Agenda Index City of Vancouver

ENGINEERING - COMMUNICATIONS

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Communications PROJECT#: B-1

PROJECT TITLE: Above Ground Terminals

PROJECT DESCRIPTION:
This project involves the installation of above ground terminals to increase accessibility of cable circuits.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

This project allows more access to test points for cable trouble shooting by the installation of cabinets placed in strategic positions where cables intersect. This allows for circuit rerouting to be conducted without opening splices in manholes. This is very important to allow reconfiguring circuits quickly, as required, in a major emergency such as an earthquake. This project is a continuation of a program started in previous Capital Plans.

Account # 10013307 Order Group: CA3EB1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $ 40,000
Less Previously approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $ 40,000
2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Communications PROJECT #: B-2

PROJECT TITLE: Underground Cable Replacement

PROJECT DESCRIPTION:

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Account # 10013308 Order Group: CA3EB2

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $ 120,000
Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $ 120,000

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Communications PROJECT #: B-3

PROJECT TITLE: Underground Cable Expansion

PROJECT DESCRIPTION:

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Account # 10013309 Order Group: CA3EB3

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $ 160,000
Less Previously Approved $ 0

NET 2002 BASIC CAPITAL REQUIREMENT $ 160,000

ENGINEERING - STREET LIGHTING

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Street Lighting PROJECT #: C-1

PROJECT TITLE: Renovate & Replace Plant

PROJECT DESCRIPTION:
This section of the Street Lighting Capital Plan addresses renovation and replacement of the plant.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

1) Plant Replacement $1,030,600

Account #: see text Order Group: CA3EC1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $ 1,155,600
Less Previously Approved $ 0
NET 2002 BASIC CAPITAL BUDGET $1,155,600
2002 BASIC CAPITAL BUDGET

PROJECT TITLE: Renovate & Replace Plant (continued) PROJECT #: C- 1

PROJECT DETAIL, HISTORY, TIMING & COSTS (continued)

the 2002 Service Panel Replacement program #10012953.

2002 BASIC CAPITAL BUDGET

PROJECT TITLE: Renovate & Replace Plant (continued) PROJECT #: C- 1

PROJECT DETAIL, HISTORY, TIMING & COSTS (continued)

be replaced. The actual work will be done in 2002. No additional budget is required in 2002.

2) Facilities Management $50,000

For investigating design and policy development by staff and external consultants. This program

3) Infill Lighting - Safer City $267,000

A program to inspect all bus stops in the City has been completed. According to various

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Street Lighting PROJECT #: C-2

PROJECT TITLE: New Local Improvement

PROJECT DESCRIPTION:
City share of the funding required for Street Lighting and Lane Lighting Local Improvements

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Lane & Street Lighting Improvements $0

Funding is required for the city's share of street lighting and lane lighting local improvements in 2002. Existing funding is adequate to meet the funding requirements for 2002.

Lanes $24,000 $216,000 $240,000
Streets $ 9,000 $ 27,000 $ 36,000

Account#: 30004540 Order Group:CA3EC2A

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $ 0
Less Previously Approved $ 0

NET 2002 BASIC CAPITAL BUDGET $ 0

ENGINEERING - SEWERS

Project
Number

Program - 2002

Est Gross
Cost (000)

Grants & Other
Sources (000)

Basic Capital
Budget (000)

D 1

SYSTEM REPLACEMENT/
SEPARATION

1. Main Sewer Reconstruction
a) China Creek Trunk
b) Grandview-Woodlands
c) Hastings-Sunrise
d) Still Creek
e) Cambie- Heather
f) Terminal Avenue
g) Downtown Peninsula
h) Kitsilano-South Granville
i) Balaclava
j) West Point Grey
k) Fraser River
l) LGG

Sub Total - Main Sewer
Reconstruction

2. Connection & Manhole
Reconstruction
3. Local Repairs & Catch Basin
and Spur Reconstruction
4. Upgrade and Replacement of
Pump Stations

TOTAL - SYSTEM REPLACEMENT/SEPARATION

Continued...2

$2,800
$ 500
$2,100
$ 300
$1,300
$1,500

$ 600

$ 900
$1,500
$2,300
$1,030
$ 635

$15,465

$900

$775

$55

$17,195

$ 635

$635

$275

$910

$2,800
$ 500
$2,100
$ 300
$1,300
$1,500
$ 600
$ 900
$1,500
$2,300
$1,030
$ 0

$14,830

$900

$500

$ 55

$ 16,285

ENGINEERING - SEWERS

Project
Number

Program - 2002

Est Gross
Cost (000)

