A5
ADMINISTRATIVE REPORT
Date: June 6, 1995
Dept. File No. A393-52
TO: Vancouver City Council
FROM: Manager of Facilities Development
Director of the Carnegie Centre
SUBJECT: Carnegie Centre, 1995 Renovations Project
- Contract Award
RECOMMENDATION
THAT the contract for the Carnegie Centre 1995 Renovations project
be awarded to Arts Class Construction Ltd. in the amount of
$485,357 plus GST; source of funding to be 1994 Basic Capital
Budget Account 47 05 9403 999.
GENERAL MANAGER'S COMMENTS
The General Manager of Corporate Services RECOMMENDS approval of
the foregoing.
COUNCIL POLICY
City Council approval is required for contract awards over $200,000.
Contracts are to awarded on the basis of best value for cost.
PURPOSE
The purpose of this report is to recommend awarding the contract for
Carnegie Centre 1995 Renovations to the low bidder Arts Class
Construction Ltd.
BACKGROUND
On May 5, 1994, City Council approved the Carnegie Centre Renovations
project and approved appointment of Birmingham & Wood Architects as
consultants. Funding of $561,000 was provided from the 1994 Basic
Capital Budget.
An increased budget of $662,000 was approved by Council on November 1,
1994, to include $101,000 in funds raised by the Carnegie Community
Centre Association.
The alterations provide for improvements to the learning centre, library
and administrative areas necessary to accommodate the current heavy
usage of the Centre. This project is scheduled to be carried out in the
summer and fall of 1995.
DISCUSSION
Tenders
From a publicly advertised "Request for Prequalification Submissions",
12 contractors were invited to submit tenders for this project. Six
contractors submitted tenders on June 1, 1995 as follows:
Arts Class Construction Ltd. $485,357
Pax Construction Ltd. 549,549
Homar Construction Services Ltd. 585,000
TurnKey Construction Inc. 636,460
Heatherbrae Construction Co. Ltd. 676,500
Novacom Construction Ltd. 700,680
It is recommended that the contract be awarded to the low bidder, Arts
Class Construction Ltd., in the amount of $485,357 plus GST. The low
bid is within the budgeted amount for construction.
Source of Funding and Budget
The sources of funding for the project are:
1994 Basic Capital Budget $561,000
Vancouver Foundation 25,000
BC 21 76,000
Total $662,000
The budget for the renovation project is:
Consultants' Fees $ 64,000
Construction, Contingency 575,000
Administration Costs 10,000
Permits, Tender Cost, Misc. 13,000