CITY OF VANCOUVER

ADMINISTRATIVE REPORT

 

Date:

March 26, 2004

 

Author:

Ken Bayne

 

Phone No.:

873-7223

 

RTS No.:

04129

 

CC File No.:

1611

 

Meeting Date:

April 20, 2004

TO:

Vancouver City Council

FROM:

General Manager of Corporate Services / Director of Finance in consultation with Capital Plan Staff Review Group

SUBJECT:

2003 -2005 Capital Plan: Funding Adjustments

RECOMMENDATION

CITY MANAGER'S COMMENTS

COUNCIL POLICY

Council approves the 3 year Capital Plan programs and projects and any alterations to that plan. Council also establishes the funding allocation in the Capital Plan based on recommendations of the Capital Plan Staff Review Group and Director of Finance.

PURPOSE

The purpose of this report is to advise Council of funding issues related to several projects in the 2003-2005 Capital Plan and to recommend an approach to providing for funding shortfalls. The report also seeks Council approval of a funding source for the grant approved for the Millennium Sports Facility Society.

BACKGROUND

The 2003-2005 Capital Plan and associated financial plan was approved by Council in September, 2002. The borrowing authority explicit in the financial plan was approved by the voters at the time of the 2002 civic election. The Capital Plan provides funding for major maintenance and upgrading of existing City infrastructure, including sewer and water systems, streets and electrical infrastructure, parks and buildings. The Plan also includes funding for replacement or new facilities. Limited funding is also available for provision of support to outside organizations undertaking work on their own or leased City property. A high level summary of the funding allocations and sources in the Capital Plan is included in Appendix A.

On January 27, 2004, Council approved a grant to the Millennium Sports Facility Society as follows:

With the recent decision to phase-in the revised City-wide DCL, the cost of this grant to the Millennium Sports Facility Society is anticipated to be $1.0 million.

DISCUSSION

In developing estimates for Capital Plan purposes, departments are expected to request sufficient funding to complete their projects without the necessity for inflationary adjustments. In periods of low cost inflation this process would normally be expected to provide sufficient funding to complete projects as anticipated. However, the 2003 - 2005 Capital Plan includes several construction related projects that have faced significant cost increases since the initial estimates were developed for planning purposes in 2001/2002. A number of factors have resulted in these increases:

1. Taking project estimates from concept to design thereby refining the costs estimates to deliver the intended program.

2. Implementation of the City-wide DCL and its application to civic projects.

3. Significant increases in construction labour and materials costs.

These findings have been discussed by staff with development industry representatives and cost estimators, who confirm that in the last year alone projects have experienced cost escalation of up to 18 percent, well beyond that anticipated during the Capital Plan planning phase.

Capital Plan Staff Review Group Review

The Capital Plan Staff Review Group was convened to consider the funding shortfalls and the options available to provide sufficient funding to allow projects to proceed as provided for in the Capital Plan. This review considered all areas of the Capital Plan as well as the need to identify a source of funding for the Millennium Sports Facility capital grant approved by Council on January 27, 2004.

When faced with cost increases in the capital program, departments are required to look first for ways to offset the costs within the existing funding allocations. In areas of ongoing program expenditure, offsets can be achieved by altering or reducing the program. For projects with defined scope and funding, costs increases can be offset by reallocating funding within the capital plan or by reducing the scope of the projects, often leading to situations where the viability of the project or its ability to provide for the intended public service is threatened.

In reviewing the Capital Plan funding allocations, it was determined that:

Sewer and Water Program: the City Engineer will be able to complete the Sewer and Water capital programs without additional funding. Any funding adjustment necessary will be reported as part of future capital budgets.

Other Public Works: The balance of the Public Works portion of the Capital Plan includes expenditures for streets, street lighting, communications and yards. The City Engineer reports that there is sufficient funding within the existing allocation to complete the capital program in these areas. Any funding adjustment necessary will be reported as part of future capital budgets.

Community Services: This program includes contributions to the Affordable Housing Fund, funding for the Downtown Eastside and the capital grants program. These areas of the plan are not affected by cost increases.

Civic Facilities/Other: This portion of the Capital Plan includes funding for the proposed Police Training Facility, capital maintenance of other civic facilities and major maintenance and replacement of data and communications infrastructure and systems. These areas of the Capital Plan are either not far enough along in the planning process to estimate funding deficiencies or have sufficient funding to complete the anticipated program.

Park Board: With the exception of the two projects detailed below, the Park Board should be able to complete the projects within their Capital Plan, including the contemplated park development projects and the routine facilities projects. However, in order to complete the program, Park Board will be recommending a number of funding adjustments, including the allocation of additional City-wide DCL funding and the reallocation of tax-supported funding within the plan.

Projects Requiring Additional Funding

The Staff Review Group identified a number of projects where additional funding is required or original project expectations cannot be met. In addition, the Staff Review Group was asked to identify a funding source for the approved grant to the Millennium Sports Facility from within the existing Capital Plan funding envelope. The specific projects are listed below.

Project

Functional Area

Funding Shortfall

Mt Pleasant Civic Centre: 1 Kingsway

Parks, Library, Daycare

$3.8 - $4.6 million

Killarney Pool

Park Board

0.85 million

Queen Elizabeth Reservoir

Park Board

0.55 million

Millennium Sports Facility

Capital Grant

1.0 million

Sunset Community Centre

Park Board

$1.8 million

Total

 

$7.8 - $8.6 million

There are a number of sources of funding that can be utilized to offset these funding shortfalls without impacting on the balance of the program/project expenditures in the Plan. These include:

Recommended Funding Changes

The Staff Review Group recommends a combination of these funding options to address the shortfalls that have been identified.