Grants & Other
Sources (000)

Basic Capital
Budget (000)

D 2

D 3

D 4

D 5

D 6

SYSTEM MANAGEMENT

1. Television Inspection

2. Investigation for Design

TOTAL SYSTEM MANAGEMENT

OTHER POLLUTION ABATEMENT

1. Liquid Waste Management

2. Inflow/Infiltration Study

3. Sewer Separation on Private
Property

TOTAL POLLUTION ABATEMENT

SYSTEM EXPANSION

PUBLIC SEWER CONNECTION

DISCOUNT ON DEBENTURES

TOTAL 2002 SEWERS
CAPITAL BUDGET

$200

$100

$300

$0

$0

$430

$430

$0

$5,000

$0

$22,925

$5,000

$0

$5,910

$200

$100

$300

$0

$0

$430

$430

$0

$0

$0

$17,015

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Sewers & Drainage PROJECT #:D - 1

PROJECT TITLE: System Replacement/Separation

PROJECT DESCRIPTION:

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

The City of Vancouver has adopted a strategy of continuous sewer replacement instead of periodic large construction programs. Some other cities have neglected their infrastructure until crises develop, and then faced financial difficulties and large, inefficient and disruptive reconstruction programs. In contrast, Vancouver has had an ongoing replacement program for sewers which spreads the costs of capital work more evenly among taxpayers over time and allows us to maintain a stable, well trained labour force. The program replaces 1% of the system annually based on an anticipated 100 year life for the new pipes being constructed. This policy was approved by Council in 1981 as part of the Sewers Long Range Plan and reaffirmed by Council in 1991 as part of the City's Design and Service Level Standards. It was also approved in each subsequent Capital Plan and reaffirmed when Council endorsed the Liquid Waste Plan submission to the Province in 2000 and 2001.

This program is effective in preventing serious collapse of sewers and in addressing major flooding problems in the City. It also has a major environmental benefit by addressing Vancouver's sewage overflows to our local waters. As this program progresses, sewage overflows will be reduced and eventually eliminated. It complies with Provincial policy and objectives for combined sewer overflow reduction and elimination, and is necessary to meet our commitments under the Liquid Waste Management Plan. In addition, as the sewer system is reconstructed, a reduction in dry weather flows to the Iona Sewage Treatment Plant will occur, thus offsetting the City's Regional District sewage levy.

Account # See Text Order group: CA3ED1

PROJECT FUNDING:
Total Cost $ 17,195,000

Total 2002 Budget $ $ 16,285,000
Less Previously Approved $ $ 0

NET 2002 BUDGET $ $ 16,285,000

2002 BASIC CAPITAL BUDGET

2002 BASIC CAPITAL BUDGET

PROJECT TITLE: System Replacement/Separation (continued) PROJECT #: D - 1

PROJECT DETAIL, HISTORY, TIMING & COSTS (continued)

The following is a summary of the 11 Basin Areas and their estimated 2002 budgets:

2002 BASIC CAPITAL BUDGET

PROJECT TITLE: System Replacement/Separation (continued) PROJECT #: D - 1

PROJECT DETAIL, HISTORY, TIMING & COSTS (continued)

2002 BASIC CAPITAL BUDGET

PROJECT TITLE: System Replacement/Separation (Continued) PROJECT #: D - 1

PROJECT DETAIL, HISTORY, TIMING & COSTS (continued)

Sub-Total Main Sewer Reconstruction: $ 15,465,000

2002 BASIC CAPITAL BUDGET

PROJECT TITLE: System Replacement/Separation (continued) PROJECT #: D - 1

PROJECT DETAIL, HISTORY, TIMING & COSTS (continued)

2 Connection and Manhole Reconstruction $ 900,000 a/c# 30004250

3 Local Repairs: Catch Basins and Spurs $ 775,000 a/c# 30004251

4 Upgrade and Replacement of Pump Stations $ 55,000 a/c# 30004252

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Sewers & Drainage PROJECT #: D - 2

PROJECT TITLE: System Management

PROJECT DESCRIPTION:

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Account # see text Order group: CA3ED2

PROJECT FUNDING:
Total Cost $ 300,000

Total 2002 Budget $ 300,000
Less Previously Approved $ 0

NET 2002 BUDGET $ 300,000

2002 BASIC CAPITAL BUDGET

PROJECT TITLE: System Management PROJECT #: D - 2

PROJECT DETAIL, HISTORY, TIMING & COSTS (continued)

