CITY OF VANCOUVER

ADMINISTRATIVE REPORT

 

Date:

January 13, 2005

 

Author:

Michael Irvine/Linda Syvertsen

 

Phone No.:

7375

 

RTS No.:

04821

 

CC File No.:

1805

 

Meeting Date:

February 1, 2005

TO:

Vancouver City Council

FROM:

General Manager, Engineering Services
Manager of Materials Management

SUBJECT:

Award of Contract for RFP PS04111 The Supply of Consulting Services for the Canoe Creek Sewer Separation Project

RECOMMENDATION

COUNCIL POLICY

Consultant contracts over $30,000 are to be approved by Council.

BACKGROUND

On March 11, 2003 Council authorized the City Manager to, on behalf of the City, enter into the Canada-British Columbia Infrastructure Program contract agreements. As part of this Program, three sewer construction projects are eligible to receive reimbursement of 2/3 of the total project costs from the Federal and Provincial governments. The remaining 1/3 of the funding is to be provided by the City of Vancouver.

DISCUSSION

On December 2, 2004 the City issued a Request for Proposals (RFP PS04111) for the supply of consulting services for the Canoe Creek Sewer Separation Project. In addition to notifying incumbent suppliers to the City the competition was advertised on the City's and the B.C. Purchasing Commissions websites.

The RFP called for assistance in identifying and evaluating alternate methods of trenchless sewer installation in the portion of the alignment where conventional open cut excavation options are not considered practical due to the required depth of installation or other physical site constraints as well as assistance in preparation of specifications for Tender documents to carry out the construction of the trenchless sewer installation portion of the project.

Two (2) Proposals were received and opened on January 7, 2005. Both Proposals were found to be compliant and were referred to the General Manager, Engineering Services and the Manager of Materials Management for evaluation and report.

The RFP process and evaluation process was facilitated by the Materials Management Branch of Corporate Services. The evaluation team consisted of representatives from Engineering Services, Sewage and Drainage Design Branch. Proposals were evaluated by team members individually and a composite score was assigned to each proposal based on weighted criteria. Pricing was then combined with the team composite score to provide an overall rating.

The City's objective for this RFP is to establish a contractual relationship with a vendor who has the capability and experience to provide consulting services for the Canoe Creek Sewer Separation Project that will include:

Golder Associates Ltd. scored the highest at 81.40 out of a possible 100 points.

 

Golder Associates Ltd.

Proponent #2

Evaluative

maximum points - 70

51.40

51.00

Pricing

maximum points - 30

30.00

26.92

Total RFP Score

81.40

77.92

The recommendation that the City execute a contract with Golder Associates Ltd is supported by the following:

FINANCIAL IMPLICATIONS

Funding is available in the 2003-5 Capital Plan, main sewers reconstruction (Canada - British Columbia Infrastructure Program). Funds are required at this time for the consulting costs of $59,861.00

CONCLUSION

The recommendation to authorize a contract with Golder Associates Ltd. is deemed to provide best value for the City over the term of the contract. Based on the proposals submitted, Golder Associates Ltd was the leading proponent demonstrating that their solution would be best able to provide the service requirements to the City.

* * * * *


ag20050201.htm