ADMINISTRATIVE REPORT
Date: November 26, 1999
Author/Local: Piet Rutgers 8463
RTS No. 01154CC File No. 1602
Council: January 11, 2000
TO:
Vancouver City Council and
Park BoardFROM:
General Manager of Parks & Recreation in consultation with Director of Financial Planning and Treasury Services
SUBJECT:
1999 Park Board Capital Budget Amendment
RECOMMENDATION
THAT the 1999 Park Board Capital Budget be increased by $458,450 with the source of funding being Senior Government grants and contributions from various community organizations.
POLICY
Council approves the Park Board budgets.
BACKGROUND
On May 6, 1999, City Council approved the Park Board 1999 Capital Budget in the amount of $6, 713,000.
DISCUSSION
Since that time the Board through its Community Partners has received the following additional Senior Government Grants and contribution.
Project
Total Cost
Previously Approved
Additional Contribution/
GrantContribution
Moberly Hall -Conversion of Community Hall to Arts and Cultural Center
$426,950
$288,500
$138,450
Government of B.C.
Stanley Park -Salmon Stream Aquarium to Coal Harbour - Design Phase
$200,000
$ 40,000
$160,000
Vancouver Aquarium
AssociationLost Lagoon Biofiltration Pond to treat Causeway runoff -
Design Phase$160,000
0
$160,000
BC Transportation Financing Authority
TOTAL
$458,450
CONCLUSION
Approval of the additional funding is sought to implement these already approved projects. The contributions from Senior Government and Community Groups represent a significant funding towards updating the Park Board Infrastructure and/or enhancing Stanley Park.
* * * * *