2 Investigation for Design $ 100,000 a/c# 30004254

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Sewers & Drainage PROJECT #: D - 3

PROJECT TITLE: Other Pollution Abatement

PROJECT DESCRIPTION:

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Account #: see text Order Group: CA3ED3

PROJECT FUNDING:
Total Cost $ 430,000

Total 2002 Budget $ 430,000
Less Previously Approved $ 0

NET 2002 BUDGET $ 430,000


2002 BASIC CAPITAL BUDGET

PROJECT TITLE: Other Pollution Abatement PROJECT #: D - 3

PROJECT DETAIL, HISTORY, TIMING & COSTS (continued)

2 Sewer Separation on Private Property $430,000 a/c# 30004255

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Sewers & Drainage PROJECT #: D - 5

PROJECT TITLE: Public Sewer Connections

PROJECT DESCRIPTION:

Installation of public sewer connections on residential and commercial properties.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Public Sewer Connections $ 5,000,000

In 2001, the City installed approximately $ 5,000,000 worth of public sewer connections. For 2002, we anticipate a similar level of residential and commercial construction activity. These costs are recovered from public sewer connection fees charged to developers and builders.

Account#: N/A Order Group: CA3ED5

PROJECT FUNDING:
Total Cost $ 5,000,000

Total 2002 Budget $ 0
Less Previously Approved $ 0

NET 2002 BUDGET $ 0

ENGINEERING - WATERWORKS

ENGINEERING - WATERWORKS

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-1a

PROJECT TITLE: Replacement of Distribution Watermains

PROJECT DESCRIPTION: Replacement of distribution watermains in various locations throughout the City.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

The City's distribution watermain network consists of over 1,400 kilometers of watermains with a replacement value of $800 million. Since 1994, the Waterworks distribution main replacement program has been organized to minimize pipeline life cycle costs and to replace watermains in a uniform manner. The 97 - 99 Capital Plan was based on an 85 year economic life and replaced 1.2% of the distribution system each year.

Past Capital Plans have replaced a significant number of high maintenance, lower design life watermains. As replacement of these mains has increased the economic life cycle of the system as a whole, the current Capital Plan reduced the annual replacement rate to 1%. This is in agreement with the Waterworks Long Range Capital Plan, which recommended working toward a 100 year replacement schedule.

Engineering Services recently assumed control and operations of the Stanley Park water system. Much of the system has passed its economic life span, and needs to be upgraded to current standards. Approximately $1.0 million of the $7.4 million budget will be spent on the replacement and rehabilitation of mains in the Stanley Park system.

Account # 30004278 Order Group: CA3EE1AXX1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $7,400,000

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $7,400,000

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-1b

PROJECT TITLE: Transmission Main Replacement

PROJECT DESCRIPTION: Design and construction of transmission mains to maintain water pressure and water supply during periods of high demand and the construction of replacement mains throughout the City.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

This program was funded entirely in 2000. No further funding is anticipated during the 2000 - 2002 Capital Plan.

Account #: N/A Order Group: CA3EE1B

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $0

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $0

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-1d

PROJECT TITLE: Replacement Meters & Services

PROJECT DESCRIPTION: Replacement of old water meters and services at various locations throughout the City.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

This program focuses on replacing old water meters and old steel, galvanized, cast iron and copper service pipes that have reached the end of their useful service life. The City has approximately 105,000 service pipes, including 14,000 metered services. When it is economical, old services are replaced as part of the watermain replacement program. This program is intended to fund services that require replacement outside of the watermain replacement program. Meters are maintained on a regular basis to ensure accurate billing, and require replacement every 10 to 15 years.

Water Meters $500,000 Account# 30004279

As meters age they typically under-read consumption, resulting in lost revenue for the City. A Waterworks study showed that neglected 4 inch diameter meters recorded only about 80% of actual consumption. Subsequent to that study, funding for water meter replacement was increased to facilitate accurate water measurement. Funding for 2002 is unchanged from 2000 and 2001, as we continue to replace outdated technology with contemporary "touch-pad" technology.

