A15
ADMINISTRATIVE REPORT
Date: May 16, 1996
Dept. File No. F587-50.01
TO: Vancouver City Council
FROM: Manager of Facilities Development
SUBJECT: Vancouver Fire & Rescue Services,
Drill Tower - Award of Contract
RECOMMENDATION
THAT the construction contract for the Drill Tower and Drafting
Pit for the Vancouver Fire & Rescue Services be awarded to Lessard
Project Management and Construction Inc. for an amount of $702,526
plus 7% GST, plus a cash allowance of $10,000 for post-tender
changes; the source of funding be the 1994-96 Basic Capital Budget
(Fire Protection).
GENERAL MANAGER'S COMMENTS
The General Manager of Corporate Services RECOMMENDS approval of
the foregoing.
COUNCIL POLICY
- Council approval is required for contracts over $300,000.
- Contracts are awarded on the basis of best value for the City.
PURPOSE
This report seeks authorization to award a contract for the Phase II
portion of the training facility to the low bidder, Lessard Project
Management and Construction Inc.
BACKGROUND
In 1995, Council approved $770,000 of the $1.23 million Fire Protection
Capital Budget for the Phase II portion of the training facility which
includes the construction of the drill tower and drafting pit.
The Phase I portion of the project included the construction of
temporary classrooms and has been tendered and completed within budget
($235,000).
DISCUSSION
By public tendering the following base bids were received for the Drill
Tower:
Lessard Project Management and Construction Inc. $702,526
Alexander Construction Ltd. 719,841
Regatta Construction 740,000
Precision Civil Installations Ltd. 748,500
Turnkey Construction Inc. 785,880
Palcor Construction Ltd. 790,449
Westpro Constructors Group Ltd. 856,500
RMT Contracting Ltd. 900,000
Civil Construction Co. Ltd. 910,400
Smith Bros. & Wilson (B.C.) Ltd. 911,000
Bynett Construction Services Ltd. 933,850
MCL Construction Limited 956,000
On the basis of the low bid, it is recommended the contract be awarded
to Lessard Project Management and Construction Inc. in the amount of
$702,526 plus 7% GST. A cash allowance of $10,000 is also recommended
for anticipated post-tender changes. The total cost of the work is
within the approved total capital funding for the project.
* * * * *