ADMINISTRATIVE REPORT

                                                   Date: September 16, 1996
                                                          File:  1.40.96.06

   TO:       Vancouver City Council

   FROM:     Capital Plan Staff Review Group

   SUBJECT:  1997-1999 Waterworks Capital Plan


   RECOMMENDATION

        A.   THAT Council approve the 1997-1999 Waterworks Capital Plan at
             a total cost of $74.1 million, including elimination of the
             50% City funded subsidy for new water services for
             single-family homes and duplexes, effective January 1, 1997.

   CONSIDERATION

        As an alternative to A, the following options are submitted:

        B.   THAT Council not approve elimination of the 50% City share of
             new water services for single family homes and duplexes and
             approve an additional $4.2 million in the 1997-1999 Waterworks
             Capital Plan for a total cost of $78.3 million.

             OR

        C.   THAT Council make further reductions to the recommended plan,
             as outlined in Appendix B to this report,  and approve the
             1997-1999 Waterworks Capital Plan with funding totalling
             $63.85 million.

   CITY MANAGER'S COMMENTS

        The City Manager RECOMMENDS approval of A.

   COUNCIL POLICY

   Vancouver's water system operates as a utility, with all funding
   recovered through its rates and fees.  City Council, under Charter
   authority, approves borrowing for Waterworks without submitting the
   borrowing to a plebiscite.

   In May, 1995, Council approved property owners funding 50% of the cost
   of residential connections for new single-family and duplex homes. 
   Since the 1990 inception of mandatory residential fire sprinklers, these
   services were funded 100% by the City.  Prior to that time, new services
   were funded 100% by the property owner.

   CityPlan, adopted by Council on June 6, 1995, proposed developing
   user-pay programs to reduce environmentally harmful actions.

   PURPOSE

   This report presents the Capital Plan Review Group s recommended funding
   level for the 1997-1999 Waterworks Capital Plan, along with alternatives
   for Council consideration.  Two alternative funding options are provided
   in Consideration items B and C, although Council also has the option of
   setting the Capital Plan funding at any other level that it feels is
   appropriate.

   BACKGROUND

   Although Council approves the Waterworks Capital Plan separate from the
   overall Capital Plan, and without going to plebiscite, it is submitted
   along with the rest of the Capital Plans for convenience and context.

   Engineering Services presented a general review of the Waterworks
   Capital Program to Council on June 11, 1996.  This review outlined the
   Department s submissions to the 1997-99 Capital Plan in the context of
   the Waterworks long range plan, and identified funding needs totalling
   $83.85 million in order to meet the long range plan objectives over the
   next three year period.  This presentation was  for information purposes
   only and no funding decisions were made.  Comments from members of
   Council at that time were generally supportive of the Department s
   approach to planned infrastructure replacement, dealing with growth in
   demand through a combination of system expansion and demand management,
   and emergency preparedness.  To deal with demand management, Council
   approved a recommendation to pursue permanent, region wide, sprinkling
   regulations with the GVRD.

   The detailed explanations of the needs, making up this $83.85 million
   submission, were then submitted to the Capital Plan Staff Review Group
   on July 26, 1996.  The review group recognized that the Waterworks
   submissions were needs based, and that they represent important
   programs; however they also recognized that it is important to address
   the issue of affordability.

   DISCUSSION

   ENGINEERING SUBMISSION                                    $83.85 million

   The plan submitted to the Staff Review Group by Engineering Services
   includes the following four categories:

   Ageing Infrastructure Replacement                          $43.5 million

      The water system has a replacement value of approximately $1.2
      billion and an average life expectancy of 70 years.  A replacement
      rate of 1.5% per year is necessary to maintain a steady replacement
      program and to limit the costs due to breaks, leaks and resulting
      damage.

   Addressing Growth                                          $11.0 million

      A number of projects are planned which are intended to address
      existing pressure and fire flow problem areas in the City.  These
      problems are due to historic and continuing City and Regional growth.


   Emergency Planning                                         $20.3 million

      This category focuses on a continuation of the development of the
      Dedicated Fire Protection System (DFPS).  It includes funding for
      construction of the third pump station at Kitsilano Point, as well as
      continuation of the construction of the DFPS pipeline system.  It is
      anticipated that the system  will be completed over the next two
      capital plans.  The DFPS provides benefits on a day to day basis, as
      well as in the event of a major disaster,  by upgrading the water
      supply available for fighting major fires in areas where building
      densities have increased the design fire demand beyond the capacity
      of the existing water system.  The system allows the deferral of
      costly upgrading of the regular water distribution network, which
      would otherwise be needed to address this increased demand. This is a
      particular issue in Kitsilano.  Engineering is assessing whether
      construction of the pipeline system in Kitsilano is a higher priority
      than completion of the downtown network, as described in the Capital
      Plan submission, and will report back prior to submission of the 1997
      Capital Budget.

      This funding category also includes exploration of alternative
      emergency water supply sources, such as the Fraser River for fire
      suppression and groundwater aquifers for potable water.

   Customer Connections and Other Works                       $9.05 million

      The cost of new water services for single-family homes and duplexes
      are currently subsidized 50% by the City.  Other works include
      short-notice watermain replacements prior to street repaving
      projects, Waterworks Operations building modifications, telemetry
      system improvements, engineering and site investigations, and
      miscellaneous and minor works.

   A summary of the submitted plan, along with three reduced funding
   options, is attached as Appendix A.  At the Review Group s request,
   Engineering has prepared the attached list (Appendix B) of potential
   reductions and their impacts.  The Review Group supports the order of
   priority presented in this list, although Council may approve any option
   in whole or in part.

