ADMINISTRATIVE REPORT

                                             Date:  July 8, 1996
                                             Dept. File No.  GL



   TO:       Vancouver City Council

   FROM:     Director of Land Use and Development

   SUBJECT:  Re-approval of Strata Title Conversion -
             869-883 East Hastings Street

   RECOMMENDATION

        THAT  the  application to  convert  the  premises  at 869-883  East
        Hastings Street (Lot  C, Block 61, D.L. 181, Plan  13940) to strata
        title ownership be  re-approved in principle, but  that pursuant to
        Section  9(1) of the  Condominium Act, the  Certificate of Approval
        (Form 10)  shall not be  issued unless the following  condition has
        been met within one year of the date of this re-approval:

             Completion  of  all   work  required  by  the   City  Building
             Inspector, under the required permits, at no cost to the City,
             and  issuance  of an  Occupancy  Permit,  in  order that  this
             previously-occupied building  substantially complies  with all
             relevant by-laws.

   GENERAL MANAGER'S COMMENTS

        The  General Manager of  Community Services RECOMMENDS  approval of
        the foregoing.

   COUNCIL POLICY

   Council policy is  reflected in the City's Strata  Title and Cooperative
   Conversion Guidelines, which outline factors which Council will consider
   in reviewing applications  for converting previously-occupied  buildings
   to strata title or cooperative ownership.

   PURPOSE

   Council  re-approval is  requested for  the  application to  convert the
   previously-occupied building  at 869-883  East Hastings  Street (Lot  C,
   Block 61, D.L. 181, Plan 13940) to strata title ownership.


   BACKGROUND

   The site  is zoned M-1  and is  developed with a  three-storey building,
   constructed  in 1984, consisting  of retail uses  on the  main floor and
   offices above.  The location of the building is illustrated in Figure 1,
   below.

                                   Figure 1




























   On  June  14,  1994,  Council   granted  approval  in  principle  to  an
   application  to convert  this building  to  21 strata  lots, subject  to
   completion of upgrading work required by the City Building Inspector and
   issuance of an  Occupancy Permit.  That condition was not satisfied, and
   pursuant to Council's  policy, the approval in principle  lapsed on June
   14, 1995.   In response to a  request by the project  architect, Council
   granted re-approval  in principle on  July 11, 1995,  to be valid  for a
   further year.


   Completion of the  required work has been further  delayed because there
   have  been several offers  to purchase the  building as  is.  Consultant
   work related to building permit issuance halted with each offer since it
   appeared  the  building  would be  sold.    In  addition, the  work  and
   documentation  required  has  greatly  exceeded  initial  estimates   as
   contained in the  Department of Permits and  Licenses' inspection report
   of May 1994,  primarily due  to the  construction of  the second  floor,
   which  complicated  requirements  for  loading  and  seismic  restraint.
   However, at this time, these issues are almost resolved, and issuance of
   a building permit for the required work is imminent.  The  applicant has
   indicated his intent to complete the work within the next year.

   STAFF ANALYSIS

   The  intent  in  establishing  the  one-year  limit  for  completion  of
   Council-imposed conditions was not to  necessarily expect that in  every
   instance, all conditions  of approval could be completed  within a year.
   Rather,  the intent  was  to  terminate  approvals  in  principle  where
   applicants  clearly had  no plans  to proceed  toward final  approval by
   completing  the  required  work.    Staff  were  concerned  that  either
   revisions to relevant  City by-laws or the possible  introduction of new
   tenants who were not  aware of the strata  title approval in  principle,
   could make the approval passe.

   However, this is not a residential building, where new tenants  may have
   been  introduced without  being made aware  of the  conversion proposal.
   Further,  given that  the  applicant  submitted  an  application  for  a
   building permit in March,  1995, and that it is now in process, the City
   Building Inspector does  not believe that a new  strata title conversion
   application,   requiring  payment  of  a  fee   and  completion  of  new
   inspections, is warranted.   All inspections of the  necessary work will
   be completed under the auspices of the permits which will be issued.

   Due to  the extensive nature of the renovations  which are to be carried
   out in  the building, the  City Building Inspector supports  the request
   for re-approval, to be valid for a further one-year period.

   CONCLUSION

   Based  on  the foregoing,  the  Director  of  Land Use  and  Development
   supports this application for re-approval.

                                   * * * * *