1. Mount Pleasant Civic Centre: 1 Kingsway

In an accompanying report, the Director of Facilities Design and Management outlines the status of the 1 Kingsway project and seeks approval to proceed to the tender process. As noted in that report, if the project is to be completed as intended, there is a potential funding shortfall of up to $4.6 million.

The Staff Review Group has made the following recommendations with respect to project funding (summarized in the table):

Mt Pleasant Civic Centre
Revised Funding Allocations1

 

Existing Allocation

Reallocated/New Funding

Revised Funding

Borrowing Authority

13,175,000

0

13,175,000

City-Wide DCLs (daycare)

$1,300,000

1,500,000

2,800,000

Community Amenity Contributions
(community centre / library)

$2,000,000

 

2,000,000

GST Rebate
(project savings)

 

$500,000

500,000

GST Rebate
(Operating Budget)

0

2,000,000

2,000,000

 

16,475,000

2,500,000

20,475,000

1. In an upcoming report the Director of Current Planning is recommending the allocation of $100,000 in CAC funding from 950 Quebec/939 Main Street to the Mt Pleasant Civic Centre. This will bring the total funding available for the project to $20.575 million.

Should Council not approve the allocation of additional Operating Budget funding to the 1 Kingsway project, the alternative would be to provide the necessary funding from the $20 million of borrowing authority for cost shared projects. However, the Director of Finance believes that further commitment of these funds will not only result in an unnecessary increase in debenture debt but could also result in the City having difficulty funding its share of future approvals from the list of projects submitted to the Canada-BC Infrastructure Program.

Should the project requirements exceed the $20.575 million (see table and note above) once the tenders for the project are in place, the Director of Finance, in consultation with the Director of Facilities Design and Management will report back on options to further reduce the cost of the project or to provide additional funding.

2. Park Board: Funding for Killarney Pool and Queen Elizabeth Park Reservoir

The Park Board requires additional funding of $1,375,000 for two projects. Council has already adjusted funding for the Dr. Sun Yat Sen Garden project by $13,000 to account for the costs of City-wide DCLs payable on the project.

The Staff Review Group recommends that the additional funding be provided by a combination of new funds and the reallocation of existing funding within the Park Board capital plan, as follows:

Park Board Capital
Capital Plan Funding Adjustments

Funding Area

Existing Allocation

Reallocated/ New Funding

Comments

Killarney Pool

$8,900,000

$825,000

    · Construction cost increases
    · City-wide DCL costs

Queen Elizabeth Park Reservoir

3,400,000

550,000

    · Construction cost increases

Recreation Facilities

 

(602,900)

    · Reallocation of existing tax supported funding, including GST rebates
    · Allocation of project surpluses

Park Development

 

(772,100)

    · Reallocation of existing tax supported funding, including GST rebates
    · New City-wide DCL funding

Net Adjustment

 

$ 0

 

3. Park Board: Millennium Sports Facility

As noted above, Council approved a grant of up to $1.18 million to allow construction of the Millennium Sports Facility to proceed. With the delay in implementing the full city-wide DCL until July 1, 2004, the anticipated DCL costs of this project have been reduced to $170,300 bringing the maximum amount of the grant to $1,000,000.

As this project is funded approximately 70% by outside funders, the Staff Review Group recommends that Council access the $20 million in borrowing authority for cost shared projects approved by the voters in November 2002 for the civic share.

4. Park Board: Sunset Community Centre

Sunset Community Centre was identified by the Park Board as the highest priority for replacement during the planning for the 2003-2005 Capital Plan. However, because of other demands on the Plan, including the need to complete the Mt Pleasant Community Centre replacement, no funding in the base plan was recommended. Instead, Council agreed to allocate a $3.0 million City contribution to be funded from the $20 million of borrowing authority for cost shared projects, subject to contributions from the Federal and Provincial governments to the replacement project.

The Canada/British Columbia infrastructure program has now awarded $4.0 million toward replacement of Sunset Community Centre. The application was based on a 30,000 square foot Community Centre to be built to the LEED Silver standard. An architect has recently been retained to begin design work and the project is estimated to be ready for tender in the spring of 2005. At that time a cost estimate will be available that more accurately reflects the effects of the costs of completing the project as submitted to the Infrastructure Program.

The project team will be instructed to design a 30,000 square feet, LEED Silver community centre to current Park Board quality specifications. It is anticipated that a request will come forward to Council in early 2005 to provide the balance between the $7,000,000 currently allocated ($3.0 million City / $4.0 million Infrastructure Program) and the actual project cost. Depending on actual cost escalation in the year ahead this could possibly require additional funding of between $2 and $3 million to complete the project as envisioned.

No Council action related to funding for the Sunset Community Centre replacement is necessary at this time. However, Council is being asked to confirm its commitment to the original project scope - and the anticipation of increased costs - prior to further design work proceeding.

FINANCIAL IMPLICATIONS

There are a number of financial implications associated with the recommendations of this report:

CONCLUSION

A number of factors including the application of city-wide DCL costs, the process of taking projects to final design and the significant escalation of construction costs have resulted in under-funding of several major construction projects in the 2003-2005 Capital Plan. Without the identification of additional funding, these projects could not be completed as intended affecting the delivery of public services. The recommendation in this report attempt to find a balance between identifying funding within the existing capital expenditure envelope, committing additional tax supported funding (capital from revenue and debenture borrowing), and accessing other City funding resources (City-wide DCLs).

- - - - -

APPENDIX A
PAGE 1 OF 1

* * * * *


ag20040420.htm