POLICY REPORT
ENVIRONMENT
Date: 18 April 2000
Author: S. McTaggart
Phone: 873-7356 RTS# 01399CC File No.3206
Council: May 2, 2000
TO: Vancouver City Council
FROM: General Manager of Engineering Services in consultation with the Director of City Plans
SUBJECT: Brunette Basin Watershed Plan
RECOMMENDATION
A. That the goals, objectives and guiding principles in the draft Brunette Basin Watershed Plan be taken into consideration when carrying out City activities in the Still Creek drainage basin.
B. That the establishment of a regional watershed coordinating committee be endorsed to help facilitate current programs and the development of new ones in accordance with the proposed strategic management options listed in Appendix A and that staff be authorized to participate for the purpose of coordinating and facilitating watershed related projects and partnerships.
CITY MANAGER'S COMMENTS
The City Manager RECOMMENDS approval of the foregoing.
COUNCIL POLICY
The Still Creek CD-1 Guidelines (adopted April 1990) call for development to occur in a manner consistent with retaining and enhancing the open watercourse. Policies and guidelines for Highway Oriented Retail and I-2 and I-3 uses in the Grandview/Boundary Industrial area (adopted July 1999) reinforce the enhancement of Still Creek including daylighting wherever possible.
The Greenways Plan and Green Zone (adopted July 1995) call for the protection and enhancement of Vancouver's ecologically important areas, including Still Creek.
Council has previously approved a number of recommendations concerning the development of the Liquid Waste Management Plan which include staff participation on related task force groups.
Directions under the City Plan approved by Council include:
· consider environmental impacts when making decisions on land use, transportation, and City services;
· establish spending priorities for City and regional sewer, water and transportation improvements.
PURPOSE
To summarize the key findings and recommendations of the draft Brunette Basin Watershed Plan and to recommend activities in the Plan related to the Still Creek drainage basin.
BACKGROUND
The Brunette watershed on the Burrard peninsula is a 73 square kilometre, highly urbanized area that drains to the Fraser River. It contains major concentrated growth centres, dense industrial and residential areas, major traffic and utility corridors, extensive road networks and a population of over 175,000 people. Over 20 percent of the watershed area currently exists as protected park, water bodies, wetlands or undeveloped green space.
The Brunette watershed receives drainage and stormwater runoff from portions of Vancouver (Still Creek), Burnaby, Coquitlam, New Westminster and Port Moody. It is also defined as a "Drainage Area" under the Greater Vancouver Sewerage & Drainage District Act with the District, on behalf of its members, responsible for drainage conveyance in the main Still Creek/Brunette channel and the lower portions of several tributaries. The basin area in Vancouver represents approximately 13% of the entire watershed.
Recognizing the importance of this waterway, the Brunette Basin Task Group (BBTG) was formed under the Greater Vancouver Regional District's (GVRD's) Liquid Waste Management Plan initiative in 1997 as a pilot project in multi-stakeholder, consensus-based urban watershed management. It consists of representatives from all municipalities in thedrainage basin, GVRD, Department of Fisheries & Oceans, Ministry of Environment Lands and Parks, UBC Institute for Resources and Environment, BCIT Fish and Wildlife and the Sapperton Fish and Game Club. As part of the process, three open houses were also held to obtain input from the public. The BBTG has completed a draft Plan (copy on file in City Clerk's Office) and has made several recommendations.
DISCUSSION
In a complex urban area such as the Brunette Basin, activities by residents, businesses, environmental stewardship groups, municipalities, the GVRD, and senior governments all impact the watershed. In order to provide a balanced approach to meet the environmental, urban growth, public recreation and flood risk management challenges, a watershed plan is widely recognized as the basic building block of an integrated solution.
GOALS, OBJECTIVES AND PRINCIPLES
The Brunette Basin Watershed Plan was developed with the overall goal to "protect or enhance the integrity of the aquatic and terrestrial ecosystems and the human populations they support in a manner that accommodates growth and development". The Plan has four objectives:
Environmental: protect or enhance aquatic habitat, terrestrial habitat and biodiversity.
Social: enhance recreational opportunities and minimize health and safety impacts related to flooding and poor water quality.
Financial: minimize the cost of carrying out the plan and minimize property damage due to flooding.
Learning: increase the understanding of natural systems and impact of the plan on these systems and human health.Based on these goals and objectives, a set of guiding principles was established and used as a framework to plan and evaluate programs. These principles were developed into three main themes: Impervious Area, Stream Corridor Protection, and Integrated Approach.
The Plan calls for generally minimizing "Impervious Areas" where possible in the drainage basin. The imperviousness of an area is determined to be critical to a stream's hydrology and habitat. There are many benefits from a water quantity and quality perspective in returning water to the soil, which acts as a sponge and filter, rather than collecting the water on impervious surfaces and piping it to the nearest stream.