Account# : see text Order Group: CA3EE1D

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $2,400,000

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $2,400,000

2002 BASIC CAPITAL BUDGET

PROJECT TITLE: Replacement Meters & Services PROJECT #: E-1d

PROJECT DETAIL, HISTORY, TIMING & COSTS (continued)

Service Pipes $1,900,000 Account# 30004280

The City has approximately 105,000 water services ranging in size from 15 mm to 300 mm diameter. Of this total, 99,000 are 50 mm and smaller and 6,000 are larger than 50 mm. Services are replaced if they leak and break due to excessive corrosion or they have lost hydraulic capacity. The goal of the service pipe replacement program is to achieve, on average, a life-cycle replacement rate through the combination of work undertaken through this program and new installations funded by redevelopments.

The smaller services are generally copper, with some galvanized iron, cast iron, lead and plastic pipes. The design life of a small service is approximately 30 to 50 years, and approximately 30,000 of these services are now at least 50 years old. A uniform replacement rate target is approximately 900 services per year with an annual cost of $1,400,000. For 2002, the expenditure will be $1,800,000 to make up for lower than target replacement rates in earlier years.

The large diameter service pipe inventory is made up of ductile iron, cast iron, and steel. The City has approximately 1,000 large unlined services with a design life of roughly 60 years. During the last two Capital Plans, funding for large service replacements was increased to as much as $1,000,000 per year to catch up on the backlog of work. This funding has been reduced to $100,000 per year to reflect a life-cycle replacement program for the unlined pipes. Approximately 15 services per year will be replaced with this level of funding.

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-1e

PROJECT TITLE: Replacement of Fire Hydrants

PROJECT DESCRIPTION: Replacement of fire hydrants independently from water main replacement programs

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

The City has approximately 6,000 fire hydrants dating to the 1920's. A considerable number of hydrants will be replaced through the distribution main replacement program; however, some hydrants need to be replaced or relocated outside of the distribution main replacement program.

Approximately half of the City's hydrant inventory has unlined cast iron service pipes connecting them to the distribution watermains. The unlined pipe has a tendency to corrode and become tuberculated. Tuberculation impedes water flow and large losses of pressure result when fire flows are drawn through the tuberculated pipes.

In areas of the City that have low pressure or capacity problems, the pressure loss caused by the tuberculated service pipes and slide gate hydrants can lower the available flow of the hydrant below an acceptable level. Replacing the older slide gate hydrants with newer compression type hydrants and cement lined service pipes will address the pressure loss problem much less expensively than increasing supply pressure in the watermains.

The 2002 Budget is has been increased to complete the work envisioned in the Capital Plan.

Account # 30004281 Order Group: CA3EE1EXX1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $300,000

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $300,000

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-2a

PROJECT TITLE: Addressing Growth: Transmission Capacity Program

PROJECT DESCRIPTION: Construction of transmission mains to restore pressure and flow in the City's water system.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

The City and the Lower Mainland are experiencing rapid population growth, increasing density, and changes in land use which strain the City and District water systems. The result has been a gradual decrease in water pressure during high demands, and difficulty in supplying the volume of water necessary to meet current fire protection standards.

The west side of the 570 Pressure Zone (Arbutus Ridge, North Dunbar and West Point Grey) is prone to low pressures during summer and has very little redundancy of supply. During the 1986 First Narrows crossing failure, much of this area had very limited water service and poor fire protection. A total of $5 million was allocated in the 2000-02 Capital Plan for transmission main work to address these system shortcomings. Through the design process, opportunities have recently been realized that reduce the total estimated cost to $4.2 million. Above the $1.5 million that was allocated in previous years, an additional $2.7 million will be needed to complete the project.

An additional $1.2 million was allocated in this Capital Plan for connection work to the GVWD's proposed Boundary #5 transmission main. As the GVWD has now postponed the Boundary #5 construction to beyond 2005, this item will not be included in the 2002 Budget.

Account # 30004282 Order Group: CA3EE2AXX1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $2,700,000

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $2,700,000

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM:Waterworks PROJECT #: E-2b

PROJECT TITLE: Fire Upgrading for Developments

PROJECT DESCRIPTION: Upgrading or extension of watermains to maintain or increase system capacity for fire protection of new developments.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

High density developments often increase water demand beyond the existing system's capacity. This program funds local system improvements to accomodate new development projects. The City's practise is to seek cost-sharing from developers for any upgrades required. In areas where a deficiency exists prior to redevelopment, the City funds the upgrades to eliminate the current deficiency and the developer is charged for the additional work that is required because of the redevelopment. This category provides funding for the City's share.

Projects in this program are difficult to predict. They depend upon the amount of development activity in the City and the specific locations of those developments. During 1997 - 2001, the program saw less activity than during previous Capital Plans. Therefore, remaining funding from the 97 - 99 Capital Plan is sufficient to fund this program for 2002.