   CAPITAL PLAN STAFF REVIEW GROUP RECOMMENDATION  $74.1 million total

   Having reviewed the needs identified in the submissions, and also having
   given consideration to the issue of affordability, the Review Group has
   arrived at a recommended plan in the amount of $74.1 million, which is a
   reduction of $9.75 million below the submission level.

   The Review Group recommends that $4.2 million of this reduction be
   achieved by elimination of the current 50% City subsidy on the cost of
   installing new water services to new single family homes and duplexes. 
   The Review Group s rationale for proposing elimination of this subsidy
   is based on the results of the CityPlan public process whereby  concerns
   were raised about the changing character of neighbourhoods, loss of
   affordable housing, and the environmental impacts of new development.
   Construction of new single-family houses results in  costs  to
   neighbourhoods, the City, and region.  Impacts can include the loss of
   more affordable character housing, increased waste resulting from
   demolition materials and broader regional consequences of  locating low
   density housing close to City jobs.  Given these impacts, there is some
   cause to question why it is appropriate to continue to subsidize the
   construction of new single-family houses.  Consequently, the Review
   Group is recommending elimination of the 50 percent subsidy for new
   services for single-family houses and duplexes.  This would achieve a
   $4.2 million reduction with no functional impact on the water system. 
   It would place the cost of servicing new development on the builder.  It
   would also result in all new water services being funded through
   connection fees, with the exception of new services required for the
   construction of secondary suites.  These would continue to be funded
   100% by the City because the construction of secondary suites is
   consistent with the goals of CityPlan, and the rationale provided above
   does not apply in these cases.

   A further $5.55 million reduction would be from the Addressing Growth
   section by deferring two transmission main upgrading projects.  During
   the June 11, 1996 Waterworks Capital Plan presentation to Council,
   Council approved that the City pursue with the Greater Vancouver Water
   District (GVWD) the adoption of permanent lawn sprinkling regulations. 
   If permanent watering restrictions are adopted regionally, along with
   other aggressive demand management measures, staff believe that these
   two transmission main projects can be deferred until the next Capital
   Plan without significant further service deterioration.

   This recommended plan represents an increase of $20.4 million (Appendix
   C) over the funding level for the 1994-96 Plan, with the major areas of
   increase being in Infrastructure Replacement and the Dedicated Fire
   Protection System (DFPS).

   The Review Group, in supporting the increase in the DFPS, were guided by
   two major factors.  First, if the additional fire protection system was
   not provided in the Kitsilano area, alternative work would be required
   to maintain adequate fire flows for the existing distribution system, at
   a higher cost.  Further, as the Citizen's Survey indicated, there is
   support among the public for expenditures to improve the City's ability
   to respond to disaster scenarios such as earthquakes.

   The increase in infrastructure replacement for the distribution and
   transmission systems, amounting to $17.75 million, reflects a
   significant increase in this work and gives recognition to the targeted
   replacement program of 1.5% per year.  Arguably, the increase in this
   program might be deferred until later Capital Plans, with maintenance
   funds utilized to address leaks and emergency repairs.  However, the
   Review Group notes that future Capital Plans beyond 1999 will address
   major initiatives for water transmission and storage facilities and the
   1997-99 Plan may be the appropriate "window" for implementing this
   increase.

   FURTHER REDUCTIONS UP TO $10 MILLION

   If Council feels that the Waterworks Plan should be reduced further than
   the $10 million dollars recommended by the Review Group, a list of
   potential cuts is included in Appendix B.  The impacts of these
   reductions are more severe, affecting levels of service, the long term
   stability of the infrastructure replacement programs, and associated
   costs due to breaks, leaks, and resulting damage.  These reductions are
   listed in order of priority.  If the full $10 million is removed, the
   resulting Plan would be $63.85 million.

   FINANCIAL IMPACT

   Waterworks capital expenditures do not effect general taxes, but do
   impact the water rates charged to customers.  Figure 1 projects
   single-family water rates from 1996 to 2000 for the total $74.1 million
   plan recommended by the Staff Review Group.  Metered water rates would
   increase by the same proportion.

   The top portion of the rate (in black) is due to the increase in this
   Capital Plan over the previous Capital Plan (increase of $20.4 million). 
   The light grey area in the bottom of each bar represents the City
   portion of the single-family rate assuming continued capital spending at
   1994 -1996 levels.  This portion of the rate rises due to financing
   costs for past capital budget increases.  The dark grey areas of these
   graphs show the increases due to GVWD projected water rates, as
   presented to the GVWD Water Committee in June, 1996.






















   Figure 2 shows the projected water rates for single family homes in 1999
   for the Review Group s recommended plan, as well as the other two
   options represented by Consideration items B and C of this report. 
   Changes to the Waterworks Capital Plan have no effects on the water rate
   in the first year of the three year plan. By the third year of the plan
   (1999), the Staff Review Group recommendation would result in a $10
   water rate increase, compared to current capital plan funding.  For
   comparison, Consideration options B and C would result in a $12 and a $5
   increase respectively.

   The greatest impact on Vancouver s water rates results from regional
   cost increases. The GVWD s historic and projected water rates are shown
   below in Figure 3.  Their rates have quadrupled in the last 10 years,
                                  and are expected to almost triple in the
                                  next 10 years due to major water quality
                                  and supply improvements. 

                                  As a result, there is little opportunity
                                  to smooth out water rate increases by
                                  deferring City work. Deferring needed
                                  capital expenditures will further burden
                                  future ratepayers, when their rates will
                                  also be higher due to regional costs. 
                                  If Vancouver s water capital programs
                                  are substantially deferred now, water
                                  rates will increase more dramatically
                                  during subsequent Capital Plans. 
                                  Recommendation A is proposed by the
                                  Capital Plan Staff Review Group as a
                                  suitable compromise between increasing
                                  water rates, and needed City water
              Figure 3            system capital works. 

                           *     *     *     *     *