Vancouver City Council |
CITY OF VANCOUVER
ADMINISTRATIVE REPORT
Date:
January 19, 2004
Author:
Joanne Griffin
Phone No.:
7928
RTS No.:
3910
CC File No.:
5804-19
Meeting Date:
February 11, 2004
TO:
Vancouver City Council
FROM:
General Manager of Engineering Services
SUBJECT:
Local Improvements Subsequent Procedure - February 11, 2004
A. THAT the projects by "Petition" in Court #613 be approved.
B. THAT projects by "Initiative Principle" in Court #614 be approved except Special Item #16 as explained in this report.
Policies governing the Local Improvement process are set out in the Vancouver Charter and Local Improvements Procedure By-law.
Projects by Petition and on the Initiative Principle have been advanced under the provisions of the Local Improvements Procedure By-law and will come before a Court of Revision on February 11, 2004.
The projects are identified as follows:
Court
Item
Type
Petition
#613
1
Pavement & Curbs, Higher Zoned
2-8
Pavement & Curbs, Local Residential
9-20
Lane Pavement, Local Residential
21-27
Speed Humps
28-29
Pedestrian Collector Sidewalks
30-37
Lane Lighting
Items
Court
Item
Defeated
Type
Initiative
#614
1
Pavement & Curbs, Higher Zoned
2-10
Pavement & Curbs, Local Residential
11-13
Lane Pavement, Higher Zoned
14-17
Lane Pavement, Local Residential
18-29
Speed Humps
30
Pedestrian Collector Sidewalks
31
Sidewalk Reconstruction
SPECIAL ITEMS
Court #614, Item #16, Lane Pavement, Local Residential
Lane south of 11th Avenue from Fraser Street to Prince Albert StreetThis project is being withdrawn to allow adjacent owners to evaluate other lane options. After consultation with the owners the project may be initiated at a later date.
Capital Funds
Funds for the City's share of the projects are available from existing Engineering Department Basic Capital Accounts or are subject to approval of the 2004 Streets Basic Capital Budget.
* * * * *