ADMINISTRATIVE REPORT


                                                               July 9, 1996
                                                           File No. 160 595


   TO:       Vancouver Traffic Commission

   FROM:     General Manager of Engineering Services

   SUBJECT:  Pedestrian Connection Under Beatty Street To SkyTrain Stadium
             Station


   RECOMMENDATION

        That BC Transit be urged to develop a plan in consultation with
        local residents, businesses, transit users and City staff, to
        reopen the underground connection to SkyTrain Stadium Station under
        Beatty Street in the context of increased security provided by
        greater pedestrian volumes and potential new developments.


   COUNCIL POLICY

   Council s top priority for transportation is walking.

   Council supports measures to increase transit use as a means of reducing
   the impacts of general vehicular traffic growth and improving regional
   air quality, as per the  Clouds of Change  initiatives.


   PURPOSE

   This report discusses BC Transit s plan to fill the west entrance
   stairwell to the pedestrian connection under Beatty Street.  The
   connection is presently closed (see Figure 1).


   BACKGROUND

   A pedestrian connection under Beatty Street at Dunsmuir Street was
   constructed as part of the ALRT/SkyTrain project, in order to provide a
   convenient walkway between the SkyTrain Stadium Station and future new
   developments in the area.  However, complementary developments with
   underground activities/walkways adjacent the station have not occurred
   to date.  The anticipated underground connection to the HA Simons
   building on the northwest corner of Dunsmuir Street and Beatty Street
   was not installed by the developer when the building was constructed.


                                      -2-


   The pedestrian connection to SkyTrain under Beatty Street was kept open
   until about 1992, and then closed because of security concerns.  The
   isolated location and corner blind spots in the connection were
   considered to be a problem because of low pedestrian volumes, even after
   additional security measures including cameras and enhanced lighting
   were added.  The closure did not impair station access as there is a
   convenient surface route across Beatty Street using the signal at
   Dunsmuir Street.  The surface route is direct and has a slightly shorter
   walking distance than the underground connection, but lacks the
   protection from weather and traffic that the connection offers. 
   Wheelchair access was not affected by the closure as the connection has
   no ramps.

   The west end of the underground connection, at the northwest corner of
   Dunsmuir Street and  Beatty Street, was originally closed by installing
   a vertical grille at the subgrade entrance to the connection corridor; 
   however, the stairwell leading down to entrance was left open.

   The Vancouver Traffic Commission on March 30, 1995 recommended:  that BC
   Transit be encouraged to make the tunnel leading from the corner of
   Dunsmuir Street and Beatty street to the SkyTrain Station available to
   transit users at least during the daytime period .  More recently, on
   May 28, 1996, the Mayor directed staff to investigate and provide
   information regarding BC Transit s plan to fill in the entrance.


   PROPOSED STAIRWELL COVER

   BC Transit have advised they intend to cover the west entrance stairwell
   to the underground connection, as it is being used as a sleeping
   quarters, dumping ground, and site for illegal activities.  The
   stairwell cavity would be filled with sand to the level of the sidewalk,
   and the surface would be finished with paving stones in order to
   maintain the look of the surrounding plaza.  Once the work is completed,
   the former entrance would be imperceptible to pedestrians.  The
   underground connection itself would not be altered in any way and could
   be opened in future with minimum effort.  Access to the station would
   not be affected as the connection is already closed.


   DISCUSSION

   If the underground connection is reopened, it would provide better
   access to transit, which is a high priority for Council.  A sheltered
   walkway would be available for SkyTrain customers.   Pedestrian delay
   and conflicts crossing Beatty Street would be reduced.
                                      -3-


   On the other hand, there are concerns regarding security and wheelchair
   access.  BC Transit indicate there are no plans to open the connection
   at present because of the security issue.  A part-time opening is not
   favoured as the pedestrian volumes would not be sufficient to provide
   security.

   In view of the above, it is recommended that BC Transit be urged to
   develop a plan to reopen the connection in the context of increased
   pedestrian activity, possibly through new developments in the area. 
   Security could be enhanced through greater pedestrian activity, as well
   as through specific security measures.  The connection should be made
   accessible to wheelchair users as a part of future developments.  Local
   residents, businesses, and transit users should also be consulted as
   part of the plan development process.

   With the plan in place, the City could work with BC Transit and with
   future developers on reopening the connection.  This is important as the
   facility represents a significant capital investment which will become
   more useful in future as more residents move into the area, new
   buildings are developed, and traffic and transit volumes increase.


                              *   *   *   *   *