With regard to "Stream Corridor Protection", the Plan states that stakeholder agencies should work toward protecting and enhancing existing stream habitat and riparian areas, establishing effective buffers over the long term, utilizing Best Management Practices to reduce runoff and to enhance base flows and designing new in stream structures to accommodate fish passage. In addition, stream corridors should be protected and managed by balancing the needs for storm water conveyance, recreational use, protecting life and property from flooding, and protecting aquatic habitat. Watershed strategies must also be cost effective, affordable and reliable.
With regard to the "Integrated Approach", the Plan states that strategic options should be integrated with land use planning, operations and maintenance, development programs, and other agency programs. It also states that activities within the watershed should be coordinated to provide continued and effective partnership and participation among all levels of government, regulatory agencies, businesses and the local community.
The Plan proposes that all municipalities, the GVRD and senior governments integrate the goals, objectives and guiding principles into their day-to-day operations in the watershed. Accordingly, it is recommended that Vancouver take these into consideration when carrying out activities in the Still Creek drainage basin. As noted below, strategic options for the Brunette Basin need to be coordinated with planning for the Grandview/Boundary Industrial Area
COORDINATING COMMITTEE AND STRATEGIC OPTIONS
To assist in coordinating the work in the drainage basin, the Plan proposes that a committee be established made up of the GVRD, municipalities, and other stakeholders within the Brunette Basin. Their mandate will be to help facilitate current programs and examine the proposed strategic options listed in Appendix A in order to develop additional work programs. Any major work programs that are developed from these options would be subject to Council approval prior to their implementation.
It is recommended that Council endorse the formation of the coordinating committee and that staff from Vancouver be authorized to sit on this committee. Staff participation would be integrated into existing work and would not require additional funding.
Many initiatives in the Plan have already been completed or are currently underway. With respect to improving water quality in Vancouver, staff have recently completed an inflow/infiltration and cross-connection project in the Still Creek area and new impervious area regulations are currently being considered to limit the amount of impervious areas on residential properties. Other major initiatives being examined include developing flood protection measures for Still Creek, daylighting culverted portions of Still Creek asdevelopment occurs, and developing memorandums of understandings with senior governments with respect to new regulations under the Fish Protection Act. In July 1999 Council approved proceeding with Grandview/Boundary Industrial area planning including development in support of the Skytrain stations, opportunities for high-tech industry, (I-3) and Highway Oriented Retail along Grandview Highway. Since Still Creek runs through the precinct, Grandview/Boundary planning initiatives must be coordinated with stream protection opportunities.
CONCLUSION
The Brunette Basin Watershed Plan has been developed to reflect a balance of watershed management options with respect to environmental protection, flood control, land use planning, financial constraints and public interest. The results of the comprehensive watershed scale approach have produced a management plan that clearly defines the common goal for the watershed and yet provides flexibility to all stakeholder municipalities, agencies and groups to develop the detailed implementation strategy and action plan that best suit their own requirements.
-----
APPENDIX A
Proposed Strategic Options for the Watershed Plan
A. POLICIES, PRINCIPLES AND BYLAWS
1
Develop floodplain management strategy and associated bylaws
2
Delineate existing riparian, wetland and flood storage areas and establish policy to protect from development, construction impacts, locating of new utilities or facilities, etc.
3
Develop watercourse protection and sediment and erosion control bylaw
4
Establish, mark and enforce suitable right-of-way/easements for maintenance
5
Consider property acquisition of riparian, wetland and flood storage areas where local planning process provides opportunity
6
Integrate stormwater management and Best Management Practices guide with land use planning tools - policy statements in Official Community Plans and zoning and subdivision bylaws; establish effective impervious area reduction guidelines or bylaw
7
Develop subwatershed stormwater management plan
8
Improve fish passage and enhance/revegetate as part of facility repair or upgrades
9
Consider daylighting where local planning process provides opportunity
B. EDUCATION AND STEWARDSHIP PROGRAMS
1
Municipal and district staff training
2
Contractor/developers program
3
General public program on watershed program
4
School curriculum program
5
Local stream restoration activities/festivals (cleanups, planting, invasive species control, etc.)
6
Signage/kiosks as part of Greenways
7
Riparian landowner contact program
8
Recognition/awards program in business and resident categories
Appendix A - Proposed Strategic Options for the Watershed Plan ( continued...)
C. IMPROVEMENT PROGRAMS
1
Sewer rehabilitation program - inflow/infiltration and cross-connection elimination
2
Flood management strategy
3
Spill response program - review and clarify
4
Bank erosion control and revegetation strategy - bank stabilization and enhancement, bioengineering considered before rip rapping, etc.
5
Fish passage improvements
6
Greenways and recreational corridors incorporating streams
7
Baseflow augmentation; infiltration basins
8
Riffle weirs
9
Culvert upgrades or bridge replacement
10
Wetland, wet or dry detention pond, biofiltration pond
11
Stream complexing and off-channel habitat; reduce channelization
12
Dredging Burnaby Lake
* * * * *