CITY OF VANCOUVER

ADMINISTRATIVE REPORT

 

Date:

July 30, 2003

 

Author:

Karen Hasselfelt

 

Phone No.:

604-871-6045

 

RTS No.:

03546

 

CC File No.:

2051

 

Meeting Date:

September 11, 2003
 

TO:

Standing Committee on City Services and Budgets

FROM:

Director, Office of Cultural Affairs

SUBJECT:

Reconsideration of 2003 Cultural Grant Recommendations

RECOMMENDATION

GENERAL MANAGER'S COMMENTS

The General Manager of Community Services presents the foregoing for Council's CONSIDERATION.

COUNCIL POLICY

On November 22, 1994, City Council established the policy that cultural grant recommendations will be reconsidered only if the reconsideration requests are based on one or both of the following premises: (1) eligibility criteria have not been properly applied; or (2) the applicant's financial situation has not been accurately assessed.

Approval of grant recommendations requires eight affirmative votes.

PURPOSE

This report relays the results of staff's reconsideration of two Cultural grant applications from the second Project Grants deadline in June as requested by grant applicants, and makes recommendations based on the outcome of this process.

BACKGROUND

In November 1994, Council approved a grant reconsideration process for Community Services and Cultural grants with the following features:

The process is not intended to revisit questions of artistic merit, organizational competence or any number of other evaluation criteria. In a letter dated June 30, 2003, all Project grant applicants were advised of staff recommendations, along with reasons for recommended reductions or no grants. Two organizations requested reconsideration, as follows:

 

Original Request

Orig. Recomm.

Absolut Theatre (under auspices of Theatre Terrific)

$5,200

$0

Eastside Culture Crawl:

$ 6,500

$0

On March 25, 2003, Council approved Operating and Project grants totaling $1,390,900, leaving a balance of $40,000 for the second Project grant deadline in June. In view of the range and quality of the applications received in this second Project grant round, on July 22, 2003 Council approved a transfer of an additional $8,000 from the Organizational Development to the Projects Grants component of the 2003 Cultural Grants budget and approved staff recommendations for the Project Grant applications totalling $48,000 for the 20 Project Grant applications not involved in the reconsideration process. The approval of these grants has left no unallocated balance in the 2003 Project grants budget.

DISCUSSION

After the two applicants for reconsideration provided written information to support their requests, staff conducted a second review of each request. Discussions were held with representatives from both organizations, and a staff committee reviewed the original applications, supporting materials, and the information submitted with the reconsideration requests. Written submissions from applicants requesting reconsideration, together with staff responses are provided in Appendix A.

FINANCIAL IMPLICATIONS

This is the last round of Project grants for 2003 and there is no unallocated balance remaining in the Project Grant category of the 2003 Cultural Grants budget. The source funds for any additional grants approved by Council would be Contingency Reserve.

CONCLUSION

After a second review of the two applications for reconsideration, staff have concluded that since there are no grounds for reconsidering Absolut Theatre and that the Eastside Culture Crawl does not meet all the eligibility requirements for a Project grant, the original recommendations for no grants should remain unchanged.

* * * * *

 

Link to Appendix A

 