Account # 30004283 Order Group: CA3EE2BXX1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $0

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $0

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM:Waterworks PROJECT #: E-2c

PROJECT TITLE: Conservation Capital Projects

PROJECT DESCRIPTION: Capital construction projects oriented toward water conservation.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Conservation of water has a significant role in the design of the water transmission system. Peak hour water demand is now 20% lower than historic levels. This change has deferred transmission watermain construction and the need for additional storage capacity.

The GVWD's bulk water cost also continues to increase rapidly. The City will spend about $26 million in 2002 on water purchased from the GVWD. This cost is projected to be $34 million per year by 2008. With water becoming more expensive, the economic benefits of conservation become more apparent.

During 2002 Waterworks will continue a number of projects oriented toward reducing drinking water consumption. The projects fall under the following three categories:

1. Reducing residential and Parks Board use of drinking water for irrigation by replacing high maintenance plants with native plants.

2. Reducing Parks Board use of drinking water for ornamental purposes, primarily by developing supplemental sources and installing recirculation systems. Conservation projects under development aim to reduce water consumption at the Charleson Park waterfall, the Devonian Park water feature and Trout Lake.

3. Greenways program demonstration projects to promote low irrigation landscaping and rain-barrel use.
Account # 30004284 Order Group: CA3EE2CXX1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $100,000

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $100,000

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-2d

PROJECT TITLE: New Meters & Services

PROJECT DESCRIPTION: Installation of new services, meter chambers on City Streets, meter installation on private property, and the purchase of new meters and appurtenances

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

New Services $50,000 Account# 30004285

The City funds 100% of the cost for construction of new water services required for secondary suites. All other water services are funded through customer connection fees. The number of new secondary suite services is small, and the funding request is adequate for about 20 services per year.

Discontinues ($50,000) Account# 30004286

Effective June 1, 1995, Council approved fees to recover the cost of discontinuing old water services. The cost applies where a development requires more than one existing service to be discontinued as part of the new servicing arrangements. The cost is for extra excavation and associated work.

Meters $600,000 Account# 30004287
The water consumption of all customers, with the exception of single family and duplex residential customers, is metered. The water meters are owned and maintained by the City. Funds are requested annually for the purchase of new meters, remote readouts, and meter parts.
Account#: see text Order Group: CA3EE2D

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $600,000

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $600,000

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-2e

PROJECT TITLE: Minor Improvements to the System

PROJECT DESCRIPTION: This is an ongoing program of miscellaneous types of work, generally unpredictable and required on short notice.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

This is an ongoing program of miscellaneous minor works that are not associated with the major capital programs. Work includes items such as valve chambers, short watermain installations or replacements, flow tests, computer design work, and water quality monitoring stations.

Account # 30004288 Order Group: CA3EE2EXX1

PROVIDED FROM:

Total 2002 Basic Capital Budget $200,000

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $200,000

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-3a

PROJECT TITLE: Dedicated Fire Protection System (DFPS)

PROJECT DESCRIPTION: Design and Construction for the Dedicated Fire Protection System (DFPS)

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Construction work for this project will extend into 2002; including the connection work between the downtown system and the False Creek crossing, as well as the remaining pipeline work through Kitsilano and Fairview Slopes. As this project was funded entirely in 2000-2001, no additional funding is requested for 2002.

Account # : N/A Order Group: CA3EE3A

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $0

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $0

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-3b

PROJECT TITLE: Emergency Water Supplies

PROJECT DESCRIPTION: Investigation, design and construction of emergency alternative water supplies for fire fighting and drinking water.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Following an emergency, such as a major transmission main failure or an earthquake, portions of the City and District potable water systems are expected to become dysfunctional. To maintain critical fire fighting and drinking water supplies, alternative sources are proposed to be developed. Alternative fire supplies can be provided from a number of non-potable sources such as the ocean, the Fraser River, lakes and pools. Alternative drinking water supplies are limited to storage options, ground water or transportation from external sources.

