CITY OF VANCOUVER

ADMINISTRATIVE REPORT

 

Date:

February 8, 2005

 

Author:

Mark Lau

 

Phone No.:

7564

 

RTS No.:

04890

 

CC File No.:

1805

 

Meeting Date:

March 1, 2005

TO:

Vancouver City Council

FROM:

Director of Facility Design and Management in consultation with the General Manager of Community Services

SUBJECT:

390 Main Street Phase Two Renovation - Award of Construction Contract

RECOMMENDATION

GENERAL MANAGER'S COMMENTS

The General Manager of Corporate Services RECOMMENDS approval of the foregoing.

COUNCIL POLICY

Council approval is required for contracts over $300,000.
Contracts are to be awarded on the basis of best value for the City.

PURPOSE

The purpose of this report is to request Council’s approval to award a contract for the Phase Two Renovation of 390 Main Street to the low bidder Parkwood Construction Ltd.

BACKGROUND

On November 16, 2004, Council approved $630,000 for Phase Two of capital improvements in 390 Main Street to accommodate The Centre For Business and Community Development; source of funding to be $230,000 from 2003 Downtown Eastside Unallocated Funding Account and $400,000 from Western Economic Diversification and the Province.

DISCUSSION

From an open request of expressions of interest for prequalification of general contractors, five contractors were prequalified to submit tenders for the project. Complete tenders were received as follows:

CDC Construction Ltd.

$416,637

Novacom Construction Ltd.

$459,000

Parkwood Construction Ltd.

$382,019

Turn-Key Construction Ltd.

$389,188

Westport Construction Ltd.

$445,400

On the basis of best value it is recommended the contract be awarded to Parkwood Construction Ltd., the low bidder, in the amount of $382,019 plus GST. Parkwood Construction Ltd. met all the requirements of the tender documents.

The contract value is within the amount budgeted for this portion of the project.

All tenderers have been advised of this recommendation.

Financial Implication

The proposed capital improvements for the City-owned building at 390 Main Street are required for a creation of a Centre for Business and Community Economic Development.
Funding for this contract is provided from the budget allocation of $630,000 approved on November 16, 2004.

Conclusion

The tender process was carried out according to the City policy and low bid, Parkwood Construction Ltd. met all the requirements of the tender documents. The contract value is within the amount budgeted for this portion of the project.

* * * * *


ag20050301.htm