Council in 1991 and the revised pedestrian
   and bicycle pathway widths approved by Council on March 11, 1997.  Staff

   support this proposal and request Council s approval. 



                   *   *   *   *   *