In 2001, funds were allocated for investigation and potential development of an emergency groundwater supply in partnership with the Vancouver Hospital complex. The hospital group is presently considering the development of on-site storage during their 2005 - 2020 site redevelopment, which would provide an excellent opportunity for a shared groundwater facility. As the planning process with the hospital group has yet to proceed beyond the concept stage, this project is not anticipated to go ahead within the 2000-2002 Capital Plan years. Therefore, remaining funding from 2000-2001 is sufficient to fund this program for 2002.
Account # : N/A Order Group: CA3EE3B

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $0

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $0

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Waterworks PROJECT #: E-4a

PROJECT TITLE: Telemetry System

PROJECT DESCRIPTION: Telemetry equipment for monitoring pressure and flow within the water system and for the remote control of pressure regulating valves and other facilities.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

The City operates a telemetry system that monitors operational information from approximately 40 sites throughout the water system. The information that is collected and stored by the telemetry system is essential for monitoring water demands, system breaks, and system performance as it alerts staff to problem areas.

Telemetry system work proposed for 2002 includes improving radio communication from stations that presently provide unreliable data transmission and replacing outdated operating software. In addition to this work, new telemetry stations will be installed in problem areas of the City network where system pressures need to be accurately monitored. The 2002 Budget proposal has been reduced significantly from the Capital Plan allocation, given a reduction to the scope of planned work and the availability of newer, less expensive, telemetry technology.

Account # 30004289 Order Group: CA3EE4AXX1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $200,000

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $200,000

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM:Waterworks PROJECT #:E-4b

PROJECT TITLE:Engineering and Site Investigation

PROJECT DESCRIPTION:Engineering and site investigations for product evaluation, research and project planning.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

Funds are requested annually to provide for miscellaneous engineering investigations, such as:

    - evaluation of new products (valves, meters, etc.) prior to tendering

- evaluation of materials in response to lawsuits

    - pilot studies of new construction and rehabilitation techniques such as trenchless technologies

- engineering studies such as hydraulic model calibration for planning transmission projects

Annual Funding of $100,000 is consistent with previous levels of funding for this program.

Account # 30004290 Order Group: CA3EE4BXX1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $100,000

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $100,000

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM:Waterworks PROJECT #:E-5a

PROJECT TITLE: Water Quality Projects

PROJECT DESCRIPTION: Capital projects that reduce the number of dead end, low flow and tuberculated watermains, and construct treatment facilities where required.

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

This program funds capital improvements to ensure adequate protection of water quality throughout the distribution system. Such projects are typically goal-oriented towards improving chlorine residuals, and can range from system modifications that eliminate low flow and tuberculated pipes to the installation of small scale disinfection stations in areas that cannot be corrected through other means.

The 2000-2001 Capital Budgets included a total of $500,000 for piping changes. Approximately half of this total will be spent in 2002 on an epoxy lining project. Some areas of the City distribution system have high total coliform counts, due to a combination of low demands and tuberculation build-up in unlined cast iron mains. The tuberculation build-up results in a greater bio-film surface area, which quickly depletes residual chlorine in the water. This project will strip the tuberculation build-up from these mains and the epoxy lining will prevent future tuberculation growth.

The 2000-2002 Capital Plan included $2.5 million for the small scale disinfection stations. No rechlorination stations will be built until the impact of Seymour and Capilano Reservoir filtration on local water quality can be assessed. Therefore, this work will be deferred to beyond 2002. In the interim, additional piping and pressure regulation will be installed to minimize stagnant areas in the distribution system. This work can be funded from previous budgets.

Account#: N/A Order Group: CA3EE5

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $0

Less Previously Approved $0

NET 2002 BASIC CAPITAL REQUIREMENT $0

ENGINEERING - YARD

2002 BASIC CAPITAL BUDGET

DEPARTMENT: Engineering PROGRAM: Yards PROJECT #: F-1

PROJECT TITLE: Yards Closure and Replacement

PROJECT DESCRIPTION: Cambie Yard Replacement

PROJECT DETAIL, HISTORY & OBJECTIVES, TIMING & COSTS

This submission is for the third year of funding for the replacement of the Cambie Works Yard and three satellite yards. In 1993, the City purchased lands on the former BN Rail yard for this purpose. The 2000 - 2002 Capital Plan provides $15,928,000 of funding toward this new facility. This submission is for the balance of the funding in the capital plan, $6,928,000, for the construction of the yard.

Account# 30005178 Order Group: CA3EF1XX1

PROJECT FUNDING:

PROVIDED FROM:

Total 2002 Basic Capital Budget $ 6,928,000

Less Previously Approved $ 0

NET 2002 BASIC CAPITAL REQUIREMENT $ 6,928,000


Comments or questions? You can send us email.
[City Homepage] [Get In Touch]

(c) 1998 City of Vancouver